15339 W GERMAIN ST 91345
Certificate Information: 15339 W GERMAIN ST 91345
- Application / Permit
- 19014-20000-05651
- Plan Check / Job No.
- B19VN17843
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Add (20'0" X 17'0") bedroom/bathroom to existing SFD. Work per LA Std WFPP.
- Permit Issued
- Issued on 10/23/2020
- Issuing Office
- Current Status
- CofO Issued on 6/19/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2019 | BINH PHAN |
| Corrections Issued | 10/17/2019 | BINH PHAN |
| Plan Check Approved | 9/14/2020 | TROY DEGUZMAN |
| Issued | 10/23/2020 | APPLICANT |
| CofO in Progress | 5/17/2021 | JENNIFER RABUCHIN |
| CofO Issued | 6/19/2021 | MICHAEL SMITH |
| Permit Finaled | 6/19/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/17/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 10/17/2019 | GUILLERMO PETRA |
| Construction near power lines | Cleared | 12/29/2019 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/4/2020 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/4/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Sewer | 11/4/2020 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 11/6/2020 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Rough | 11/6/2020 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 12/7/2020 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 12/7/2020 | Approved | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 12/7/2020 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 12/7/2020 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 12/7/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Shower Pan | 12/11/2020 | Approved | DANIEL ORRANTE |
| HVAC-Rough | 12/16/2020 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 12/16/2020 | Partial Approval | JENNIFER RABUCHIN |
| Shower Pan | 12/16/2020 | Approved | JENNIFER RABUCHIN |
| Insulation | 12/18/2020 | Approved | DANIEL ORRANTE |
| Drywall Nailing | 12/21/2020 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 12/21/2020 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 2/17/2021 | Approved | JENNIFER RABUCHIN |
| Final | 2/17/2021 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 2/17/2021 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 2/17/2021 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 2/17/2021 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 2/17/2021 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 5/18/2021 | Approved | JENNIFER RABUCHIN |
| Final | 5/18/2021 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 5/18/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 5/18/2021 | Approved | JENNIFER RABUCHIN |