1958 N AVON ST 90026

Certificate Information: 1958 N AVON ST 90026

Application / Permit
19014-20000-05828
Plan Check / Job No.
B19VN18516
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel kitchen/bathrooms, expand 24'9" x 13'10" over roof deck of attached garage and create 8.5' x 13.8' attached patio cover below, add 20' x 24.5' to the rear for master bed/bath room, laundry closet and den . All works are per design. See comment
Permit Issued
Issued on 5/4/2020
Issuing Office
Current Status
CofO Issued on 2/25/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/25/2019 APPLICANT
Assigned to Plan Check Engineer 10/31/2019 ALDOUS CHIC
Corrections Issued 11/4/2019 ALDOUS CHIC
Quality Review Completed 11/5/2019 ABDUL CHEGENI
Building Plans Picked Up 12/6/2019 APPLICANT
Green Plans Picked Up 12/6/2019 APPLICANT
Applicant returned to address corrections 3/12/2020 ALDOUS CHIC
Plan Check Approved 4/13/2020 ALDOUS CHIC
Issued 5/4/2020 APPLICANT
CofO in Progress 2/3/2021 KATHRYN BUTTERWORTH
Permit Finaled 2/25/2021 DEROLD HAUFF
CofO Issued 2/25/2021 DEROLD HAUFF
Permit Finaled 2/25/2021 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/28/2019 ALDOUS CHIC
GPI Written Notices Cleared 11/2/2019 ALDOUS CHIC
Eng Process Fee Ord 176,300 Cleared 2/3/2020 GUILLERMO PETRA
Sewer availability Cleared 2/3/2020 GUILLERMO PETRA
Low Impact Development Cleared 2/5/2020 ORVAL HERNANDEZ-MARCIAL
Roof/Waste drainage to street Cleared 2/5/2020 THOMAS LANG
Green Code Cleared 3/4/2020 DAVID MATSON

Contact Information

Contractor Resourceful Construction Inc; Lic. No.: 1003215-B P O BOX 5899      GLENDALE, CA 91221
Engineer Espino,, Manuel A; Lic. No.: C55526 12109 WOODRUFF AVE      DOWNEY, CA 90241
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107
Geologist Irvine,, Jon A; Lic. No.: EG1691 819 W HERITAGE OAK CT      ALTADENA, CA 91001

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/29/2020 Approved ENRIQUE MIRELES
Piling/Pier/Caisson 5/29/2020 Partial Approval ENRIQUE MIRELES
Piling/Pier/Caisson 6/9/2020 Partial Approval RUBEN SALAS
Special/Order Compliance 6/15/2020 Corrections Issued RUBEN SALAS
Special/Order Compliance 6/17/2020 Approved RUBEN SALAS
Special/Order Compliance 6/22/2020 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 7/16/2020 Not Ready for Inspection DAVID CHAN
Interior/Exterior Lathing 8/3/2020 Not Ready for Inspection STUART CHAPMAN
Shower Pan 8/3/2020 Corrections Issued STUART CHAPMAN
BUILDING-Rough-Frame 8/4/2020 Partial Approval DAVID CHAN
Interior/Exterior Lathing 8/4/2020 Approved DAVID CHAN
BUILDING-Rough-Frame 8/11/2020 Conditional Approval DAVID CHAN
ELECTRICAL-Rough 8/11/2020 Approved DAVID CHAN
HVAC-Rough 8/11/2020 Approved DAVID CHAN
PLUMBING-Rough 8/11/2020 Approved DAVID CHAN
BUILDING-Rough-Frame 8/17/2020 Not Ready for Inspection JOSEPH MCGARRY
Green Building Rough 8/17/2020 Approved JOSEPH MCGARRY
Verify Sprinkler Sign Off 8/17/2020 Not Ready for Inspection JOSEPH MCGARRY
Insulation 9/15/2020 Approved DAVID CHAN
Drywall Nailing 9/21/2020 Conditional Approval HAMIK HARTOUNIAN
Special/Order Compliance 11/4/2020 Corrections Issued RUBEN SALAS
Special/Order Compliance 11/9/2020 Corrections Issued RUBEN SALAS
Special/Order Compliance 11/19/2020 Corrections Issued STUART CHAPMAN
Final 11/23/2020 Not Ready for Inspection DAVID CHAN
Gas Test 11/23/2020 Approved DAVID CHAN
Green Building Final 11/23/2020 Not Ready for Inspection DAVID CHAN
SGSOV-Seismic Gas S/O Valve 11/23/2020 SGSOV Not Ready DAVID CHAN
Smoke Detectors 11/23/2020 Not Ready for Inspection DAVID CHAN
Verify Sprinkler Sign Off 11/23/2020 Not Ready for Inspection DAVID CHAN
Special/Order Compliance 12/1/2020 Order to Comply Issued STUART CHAPMAN
ELECTRICAL-Final 12/11/2020 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Final 12/11/2020 Approved HAMIK HARTOUNIAN
PLUMBING-Final 12/11/2020 Approved HAMIK HARTOUNIAN
Final 12/21/2020 Corrections Issued DAVID CHAN
BUILDING-Rough-Frame 12/23/2020 Not Ready for Inspection ROBERT VORHIS
Drywall Nailing 12/23/2020 Not Ready for Inspection ROBERT VORHIS
Green Building Final 12/23/2020 Not Ready for Inspection ROBERT VORHIS
SGSOV-Seismic Gas S/O Valve 12/23/2020 SGSOV Not Ready ROBERT VORHIS
Smoke Detectors 12/23/2020 Not Ready for Inspection ROBERT VORHIS
Verify Sprinkler Sign Off 12/23/2020 Not Ready for Inspection ROBERT VORHIS
BUILDING-Rough-Frame 1/28/2021 Approved KATHRYN BUTTERWORTH
Drywall Nailing 1/28/2021 Approved KATHRYN BUTTERWORTH
Final 1/28/2021 OK to Issue CofO KATHRYN BUTTERWORTH
Green Building Final 1/28/2021 Approved KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 1/28/2021 SGSOV Approved KATHRYN BUTTERWORTH
Smoke Detectors 1/28/2021 Approved KATHRYN BUTTERWORTH
Verify Sprinkler Sign Off 1/28/2021 Approved KATHRYN BUTTERWORTH
Special/Order Compliance 2/3/2021 Approved STUART CHAPMAN
Special/Order Compliance 2/22/2021 Partial Inspection ROBERT VORHIS