8308 S MCCONNELL AVE 90045

Certificate Information: 8308 S MCCONNELL AVE 90045

Application / Permit
19014-20000-05698
Plan Check / Job No.
B19VN18004
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL AND ADDITION TO EXISTING SINGLE FAMILY DWELLING; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 6/12/2020
Issuing Office
Current Status
CofO Issued on 3/22/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2019 APPLICANT
Assigned to Plan Check Engineer 10/31/2019 SELLA BENYAMIN
Corrections Issued 11/4/2019 SELLA BENYAMIN
Quality Review Completed 11/5/2019 STEVEN KIM
Building Plans Picked Up 11/5/2019 APPLICANT
Green Plans Picked Up 11/5/2019 APPLICANT
Applicant returned to address corrections 4/20/2020 SELLA BENYAMIN
Applicant returned to address corrections 5/19/2020 SELLA BENYAMIN
Plan Check Approved 5/21/2020 SELLA BENYAMIN
Issued 6/12/2020 APPLICANT
CofO in Progress 3/15/2022 BOBBY KEY
Permit Finaled 3/22/2022 DANIEL ORRANTE
CofO Issued 3/22/2022 DANIEL ORRANTE
Permit Finaled 3/22/2022 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/3/2019 APEKSHYA BAJRACHARYA
Permit Cleared 12/3/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 12/3/2019 APEKSHYA BAJRACHARYA
Hydrant and Access approval Cleared 2/13/2020 JEREMY CARTER
Trees in Parkway Cleared 2/21/2020 ADRIAN SANCHEZ
Low Impact Development Cleared 2/25/2020 SARAH YOUSSEF
Green Code Cleared 3/9/2020 DAVID MATSON
Roof/Waste drainage to street Cleared 4/9/2020 JOHN TRIANTAFYLLOS

Contact Information

Contractor H T Builders; Lic. No.: 1051585-B 223 N GLENDORA AVENUE      GLENDORA, CA 91741

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/8/2020 Approved JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 8/14/2020 Corrections Issued JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 8/27/2020 Approved CRAIG DAVIS
Footing/Foundation/Slab 8/27/2020 Approved CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 9/11/2020 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 9/11/2020 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 9/15/2020 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 9/24/2020 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 10/27/2020 Corrections Issued JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 11/13/2020 Not Ready for Inspection JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 11/17/2020 Corrections Issued JUAN VALENZUELA
BUILDING-Rough-Frame 1/27/2021 Not Ready for Inspection JUAN VALENZUELA
ELECTRICAL-Rough 1/27/2021 Corrections Issued JUAN VALENZUELA
Green Building Rough 1/27/2021 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Rough 1/27/2021 Corrections Issued JUAN VALENZUELA
Wood Frame 1/27/2021 Not Ready for Inspection JUAN VALENZUELA
BUILDING-Rough-Frame 2/4/2021 Corrections Issued JUAN VALENZUELA
ELECTRICAL-Rough 2/4/2021 Not Ready for Inspection JUAN VALENZUELA
Green Building Rough 2/4/2021 Not Ready for Inspection JUAN VALENZUELA
PLUMBING-Rough 2/4/2021 Approved JUAN VALENZUELA
Deputy Drilled-In Anchors 2/5/2021 Partial Approval DAVID HEINE
ELECTRICAL-Rough 3/22/2021 Not Ready for Inspection JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 3/22/2021 Partial Approval JUAN VALENZUELA
Green Building Rough 3/22/2021 Not Ready for Inspection JUAN VALENZUELA
HVAC-Rough 3/22/2021 Partial Inspection JUAN VALENZUELA
Shower Pan 3/22/2021 Approved JUAN VALENZUELA
ELECTRICAL-Rough 4/30/2021 No Access for Inspection BRENDAN LOONEY
PLUMBING-Rough 4/30/2021 No Access for Inspection BRENDAN LOONEY
ELECTRICAL-Rough 5/3/2021 Corrections Issued BRENDAN LOONEY
HVAC-Rough 5/3/2021 Corrections Issued BRENDAN LOONEY
Wood Frame 5/3/2021 Corrections Issued BRENDAN LOONEY
BUILDING-Rough-Frame 5/6/2021 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Rough 5/6/2021 Approved BRENDAN LOONEY
Green Building Rough 5/6/2021 Approved BRENDAN LOONEY
HVAC-Rough 5/6/2021 Approved BRENDAN LOONEY
Interior/Exterior Lathing 5/6/2021 Not Ready for Inspection BRENDAN LOONEY
PLUMBING-Rough 5/6/2021 Approved BRENDAN LOONEY
Insulation 5/18/2021 Corrections Issued BRENDAN LOONEY
Interior/Exterior Lathing 5/18/2021 Partial Approval BRENDAN LOONEY
Insulation 5/19/2021 Approved AMY COLIN
Pre-Inspection 6/4/2021 No Access for Inspection PIERRE VEGA
Drywall Nailing 6/9/2021 Approved ADAM ESCOTO
Interior/Exterior Lathing 7/30/2021 Corrections Issued ANTHONY MCDOWALL
Interior/Exterior Lathing 8/3/2021 Partial Approval MORRIS JACKSON
BUILDING-Rough-Frame 8/4/2021 Approved BRENDAN LOONEY
Verify Sprinkler Sign Off 8/4/2021 Approved BRENDAN LOONEY
Interior/Exterior Lathing 8/26/2021 Corrections Issued SHAVONNE ESPINOZA
Interior/Exterior Lathing 8/31/2021 Conditional Approval JESUS RODRIGUEZ
Interior/Exterior Lathing 9/8/2021 Approved MORRIS JACKSON
Final 12/2/2021 Partial Inspection ENRIQUE MIRELES
Green Building Final 12/2/2021 Not Ready for Inspection ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 12/2/2021 SGSOV Not Ready ENRIQUE MIRELES
Smoke Detectors 12/2/2021 Not Ready for Inspection ENRIQUE MIRELES
Final 12/15/2021 Corrections Issued ENRIQUE MIRELES
Green Building Final 12/15/2021 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 12/15/2021 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 12/15/2021 Approved ENRIQUE MIRELES
ELECTRICAL-Final 12/17/2021 Corrections Issued BOBBY KEY
ELECTRICAL-Final 1/5/2022 Corrections Issued BOBBY KEY
ELECTRICAL-Final 1/6/2022 Approved BOBBY KEY
Final 1/6/2022 Corrections Issued BOBBY KEY
ELECTRICAL-Final 3/2/2022 Corrections Issued BOBBY KEY
Final 3/2/2022 Corrections Issued BOBBY KEY
HVAC-Final 3/2/2022 Corrections Issued BOBBY KEY
PLUMBING-Final 3/2/2022 Corrections Issued BOBBY KEY
Verify Sprinkler Sign Off 3/2/2022 Approved BOBBY KEY
ELECTRICAL-Final 3/8/2022 Approved BOBBY KEY
Final 3/8/2022 Not Ready for Inspection BOBBY KEY
HVAC-Final 3/8/2022 Corrections Issued BOBBY KEY
PLUMBING-Final 3/8/2022 Approved BOBBY KEY
Final 3/15/2022 OK to Issue CofO BOBBY KEY
HVAC-Final 3/15/2022 Approved BOBBY KEY
Service/Power Release 3/17/2022 Approved BOBBY KEY