317 N KINGS ROAD 90048

Certificate Information: 317 N KINGS ROAD 90048

Application / Permit
19014-20000-05777
Plan Check / Job No.
B19VN18321
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
21' 8" X 3' FIRST FLOOR ADDITION TO SOUTH, 27' 3" X 17' 4" IRR.-SHAPE FIRST FLOOR ADDITION TO WEST, 5' 9" X 11' STAIRS ADDITION AND INTERIOR REMODEL TO ADD (2) BATHROOMS AND RELOCATE (1) BATHROOM TO (E) SINGLE FAMILY DWELLING. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 1/29/2020
Issuing Office
Valley
Current Status
CofO Issued on 2/23/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/23/2019 APPLICANT
Assigned to Plan Check Engineer 10/31/2019 GURUNATH NESARAJAH
Corrections Issued 11/6/2019 GURUNATH NESARAJAH
Quality Review Completed 11/7/2019 GUANG MIN TUNG
Building Plans Picked Up 11/8/2019 APPLICANT
Green Plans Picked Up 11/8/2019 APPLICANT
Plan Check Approved 1/29/2020 GURUNATH NESARAJAH
Issued 1/29/2020 LADBS
CofO in Progress 2/18/2021 CHRIS CHRISTENSEN
No Progress 2/19/2021 CHRIS CHRISTENSEN
CofO in Progress 2/19/2021 CHRIS CHRISTENSEN
Permit Finaled 2/23/2021 DEROLD HAUFF
CofO Issued 2/23/2021 DEROLD HAUFF
Permit Finaled 2/23/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/3/2020 THOMAS LANG
Roof/Waste drainage to street Cleared 1/3/2020 THOMAS LANG
Sewer availability Cleared 1/3/2020 THOMAS LANG
ZA Case Cleared 1/3/2020 SOPHIE GABEL-SCHEINBAU
ZI Cleared 1/3/2020 SOPHIE GABEL-SCHEINBAU
Green Code Cleared 1/16/2020 AARON COSTA

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia, Zelada, Eddy Alexander; Lic. No.: S6159 17958 LULL ST      RESEDA, CA 91335

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/17/2020 Partial Approval CHRIS CHRISTENSEN
METHANE-Barrier 4/17/2020 Approved CHRIS CHRISTENSEN
METHANE-Subgrade 4/17/2020 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 5/12/2020 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 6/22/2020 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 7/31/2020 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 7/31/2020 Approved CHRIS CHRISTENSEN
ELECTRICAL-Rough 8/5/2020 Approved JOSEPH MCGARRY
HVAC-Rough 8/5/2020 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 8/7/2020 Approved ARTHUR SARGSYAN
Green Building Rough 8/7/2020 Approved ARTHUR SARGSYAN
Interior/Exterior Lathing 8/7/2020 Approved ARTHUR SARGSYAN
METHANE-Rough 8/7/2020 Approved ARTHUR SARGSYAN
Shower Pan 8/12/2020 Corrections Issued THOMAS LOGRASSO
Drywall Nailing 8/31/2020 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 9/25/2020 Approved CHRIS CHRISTENSEN
Shower Pan 9/25/2020 Approved CHRIS CHRISTENSEN
ELECTRICAL-Final 10/16/2020 Approved CHRIS CHRISTENSEN
HVAC-Final 11/23/2020 Corrections Issued JOSEPH MCGARRY
PLUMBING-Final 11/23/2020 Partial Approval JOSEPH MCGARRY
Final 1/22/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Footing/Foundation/Slab 1/22/2021 Approved CHRIS CHRISTENSEN
Green Building Final 1/22/2021 Approved CHRIS CHRISTENSEN
HVAC-Final 1/22/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Final 1/22/2021 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 1/22/2021 SGSOV Approved CHRIS CHRISTENSEN
Smoke Detectors 1/22/2021 Approved CHRIS CHRISTENSEN
Final 2/17/2021 OK to Issue CofO CHRIS CHRISTENSEN