11009 W DORA ST 91352
Certificate Information: 11009 W DORA ST 91352
- Application / Permit
- 19014-20000-05824
- Plan Check / Job No.
- B19VN18512
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD IRREGULAR SHAPED 28'-2.5" x 26'-6" TO AND CONVERT (E) 20' X 18'4" DETACHED GARAGE TO ACCESSORY DWELLING UNIT AS PER AB 494 AND SB 229, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 10/30/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2019 | RARES BODEA |
| Corrections Issued | 10/28/2019 | RARES BODEA |
| Plan Check Approved | 10/30/2019 | SARKIS HARABEDIAN |
| Issued | 10/30/2019 | LADBS |
| CofO in Progress | 3/10/2021 | BEAU COLLINS |
| Permit Finaled | 4/29/2021 | MICHAEL SMITH |
| CofO Issued | 4/29/2021 | MICHAEL SMITH |
| Permit Finaled | 4/29/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 10/28/2019 | APEKSHYA BAJRACHARYA |
| Permit | Cleared | 10/28/2019 | APEKSHYA BAJRACHARYA |
| Eng Process Fee Ord 176,300 | Cleared | 10/29/2019 | CELINA MORENO |
| Sewer availability | Cleared | 10/29/2019 | CELINA MORENO |
| Trees in Parkway | Cleared | 10/29/2019 | JOHN KIM |
| Low Impact Development | Cleared | 10/30/2019 | MARTIN FRAGOSO |
| Roof/Waste drainage to street | Cleared | 10/30/2019 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Singh,, Jasbir; Lic. No.: C38767 | 16194 EASTRIDGE CT CHINO HILLS, CA 91709 |
Inspector Information
| DAVID ANDERSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 1/7/2020 | Corrections Issued | BEAU COLLINS |
| Footing/Foundation/Slab | 1/27/2020 | Not Ready for Inspection | BEAU COLLINS |
| Footing/Foundation/Slab | 2/3/2020 | Approved | BEAU COLLINS |
| BUILDING-Rough-Frame | 3/2/2020 | Conditional Approval | BEAU COLLINS |
| Green Building Rough | 3/2/2020 | Not Ready for Inspection | BEAU COLLINS |
| BUILDING-Rough-Frame | 4/30/2020 | Corrections Issued | BEAU COLLINS |
| ELECTRICAL-Rough | 4/30/2020 | Not Ready for Inspection | BEAU COLLINS |
| Green Building Rough | 5/19/2020 | Not Ready for Inspection | BEAU COLLINS |
| Interior/Exterior Lathing | 5/19/2020 | Partial Approval | BEAU COLLINS |
| PLUMBING-Rough | 5/19/2020 | Not Ready for Inspection | BEAU COLLINS |
| BUILDING-Rough-Frame | 6/9/2020 | Approved | BEAU COLLINS |
| Green Building Rough | 6/9/2020 | Approved | BEAU COLLINS |
| HVAC-Rough | 6/9/2020 | Approved | BEAU COLLINS |
| PLUMBING-Rough | 6/9/2020 | Approved | BEAU COLLINS |
| Insulation | 6/22/2020 | Approved | PIERRE VEGA |
| Interior/Exterior Lathing | 6/22/2020 | Approved | PIERRE VEGA |
| Drywall Nailing | 7/1/2020 | Approved | BEAU COLLINS |
| Final | 11/4/2020 | Corrections Issued | BEAU COLLINS |
| Green Building Final | 11/4/2020 | Not Ready for Inspection | BEAU COLLINS |
| SGSOV-Seismic Gas S/O Valve | 11/4/2020 | SGSOV Not Ready | BEAU COLLINS |
| Smoke Detectors | 11/4/2020 | Approved | BEAU COLLINS |
| Final | 11/30/2020 | Corrections Issued | BEAU COLLINS |
| Green Building Final | 11/30/2020 | Not Ready for Inspection | BEAU COLLINS |
| SGSOV-Seismic Gas S/O Valve | 11/30/2020 | SGSOV Not Ready | BEAU COLLINS |
| Final | 12/10/2020 | Not Ready for Inspection | BEAU COLLINS |
| SGSOV-Seismic Gas S/O Valve | 12/10/2020 | SGSOV Not Ready | BEAU COLLINS |
| SGSOV-Seismic Gas S/O Valve | 12/16/2020 | SGSOV Not Ready | BEAU COLLINS |
| Final | 2/25/2021 | Corrections Issued | BEAU COLLINS |
| Green Building Final | 2/25/2021 | Not Ready for Inspection | BEAU COLLINS |
| SGSOV-Seismic Gas S/O Valve | 2/25/2021 | SGSOV Approved | BEAU COLLINS |
| Special/Order Compliance | 3/2/2021 | Corrections Issued | BEAU COLLINS |
| Final | 3/5/2021 | Corrections Issued | BEAU COLLINS |
| Green Building Final | 3/5/2021 | Not Ready for Inspection | BEAU COLLINS |
| Pre-Inspection | 3/9/2021 | Not Ready for Inspection | BEAU COLLINS |
| Final | 3/11/2021 | OK to Issue CofO | BEAU COLLINS |
| Green Building Final | 3/11/2021 | Approved | BEAU COLLINS |