629 E 92ND ST 90002

Certificate Information: 629 E 92ND ST 90002

Application / Permit
19014-20000-05567
Plan Check / Job No.
B19VN17524
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL AND ADD 35'-9" X 21'-0" IRREGULAR SHAPE TO (E) SFD, REMOVE 2'-6" X 18' DETACHED CARPORT AND CONVERT REMAINING 9'-6" X 18' CARPORT TO ATTACHED PATIO COVER TO (E) SFD PER WFPP. "Comply with Department Order effective date 11/01/2019.
Permit Issued
Issued on 11/7/2019
Issuing Office
Valley
Current Status
CofO Issued on 9/29/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/11/2019 APPLICANT
Assigned to Plan Check Engineer 10/11/2019 ARTIN ZARUKIAN
Corrections Issued 10/11/2019 ARTIN ZARUKIAN
Plan Check Approved 10/31/2019 RAPHAEL ROSAS
Issued 11/7/2019 LADBS
CofO in Progress 8/25/2020 GABRIEL HERRERA
CofO in Progress 8/25/2020 GABRIEL HERRERA
CofO Issued 9/29/2020 ARMOND GREGORYONA
Permit Finaled 9/29/2020 ARMOND GREGORYONA

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/31/2019 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 10/31/2019 ADRIAN CASTRO
Sewer availability Cleared 10/31/2019 ADRIAN CASTRO
Hold Cleared 2/13/2020 CYNTHIA RYAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EDMUND LUM, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
LUCIANO GAUNA, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
JAIME RIOS, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
ANDEY CHAPARRO, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
RYAN BARNES, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
PATRICK LIEBREGT, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
GLEN RAND, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
SHAWN ESHBACH, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
GABRIEL HERRERA, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/18/2020 Corrections Issued NEVILLE REID
Deputy Drilled-In Anchors 2/20/2020 Approved NEVILLE REID
Excavation/Setback/Form/Re-Bar 2/20/2020 Corrections Issued NEVILLE REID
Excavation/Setback/Form/Re-Bar 2/21/2020 Approved NEVILLE REID
Floor/Roof Diaphrgm/Shear Wall 3/5/2020 Corrections Issued NEVILLE REID
PLUMBING-Rough 3/5/2020 Corrections Issued NEVILLE REID
Footing/Foundation/Slab 3/25/2020 Approved NEVILLE REID
PLUMBING-Rough 4/3/2020 Not Ready for Inspection NEVILLE REID
BUILDING-Rough-Frame 6/3/2020 Not Ready for Inspection NEVILLE REID
Drywall Nailing 6/3/2020 Not Ready for Inspection NEVILLE REID
Floor/Roof Diaphrgm/Shear Wall 6/3/2020 Not Ready for Inspection NEVILLE REID
Floor/Roof Diaphrgm/Shear Wall 6/9/2020 Approved JEFFREY CORPUZ
Wood Frame 6/9/2020 Partial Approval JEFFREY CORPUZ
ELECTRICAL-Rough 6/16/2020 Not Ready for Inspection JEFFREY CORPUZ
Interior/Exterior Lathing 6/16/2020 Approved JEFFREY CORPUZ
PLUMBING-Rough 6/16/2020 Not Ready for Inspection JEFFREY CORPUZ
BUILDING-Rough-Frame 6/26/2020 Approved GABRIEL HERRERA
ELECTRICAL-Rough 6/26/2020 Approved GABRIEL HERRERA
HVAC-Rough 6/26/2020 Approved GABRIEL HERRERA
PLUMBING-Rough 6/26/2020 Approved GABRIEL HERRERA
ELECTRICAL-Rough 7/7/2020 Approved GABRIEL HERRERA
Floor/Roof Diaphrgm/Shear Wall 7/15/2020 Approved GABRIEL HERRERA
Insulation 7/15/2020 Approved GABRIEL HERRERA
Interior/Exterior Lathing 7/15/2020 Approved GABRIEL HERRERA
Service/Power Release 7/15/2020 Approved GABRIEL HERRERA
Drywall Nailing 8/21/2020 Approved GABRIEL HERRERA
SGSOV-Seismic Gas S/O Valve 8/21/2020 SGSOV Approved GABRIEL HERRERA
Smoke Detectors 8/21/2020 Approved GABRIEL HERRERA
Final 8/25/2020 OK to Issue CofO GABRIEL HERRERA