5642 N VARNA AVE 91401
Certificate Information: 5642 N VARNA AVE 91401
- Application / Permit
- 19014-20000-05745
- Plan Check / Job No.
- B19VN18222
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- MAJOR REMODEL AND ADDITION OF IRREGULAR SHAPE 35' 3" X 30' 5" TO REAR OF (E) SFD All WORK PER ENGINEERING DESIGN FIRE SPRINKLER NFPA 13D REQUIRED
- Permit Issued
- Issued on 7/31/2024
- Issuing Office
- Current Status
- CofO Issued on 6/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/22/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2019 | GURUNATH NESARAJAH |
| Corrections Issued | 10/22/2019 | GURUNATH NESARAJAH |
| Applicant returned to address corrections | 7/19/2024 | ISIS ARGUETA |
| Applicant returned to address corrections | 7/29/2024 | MOHAMMAD ESMAILI |
| Issued | 7/31/2024 | APPLICANT |
| CofO in Progress | 5/21/2025 | RYAN SALAZAR |
| Permit Finaled | 6/5/2025 | RUBEN SALAS |
| CofO Issued | 6/5/2025 | RUBEN SALAS |
| Permit Finaled | 6/5/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Low Impact Development | Cleared | 7/11/2022 | MARCO SANCHEZ |
| Sewer availability | Cleared | 7/14/2022 | MEGAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/27/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 6/27/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/13/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Footing/Foundation/Slab | 9/13/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Pre-Inspection | 9/13/2024 | Partial Inspection | RYAN SALAZAR |
| BUILDING-Rough-Frame | 12/6/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Drywall Nailing | 12/6/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Final | 12/6/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Footing/Foundation/Slab | 12/6/2024 | Approved | RYAN SALAZAR |
| Green Building Final | 12/6/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Rough | 12/6/2024 | Not Ready for Inspection | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 12/6/2024 | SGSOV Not Ready | RYAN SALAZAR |
| Smoke Detectors | 12/6/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Green Building Rough | 12/16/2024 | Approved | RYAN SALAZAR |
| Rough-Elec/Plmb/HVAC | 12/16/2024 | Approved | RYAN SALAZAR |
| Rough-Elec/Plmb/HVAC | 1/7/2025 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 1/15/2025 | Approved | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2025 | Approved | RYAN SALAZAR |
| Insulation | 1/15/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 1/15/2025 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 1/22/2025 | Approved | RYAN SALAZAR |
| Final | 1/24/2025 | Partial Inspection | RYAN SALAZAR |
| Green Building Final | 1/24/2025 | Partial Inspection | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 1/24/2025 | SGSOV Approved | RYAN SALAZAR |
| Smoke Detectors | 1/24/2025 | Approved | RYAN SALAZAR |
| Final | 2/20/2025 | Partial Approval | RYAN SALAZAR |
| Green Building Final | 2/20/2025 | Approved | RYAN SALAZAR |
| Final | 5/22/2025 | OK to Issue CofO | RYAN SALAZAR |