8316 W SKYLINE DR 90046
Certificate Information: 8316 W SKYLINE DR 90046
- Application / Permit
- 19014-20000-05569
- Plan Check / Job No.
- B19VN17534
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE ATTACHED DECK, ADD WALK IN CLOSET IN (E) BEDROOM, 11'-11" X 28'-6" ADDITION TO (E) SFD TO EXTEND (E) BEDROOMS AND ADD A BATHROOM & CLOSET.
- Permit Issued
- Issued on 1/29/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/8/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/11/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2019 | ARTIN ZARUKIAN |
| Corrections Issued | 10/26/2019 | ARTIN ZARUKIAN |
| Quality Review Completed | 10/28/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 10/29/2019 | APPLICANT |
| Green Plans Picked Up | 10/29/2019 | APPLICANT |
| Applicant returned to address corrections | 12/16/2019 | ARTIN ZARUKIAN |
| Plan Check Approved | 1/17/2020 | ARTIN ZARUKIAN |
| Issued | 1/29/2020 | LADBS |
| CofO in Progress | 12/23/2020 | RAUL BARAJAS |
| Permit Finaled | 5/8/2021 | DEROLD HAUFF |
| CofO Issued | 5/8/2021 | DEROLD HAUFF |
| Permit Finaled | 5/8/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/29/2019 | GUILLERMO PETRA |
| Permit | Cleared | 10/29/2019 | GUILLERMO PETRA |
| ZA Case | Cleared | 11/12/2019 | STEVEN WECHSLER |
| Green Code | Cleared | 12/2/2019 | AARON COSTA |
| Specific Plan | Cleared | 12/6/2019 | TRACY WILLIAMS |
| ZI | Cleared | 12/6/2019 | TRACY WILLIAMS |
| Grading Pre-Inspection | Cleared | 12/16/2019 | ARTIN ZARUKIAN |
Contact Information
| Contractor | 24/7 Construction Works Inc; Lic. No.: 1022079-B | 4648 SANTA ANITA AVE EL MONTE, CA 91731 |
| Engineer | Garcia,, Lionel Jesus; Lic. No.: S4653 | 24702 NARBONNE AVE LOMITA, CA 90717 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/24/2020 | Partial Approval | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 8/24/2020 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 8/26/2020 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 10/2/2020 | Corrections Issued | RAUL BARAJAS |
| ELECTRICAL-Rough | 10/2/2020 | Not Ready for Inspection | RAUL BARAJAS |
| HVAC-Rough | 10/2/2020 | Not Ready for Inspection | RAUL BARAJAS |
| PLUMBING-Rough | 10/2/2020 | Not Ready for Inspection | RAUL BARAJAS |
| Deputy Wood Construction | 10/13/2020 | No Access for Inspection | ELMER BLAND |
| ELECTRICAL-Rough | 10/16/2020 | Approved | RAUL BARAJAS |
| HVAC-Rough | 10/16/2020 | Approved | RAUL BARAJAS |
| PLUMBING-Rough | 10/16/2020 | Approved | RAUL BARAJAS |
| Insulation | 10/28/2020 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 10/28/2020 | Approved | RAUL BARAJAS |
| Shower Pan | 10/28/2020 | Approved | RAUL BARAJAS |
| Drywall Nailing | 11/5/2020 | Approved | RAUL BARAJAS |
| Green Building Rough | 11/5/2020 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 12/9/2020 | Approved | RAUL BARAJAS |
| Final | 12/9/2020 | Corrections Issued | RAUL BARAJAS |
| Green Building Final | 12/9/2020 | Not Ready for Inspection | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 12/9/2020 | SGSOV Approved | RAUL BARAJAS |
| Smoke Detectors | 12/9/2020 | Approved | RAUL BARAJAS |
| Final | 12/23/2020 | OK to Issue CofO | RAUL BARAJAS |
| Green Building Final | 12/23/2020 | Approved | RAUL BARAJAS |