10764-10768 N SUTTER AVE 91331
Certificate Information: 10764-10768 N SUTTER AVE 91331
- Application / Permit
- 19014-20000-05658
- Plan Check / Job No.
- B19VN17869
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- REMODEL BEDROOM, CREATE NEW BATHROOM AND ADD 11' x 28'10" BEDROOM/BATHROOM TO REAR UNIT PER DESIGN
- Permit Issued
- Issued on 1/8/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/17/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2019 | ALDOUS CHIC |
| Corrections Issued | 10/17/2019 | ALDOUS CHIC |
| Applicant returned to address corrections | 1/7/2020 | JENNIFER LEE |
| Plan Check Approved | 1/8/2020 | JEROME MAGAT PALMA |
| Issued | 1/8/2020 | LADBS |
| CofO in Progress | 10/23/2020 | MICHEL ABAJAN |
| CofO Issued | 12/17/2020 | MICHAEL SMITH |
| Permit Finaled | 12/17/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/7/2020 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 1/7/2020 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/7/2020 | LEE GUILBEAUX |
| Miscellaneous | Cleared | 1/8/2020 | JEROME MAGAT PALMA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/17/2020 | Approved | MICHEL ABAJAN |
| METHANE-Barrier | 3/17/2020 | Approved | MICHEL ABAJAN |
| METHANE-Subgrade | 3/17/2020 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 4/2/2020 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 4/2/2020 | Not Ready for Inspection | MICHEL ABAJAN |
| METHANE-Rough | 4/2/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 4/2/2020 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 5/7/2020 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 5/7/2020 | Approved | MICHEL ABAJAN |
| Green Building Rough | 5/7/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 5/7/2020 | Approved | MICHEL ABAJAN |
| Insulation | 6/15/2020 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 6/15/2020 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 6/25/2020 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 10/23/2020 | Approved | MICHEL ABAJAN |
| Final | 10/23/2020 | OK to Issue CofO | MICHEL ABAJAN |
| Green Building Final | 10/23/2020 | Approved | MICHEL ABAJAN |
| HVAC-Final | 10/23/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 10/23/2020 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 10/23/2020 | SGSOV Approved | MICHEL ABAJAN |
| Smoke Detectors | 10/23/2020 | Approved | MICHEL ABAJAN |