8553-8555 N ELIZALDE AVE 91324

Certificate Information: 8553-8555 N ELIZALDE AVE 91324

Application / Permit
19014-20000-05750
Plan Check / Job No.
B19VN18229
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 18' X 18'-6" TO AND CONVERT 9' X 17'-6" PORTION OF GARAGE TO ACCESSORY DWELLING UNIT PER AB494 AND SB229; ADD 9' X 17'-6" TO EXISTING GARAGE
Permit Issued
Issued on 11/13/2019
Issuing Office
Valley
Current Status
Issued on 11/13/2019
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/22/2019 APPLICANT
Assigned to Plan Check Engineer 10/22/2019 SELLA BENYAMIN
Corrections Issued 10/23/2019 SELLA BENYAMIN
Building Plans Picked Up 10/25/2019 APPLICANT
Plan Check Approved 11/13/2019 SELLA BENYAMIN
Issued 11/13/2019 LADBS

Permit Application Clearance Information

Address approval Cleared 11/1/2019 SAFA JAVANMARDI
Eng Process Fee Ord 176,300 Cleared 11/1/2019 SAFA JAVANMARDI
Roof/Waste drainage to street Cleared 11/1/2019 SAFA JAVANMARDI
Sewer availability Cleared 11/1/2019 SAFA JAVANMARDI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/21/2020 Approved DONALD SUNSERI
PLUMBING-Rough 4/22/2020 Partial Approval JOHN KIDWELL
Footing/Foundation/Slab 5/14/2020 Approved VINCENT HANLEY
BUILDING-Rough-Frame 8/28/2020 Partial Approval JEFFREY PARD
ELECTRICAL-Rough 8/28/2020 Not Ready for Inspection JEFFREY PARD
Floor/Roof Diaphrgm/Shear Wall 8/28/2020 Partial Approval JEFFREY PARD
Green Building Rough 8/28/2020 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 8/28/2020 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 11/23/2020 Approved JEFFREY PARD
Wood Frame 11/23/2020 Partial Approval JEFFREY PARD
ELECTRICAL-Rough 12/28/2021 Not Ready for Inspection JEFFREY PARD
PLUMBING-Rough 12/28/2021 Not Ready for Inspection JEFFREY PARD
Wood Frame 12/28/2021 Corrections Issued JEFFREY PARD
Pre-Inspection 6/17/2022 Partial Approval JEFFREY PARD
ELECTRICAL-Rough 1/4/2023 Approved JOHN KIDWELL
Special/Order Compliance 1/4/2023 Partial Inspection MORRIS JACKSON
Pre-Inspection 6/11/2024 Partial Inspection KRISTEN CAUSEY
Interior/Exterior Lathing 11/13/2024 Not Ready for Inspection KRISTEN CAUSEY
Interior/Exterior Lathing 11/15/2024 Partial Approval KRISTEN CAUSEY
Rough-Elec/Plmb/HVAC 4/15/2025 Corrections Issued KRISTEN CAUSEY
Underground Mechanical 4/17/2025 Approved DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 4/30/2025 Not Ready for Inspection KRISTEN CAUSEY
Special/Order Compliance 5/6/2025 Corrections Issued HENRY KIM