10617 N VANORA DR 91040
Certificate Information: 10617 N VANORA DR 91040
- Application / Permit
- 19014-20000-05576
- Plan Check / Job No.
- B19VN17548
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 33'-6" X 26'-6" IRREGULAR SHAPED ADDITION OF BEDROOM, BATHROOM, CLOSET AND DINING ROOM TO THE (E) SFD PER ENGINEERING.
- Permit Issued
- Issued on 10/28/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/15/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/11/2019 | ARTIN ZARUKIAN |
| Corrections Issued | 10/11/2019 | ARTIN ZARUKIAN |
| Plan Check Approved | 10/25/2019 | SEAN SHAHMIRI |
| Issued | 10/28/2019 | ZABEL ALTUNKARYAN |
| CofO in Progress | 9/14/2022 | DAVID MATSON |
| CofO Issued | 10/15/2022 | MICHAEL SMITH |
| Permit Finaled | 10/15/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/15/2019 | SAFA JAVANMARDI |
| Grading Pre-Inspection | Cleared | 10/15/2019 | BARTON HOLMES |
| Roof/Waste drainage to street | Cleared | 10/15/2019 | SAFA JAVANMARDI |
| Specific Plan | Cleared | 10/23/2019 | PEGGY MALONE-BROWN |
| ZI | Cleared | 10/23/2019 | PEGGY MALONE-BROWN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Medina,, Ferdinand Casaclang; Lic. No.: C88007 | 1051 S HOLT AVE APT F LOS ANGELES, CA 90035 |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/2/2020 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 7/2/2020 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 8/4/2020 | Corrections Issued | MATTHEW NELSON |
| PLUMBING-Rough | 8/14/2020 | Partial Inspection | MATTHEW NELSON |
| Insulation | 9/23/2020 | Partial Inspection | MATTHEW NELSON |
| Wood Frame | 9/23/2020 | Approved | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2020 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 10/22/2020 | Not Ready for Inspection | MATTHEW NELSON |
| ELECTRICAL-Rough | 10/22/2020 | Approved | MATTHEW NELSON |
| Green Building Rough | 10/22/2020 | Approved | MATTHEW NELSON |
| HVAC-Rough | 10/22/2020 | Not Ready for Inspection | MATTHEW NELSON |
| PLUMBING-Rough | 10/22/2020 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 10/27/2020 | Approved | MATTHEW NELSON |
| HVAC-Rough | 10/27/2020 | Approved | MATTHEW NELSON |
| Insulation | 11/5/2020 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 11/5/2020 | Approved | MATTHEW NELSON |
| Drywall Nailing | 11/16/2020 | Approved | MATTHEW NELSON |
| Final | 2/16/2022 | Conditional Approval | DAVID MATSON |
| Green Building Final | 2/16/2022 | Approved | DAVID MATSON |
| SGSOV-Seismic Gas S/O Valve | 2/16/2022 | SGSOV Approved | DAVID MATSON |
| Smoke Detectors | 2/16/2022 | Approved | DAVID MATSON |
| Final | 9/6/2022 | Conditional Approval | DAVID MATSON |
| Final | 9/14/2022 | OK to Issue CofO | DAVID MATSON |