3215 S BOAZ ST 90011
Certificate Information: 3215 S BOAZ ST 90011
- Application / Permit
- 19014-20000-05832
- Plan Check / Job No.
- B19VN18523
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 24' X 18' ADDITION TO (E) SFD TO CREATE A NEW (2) BEDROOMS , (1) BATHROOM AND HALLWAY, ALL WORK PER WFPP
- Permit Issued
- Issued on 12/21/2020
- Issuing Office
- Current Status
- CofO Issued on 3/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/25/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/25/2019 | RARES BODEA |
| Corrections Issued | 10/25/2019 | RARES BODEA |
| Applicant returned to address corrections | 2/27/2020 | HAYATO TSUCHIYA |
| Plan Check Approved | 11/16/2020 | PINANK PATEL |
| Issued | 12/21/2020 | APPLICANT |
| CofO in Progress | 3/23/2024 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 3/29/2024 | DEROLD HAUFF |
| CofO Issued | 3/29/2024 | DEROLD HAUFF |
| Permit Finaled | 3/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Housing rent stabilization | Cleared | 11/20/2019 | CHARLES GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 12/5/2019 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 12/5/2019 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 12/5/2019 | MARKOS PEREZ-BRAN |
| Community Plan Implem. Overlay | Cleared | 1/7/2020 | HELEN JADALI |
| Community Plan Implem. Overlay | Cleared | 1/7/2020 | HELEN JADALI |
| Project located in CRA area | Cleared | 1/30/2020 | GRACIELA ACOSTA |
Contact Information
| Contractor | Ochoa Victor Manuel; Lic. No.: 908306-B | 13700 FOOTHILL BLVD #920151 SYLMAR, CA 91342 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/11/2021 | Corrections Issued | SCOTT FINNILA |
| Pre-Inspection | 3/10/2021 | Approved | FREDDIE RIVERA |
| Footing/Foundation/Slab | 6/10/2021 | Corrections Issued | FREDDIE RIVERA |
| Deputy Drilled-In Anchors | 6/11/2021 | No Access for Inspection | ELMER BLAND |
| Footing/Foundation/Slab | 3/9/2022 | Approved | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2022 | Corrections Issued | HORACE FULTZ |
| PLUMBING-Rough | 4/1/2022 | Corrections Issued | HORACE FULTZ |
| Rough-Elec/Plmb/HVAC | 4/1/2022 | Not Ready for Inspection | HORACE FULTZ |
| PLUMBING-Rough | 4/5/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Wood Frame | 4/5/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Deputy Drilled-In Anchors | 4/6/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Deputy Other (see comments) | 4/6/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 4/7/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Wood Frame | 4/7/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Insulation | 4/12/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Insulation | 4/14/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2022 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 5/12/2022 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Rough | 5/12/2022 | Approved | JOAQUIN GREENOUGH |
| Green Building Rough | 5/12/2022 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 5/12/2022 | Approved | JOAQUIN GREENOUGH |
| Insulation | 6/9/2022 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 6/23/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 6/23/2022 | Approved | JOAQUIN GREENOUGH |
| Shower Pan | 7/6/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Shower Pan | 7/11/2022 | Approved | JOAQUIN GREENOUGH |
| Shower Pan | 7/27/2022 | Approved | JOAQUIN GREENOUGH |
| Final | 11/8/2022 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 11/8/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 11/8/2022 | SGSOV Not Ready | LILIANA PORTILLO |
| Smoke Detectors | 11/8/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 1/3/2023 | Corrections Issued | BRENDAN MORELLI |
| Green Building Final | 1/3/2023 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 1/3/2023 | SGSOV Approved | BRENDAN MORELLI |
| Smoke Detectors | 1/3/2023 | Approved | BRENDAN MORELLI |
| Final | 2/22/2023 | Corrections Issued | BRENDAN MORELLI |
| ELECTRICAL-Final | 8/31/2023 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 2/13/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 2/23/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 3/20/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 3/20/2024 | Approved | ALEJANDRO DE ARTOLA |
| Final | 3/22/2024 | OK to Issue CofO | ALEJANDRO DE ARTOLA |