Certificate Information: 7155 N OAKDALE AVE 91306

Application / Permit
19014-20000-05726
Plan Check / Job No.
B19VN18125
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 11' 7" X 7' PORTION OF (E) GARAGE TO STORAGE, CONVERT 21' X 30' IRR.-SHAPE PORTION OF (E) GARAGE TO ACCESSORY DWELLING UNIT AND ADD 18' 4" X 30' IRR.-SHAPE 2ND FLOOR TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 7/14/2021
Issuing Office
Current Status
CofO Issued on 3/25/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/21/2019 APPLICANT
Green Plans Picked Up 10/29/2019 APPLICANT
Assigned to Plan Check Engineer 10/31/2019 GURUNATH NESARAJAH
Corrections Issued 11/5/2019 GURUNATH NESARAJAH
Quality Review Completed 11/8/2019 GUANG MIN TUNG
Application Withdrawn-Void 9/15/2020 ALDO UBAU
Re-Activate Application 9/21/2020 ALDO UBAU
Plan Check Approved 6/13/2021 GURUNATH NESARAJAH
Issued 7/14/2021 APPLICANT
Building Plans Picked Up 10/12/2021 APPLICANT
CofO in Progress 3/24/2022 STEVEN BACK
Permit Finaled 3/25/2022 JOHN JANSON
CofO Issued 3/25/2022 JOHN JANSON
Permit Finaled 3/25/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 1/17/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 1/17/2020 ADRIAN CASTRO
Permit Cleared 1/17/2020 ADRIAN CASTRO
Sewer availability Cleared 1/17/2020 ADRIAN CASTRO
ZI Cleared 2/4/2020 PABLO ESTRADA
Green Code Cleared 3/9/2020 AARON COSTA
Trees in Parkway Cleared 3/13/2020 JOHN KIM
Low Impact Development Cleared 5/29/2021 ORVAL HERNANDEZ-MARCI
Low Impact Development Cleared 5/29/2021 ORVAL HERNANDEZ-MARCI

Contact Information

Contractor Eco Home Builders; Lic. No.: 1018718-B PO BOX 14      SUN VALLEY, CA 91353
Engineer Rodriguez,, Jacob; Lic. No.: S5084 8206 ENCINO AVE      NORTHRIDGE, CA 91325

Inspector Information

ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/22/2021 Approved HENRY KIM
Pre-Inspection 10/18/2021 Partial Approval STEVEN BACK
Footing/Foundation/Slab 10/28/2021 Corrections Issued HENRY KIM
BUILDING-Rough-Frame 11/2/2021 Partial Approval STEVEN BACK
ELECTRICAL-Rough 11/2/2021 Not Ready for Inspection STEVEN BACK
Footing/Foundation/Slab 11/2/2021 Approved STEVEN BACK
Green Building Rough 11/2/2021 Not Ready for Inspection STEVEN BACK
PLUMBING-Rough 11/2/2021 Not Ready for Inspection STEVEN BACK
BUILDING-Rough-Frame 11/15/2021 Partial Approval STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 11/15/2021 Not Ready for Inspection STEVEN BACK
Green Building Rough 11/15/2021 Not Ready for Inspection STEVEN BACK
PLUMBING-Rough 11/15/2021 Approved STEVEN BACK
Deputy Wood Construction 12/20/2021 Conditional Approval STEVEN BACK
BUILDING-Rough-Frame 12/21/2021 Corrections Issued STEVEN BACK
Floor/Roof Diaphrgm/Shear Wall 12/21/2021 Approved STEVEN BACK
BUILDING-Rough-Frame 1/4/2022 Not Ready for Inspection PETER FOLLING
ELECTRICAL-Rough 1/4/2022 Approved PETER FOLLING
Green Building Rough 1/4/2022 Not Ready for Inspection PETER FOLLING
HVAC-Rough 1/4/2022 Approved PETER FOLLING
PLUMBING-Rough 1/4/2022 Approved PETER FOLLING
BUILDING-Rough-Frame 1/7/2022 Corrections Issued STEVEN BACK
Green Building Rough 1/7/2022 Approved STEVEN BACK
Interior/Exterior Lathing 1/7/2022 Partial Approval STEVEN BACK
BUILDING-Rough-Frame 1/11/2022 Approved STEVEN BACK
Insulation 1/11/2022 Approved STEVEN BACK
Drywall Nailing 1/18/2022 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 1/18/2022 Approved JUSTIN HAWLEY
Final 2/23/2022 Corrections Issued JEFFREY PARD
Green Building Final 2/23/2022 Corrections Issued JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 2/23/2022 SGSOV Approved JEFFREY PARD
Smoke Detectors 2/23/2022 Approved JEFFREY PARD
Final 3/15/2022 Corrections Issued STEVEN BACK
Green Building Final 3/15/2022 Approved STEVEN BACK
Final 3/24/2022 OK to Issue CofO STEVEN BACK
SGSOV-Seismic Gas S/O Valve 3/24/2022 SGSOV Approved STEVEN BACK
Service/Power Release 3/24/2022 Approved STEVEN BACK