4746 N KRAFT AVE 91602

Certificate Information: 4746 N KRAFT AVE 91602

Application / Permit
19014-20000-05802
Plan Check / Job No.
B19VN18451
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
IRREGULAR ADDITION OF 10'6" X 14' 2" TO (E) SINGLE FAMILY DWELLING AND CONVERSION OF (E) KITCHEN TO BEDROOM See Comments
Permit Issued
Issued on 5/4/2020
Issuing Office
Valley
Current Status
CofO Issued on 10/9/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/24/2019 APPLICANT
Assigned to Plan Check Engineer 10/24/2019 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 10/24/2019 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 4/8/2020 YAQUB MIRZA
Issued 5/4/2020 LADBS
CofO in Progress 10/7/2021 WILLIAM KUEHN
CofO Issued 10/9/2021 MICHAEL SMITH
Permit Finaled 10/9/2021 MICHAEL SMITH

Permit Application Clearance Information

Specific Plan Cleared 3/23/2020 OLGA AYALA
Eng Process Fee Ord 176,300 Cleared 3/31/2020 GUILLERMO PETRA
Roof/Waste drainage to street Cleared 3/31/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor Voskanian Razmik Thomas; Lic. No.: 909850-B 2330 N SPARKS STREET      BURBANK, CA 91504
Engineer Khatchadourian,, Vicken; Lic. No.: S3141 1221 N CEDAR ST      GLENDALE, CA 92107

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/5/2020 Partial Approval GREGG CUMMINGS
Footing/Foundation/Slab 5/6/2020 Approved JEFFREY PARD
Excavation/Setback/Form/Re-Bar 5/15/2020 Partial Approval JEFFREY PARD
Wood Frame 5/21/2020 Corrections Issued JEFFREY PARD
BUILDING-Rough-Frame 5/26/2020 Approved JEFFREY PARD
Green Building Rough 5/26/2020 Approved JEFFREY PARD
MERV13>=Rough 5/26/2020 Approved JEFFREY PARD
HVAC-Rough 5/28/2020 Corrections Issued JEFFREY PARD
Insulation 6/2/2020 Approved JEFFREY PARD
Interior/Exterior Lathing 6/2/2020 Not Ready for Inspection JEFFREY PARD
Interior/Exterior Lathing 6/4/2020 Approved JEFFREY PARD
Drywall Nailing 6/9/2020 Not Ready for Inspection JEFFREY PARD
HVAC-Rough 6/24/2020 Corrections Issued THOMAS FINNILA
Insulation 6/24/2020 Approved THOMAS FINNILA
Interior/Exterior Lathing 11/30/2020 Partial Approval THOMAS FINNILA
Shower Pan 11/30/2020 Approved THOMAS FINNILA
Drywall Nailing 9/1/2021 Approved THOMAS FINNILA
ELECTRICAL-Final 9/1/2021 Not Ready for Inspection THOMAS FINNILA
Final 9/1/2021 Not Ready for Inspection THOMAS FINNILA
HVAC-Final 9/1/2021 Corrections Issued THOMAS FINNILA
PLUMBING-Final 9/1/2021 Approved THOMAS FINNILA
ELECTRICAL-Final 10/4/2021 Not Ready for Inspection MATTHEW NELSON
Final 10/4/2021 Partial Inspection MATTHEW NELSON
Green Building Final 10/4/2021 Not Ready for Inspection MATTHEW NELSON
HVAC-Final 10/4/2021 Approved MATTHEW NELSON
MERV13>=Final 10/4/2021 Approved MATTHEW NELSON
PLUMBING-Final 10/4/2021 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 10/4/2021 SGSOV Approved MATTHEW NELSON
Smoke Detectors 10/4/2021 Approved MATTHEW NELSON
Final 10/6/2021 OK to Issue CofO WILLIAM KUEHN
Green Building Final 10/6/2021 Approved WILLIAM KUEHN