10617 N VANORA DR 91040

Certificate Information: 10617 N VANORA DR 91040

Application / Permit
19014-20000-05576
Plan Check / Job No.
B19VN17548
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
33'-6" X 26'-6" IRREGULAR SHAPED ADDITION OF BEDROOM, BATHROOM, CLOSET AND DINING ROOM TO THE (E) SFD PER ENGINEERING.
Permit Issued
Issued on 10/28/2019
Issuing Office
Valley
Current Status
CofO Issued on 10/15/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/11/2019 APPLICANT
Assigned to Plan Check Engineer 10/11/2019 ARTIN ZARUKIAN
Corrections Issued 10/11/2019 ARTIN ZARUKIAN
Plan Check Approved 10/25/2019 SEAN SHAHMIRI
Issued 10/28/2019 ZABEL ALTUNKARYAN
CofO in Progress 9/14/2022 DAVID MATSON
CofO Issued 10/15/2022 MICHAEL SMITH
Permit Finaled 10/15/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/15/2019 SAFA JAVANMARDI
Grading Pre-Inspection Cleared 10/15/2019 BARTON HOLMES
Roof/Waste drainage to street Cleared 10/15/2019 SAFA JAVANMARDI
Specific Plan Cleared 10/23/2019 PEGGY MALONE-BROWN
ZI Cleared 10/23/2019 PEGGY MALONE-BROWN

Contact Information

Contractor Owner-Builder       ,
Engineer Medina,, Ferdinand Casaclang; Lic. No.: C88007 1051 S HOLT AVE APT F      LOS ANGELES, CA 90035

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/2/2020 Approved MATTHEW NELSON
Footing/Foundation/Slab 7/2/2020 Approved MATTHEW NELSON
PLUMBING-Rough 8/4/2020 Corrections Issued MATTHEW NELSON
PLUMBING-Rough 8/14/2020 Partial Inspection MATTHEW NELSON
Insulation 9/23/2020 Partial Inspection MATTHEW NELSON
Wood Frame 9/23/2020 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 10/9/2020 Approved MATTHEW NELSON
BUILDING-Rough-Frame 10/22/2020 Not Ready for Inspection MATTHEW NELSON
ELECTRICAL-Rough 10/22/2020 Approved MATTHEW NELSON
Green Building Rough 10/22/2020 Approved MATTHEW NELSON
HVAC-Rough 10/22/2020 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 10/22/2020 Approved MATTHEW NELSON
BUILDING-Rough-Frame 10/27/2020 Approved MATTHEW NELSON
HVAC-Rough 10/27/2020 Approved MATTHEW NELSON
Insulation 11/5/2020 Approved MATTHEW NELSON
Interior/Exterior Lathing 11/5/2020 Approved MATTHEW NELSON
Drywall Nailing 11/16/2020 Approved MATTHEW NELSON
Final 2/16/2022 Conditional Approval DAVID MATSON
Green Building Final 2/16/2022 Approved DAVID MATSON
SGSOV-Seismic Gas S/O Valve 2/16/2022 SGSOV Approved DAVID MATSON
Smoke Detectors 2/16/2022 Approved DAVID MATSON
Final 9/6/2022 Conditional Approval DAVID MATSON
Final 9/14/2022 OK to Issue CofO DAVID MATSON