2639 S CLYDE AVE 90016

Certificate Information: 2639 S CLYDE AVE 90016

Application / Permit
19014-20000-05690
Plan Check / Job No.
B19VN17987
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 28'3" X 15'11" IRREGULAR SHAPED ADDITION TO (E) SFD TO CREATE MASTER BEDROOM , MASTER BATHROOM AND W.I.C. INTERIOR REMODEL TO (E) SFD TO REMODEL (2) BEDROOM , (1)BATHROOM , (1) LAUNDRY ROOM , KITCHEN AND LIVING ROOM , ALL WORK PER ENGINEERING
Permit Issued
Issued on 1/16/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 3/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/18/2019 APPLICANT
Assigned to Plan Check Engineer 10/18/2019 RARES BODEA
Corrections Issued 10/18/2019 RARES BODEA
Plan Check Approved 10/18/2019 ROSENDO MEDINA
Issued 1/16/2020 LADBS
CofO in Progress 9/16/2021 STUART CHAPMAN
Permit Finaled 3/4/2023 DANIEL ORRANTE
CofO Issued 3/4/2023 DANIEL ORRANTE
Permit Finaled 3/4/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/18/2019 HOWARD COOPER
Roof/Waste drainage to street Cleared 10/18/2019 HOWARD COOPER
Sewer availability Cleared 10/18/2019 HOWARD COOPER

Contact Information

Contractor A & H Construction Home Improvement Inc; Lic. No.: 1061876-B 4543 E 55TH STREET      MAYWOOD, CA 90270
Engineer Alson,, Ken; Lic. No.: C41697 9744 MAPLE ST 201      BELLFLOWER, CA 90706

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/12/2020 Corrections Issued DAVID CHAN
Footing/Foundation/Slab 3/12/2020 Corrections Issued DAVID CHAN
Deputy Drilled-In Anchors 3/18/2020 Conditional Approval MATTHEW NUCKOLLS
Excavation/Setback/Form/Re-Bar 3/20/2020 Approved MATTHEW NUCKOLLS
Footing/Foundation/Slab 3/20/2020 Approved MATTHEW NUCKOLLS
Floor/Roof Diaphrgm/Shear Wall 5/6/2020 Partial Approval DAVID CHAN
PLUMBING-Rough 5/6/2020 Partial Approval DAVID CHAN
BUILDING-Rough-Frame 7/13/2020 Corrections Issued DAVID CHAN
ELECTRICAL-Rough 7/13/2020 Corrections Issued DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 7/13/2020 Corrections Issued DAVID CHAN
Green Building Rough 7/13/2020 Not Ready for Inspection DAVID CHAN
PLUMBING-Rough 7/13/2020 Corrections Issued DAVID CHAN
BUILDING-Rough-Frame 8/21/2020 Corrections Issued DAVID CHAN
ELECTRICAL-Rough 8/21/2020 Approved DAVID CHAN
Floor/Roof Diaphrgm/Shear Wall 8/21/2020 Corrections Issued DAVID CHAN
Interior/Exterior Lathing 8/21/2020 Not Ready for Inspection DAVID CHAN
PLUMBING-Rough 8/21/2020 Approved DAVID CHAN
Shower Pan 8/21/2020 Partial Inspection DAVID CHAN
Interior/Exterior Lathing 8/28/2020 Approved DAVID CHAN
Wood Frame 8/28/2020 Approved DAVID CHAN
Insulation 9/3/2020 Corrections Issued STUART CHAPMAN
Insulation 9/9/2020 Approved DAVID CHAN
Drywall Nailing 9/23/2020 Approved DAVID CHAN
Green Building Rough 9/23/2020 Approved DAVID CHAN
Shower Pan 9/23/2020 Not Ready for Inspection DAVID CHAN
ELECTRICAL-Rough 6/25/2021 Approved STUART CHAPMAN
Wood Frame 6/25/2021 Approved STUART CHAPMAN
Insulation 7/1/2021 Partial Approval CHRISTOPHER DELLEFIELD
Drywall Nailing 7/7/2021 Approved STUART CHAPMAN
BUILDING-Rough-Frame 9/16/2021 Approved STUART CHAPMAN
ELECTRICAL-Final 9/16/2021 Approved STUART CHAPMAN
Final 9/16/2021 OK to Issue CofO STUART CHAPMAN
Green Building Final 9/16/2021 Approved STUART CHAPMAN
HVAC-Final 9/16/2021 Approved STUART CHAPMAN
PLUMBING-Final 9/16/2021 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 9/16/2021 SGSOV Approved STUART CHAPMAN
Smoke Detectors 9/16/2021 Approved STUART CHAPMAN