26'-0" x 34'-0" and 25'-8" x 34'-0" Irregular shaped additions to existing Single-Family Dwelling.
Permit Issued
Issued on 1/17/2020
Issuing Office
Valley
Current Status
CofO Issued on 10/2/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/17/2019 APPLICANT
Assigned to Plan Check Engineer 10/17/2019 ARTIN ZARUKIAN
Corrections Issued 10/17/2019 ARTIN ZARUKIAN
Building Plans Picked Up 10/24/2019 APPLICANT
Plan Check Approved 1/17/2020 ARTIN ZARUKIAN
Issued 1/17/2020 LADBS
CofO in Progress 5/31/2020 VINCENT HANLEY
Permit Finaled 10/2/2020 JOHN JANSON
CofO Issued 10/2/2020 JOHN JANSON
Permit Finaled 10/2/2020 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/8/2020 GABRIEL ROBLES
Sewer availability Cleared 1/8/2020 GABRIEL ROBLES
Low Impact Development Cleared 1/9/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 1/9/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Yenjai,, Seree; Lic. No.: C73151 3249 SHADYLAWN DRIVE      DUARTE, CA 91010

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 2/6/2020 Corrections Issued VINCENT HANLEY
PLUMBING-Rough 2/6/2020 Partial Approval VINCENT HANLEY
Deputy Drilled-In Anchors 2/10/2020 Approved DAVID SANDOVAL
Excavation/Setback/Form/Re-Bar 2/11/2020 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/4/2020 Approved VINCENT HANLEY
BUILDING-Rough-Frame 3/17/2020 Partial Approval VINCENT HANLEY
Rough-Elec/Plmb/HVAC 3/17/2020 Approved VINCENT HANLEY
BUILDING-Rough-Frame 3/24/2020 Approved VINCENT HANLEY
Green Building Rough 3/24/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 3/24/2020 Not Ready for Inspection VINCENT HANLEY
Insulation 3/26/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 3/26/2020 Partial Approval VINCENT HANLEY
Drywall Nailing 3/31/2020 Approved VINCENT HANLEY
Interior/Exterior Lathing 3/31/2020 Approved VINCENT HANLEY
Shower Pan 3/31/2020 Approved VINCENT HANLEY
Final 5/13/2020 Corrections Issued VINCENT HANLEY
Footing/Foundation/Slab 5/13/2020 Approved VINCENT HANLEY
Green Building Final 5/13/2020 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/13/2020 SGSOV Not Ready VINCENT HANLEY
Service/Power Release 5/13/2020 Approved VINCENT HANLEY
Smoke Detectors 5/13/2020 Approved VINCENT HANLEY
Final 5/19/2020 Partial Approval VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 5/19/2020 SGSOV Approved VINCENT HANLEY