9709 N HAYVENHURST AVE 91343

Certificate Information: 9709 N HAYVENHURST AVE 91343

Application / Permit
19014-20000-05672
Plan Check / Job No.
B19VN17921
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20' X 20' DETACHED GARAGE TO ACCESSORY DWELLING UNIT AND ADD 7' X 20' TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
Permit Issued
Issued on 10/30/2019
Issuing Office
Valley
Current Status
CofO Issued on 8/10/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/17/2019 APPLICANT
Assigned to Plan Check Engineer 10/23/2019 JENNIFER LEE
Corrections Issued 10/23/2019 JENNIFER LEE
Applicant returned to address corrections 10/24/2019 ANGELICA DAVE
Plan Check Approved 10/30/2019 PINANK PATEL
Issued 10/30/2019 LADBS
CofO in Progress 6/28/2021 ARTHUR SARGSYAN
CofO Issued 8/10/2021 MICHAEL SMITH
Permit Finaled 8/10/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 10/28/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 10/28/2019 GUILLERMO PETRA
Grading Pre-Inspection Cleared 10/28/2019 BARTON HOLMES
Roof/Waste drainage to street Cleared 10/28/2019 GUILLERMO PETRA
Sewer availability Cleared 10/28/2019 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 5/12/2020 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 5/12/2020 Partial Inspection MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 5/12/2020 SGSOV Not Ready MATTHEW NELSON
Sewer 5/12/2020 Partial Inspection MATTHEW NELSON
Footing/Foundation/Slab 7/2/2020 Approved DANIEL DREW
PLUMBING-Rough 7/2/2020 Approved DANIEL DREW
ELECTRICAL-Rough 11/9/2020 Approved ARTHUR SARGSYAN
Gas Test 11/9/2020 Approved ARTHUR SARGSYAN
HVAC-Rough 11/9/2020 Approved ARTHUR SARGSYAN
PLUMBING-Rough 11/9/2020 Approved ARTHUR SARGSYAN
Rough-Elec/Plmb/HVAC 11/9/2020 Approved ARTHUR SARGSYAN
Wood Frame 11/9/2020 Approved ARTHUR SARGSYAN
Insulation 11/17/2020 Corrections Issued DAVID MATSON
Insulation 11/25/2020 Approved ARTHUR SARGSYAN
Drywall Nailing 12/7/2020 Approved ARTHUR SARGSYAN
Green Building Rough 12/7/2020 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 3/25/2021 Approved ARTHUR SARGSYAN
ELECTRICAL-Final 3/25/2021 Not Ready for Inspection ARTHUR SARGSYAN
Final 3/25/2021 Corrections Issued ARTHUR SARGSYAN
Green Building Final 3/25/2021 Not Ready for Inspection ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 3/25/2021 SGSOV Approved ARTHUR SARGSYAN
Smoke Detectors 3/25/2021 Approved ARTHUR SARGSYAN
Final 4/28/2021 Corrections Issued ARTHUR SARGSYAN
Green Building Final 4/28/2021 Approved ARTHUR SARGSYAN
Final 5/11/2021 Not Ready for Inspection ARTHUR SARGSYAN
Final 6/28/2021 OK to Issue CofO ARTHUR SARGSYAN