9453 N NATICK AVE 91343

Certificate Information: 9453 N NATICK AVE 91343

Application / Permit
19014-20000-05564
Plan Check / Job No.
B19VN17515
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18'-3" X 20'-2" DETACHED GARAGE AND ADD IRREGULAR 10'-10" X 20'-2" FOR (N) ACCESSORY DWELLING UNIT. ALL WORK PER WFPP.
Permit Issued
Issued on 2/12/2020
Issuing Office
Valley
Current Status
CofO Issued on 8/7/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/11/2019 APPLICANT
Assigned to Plan Check Engineer 10/16/2019 JENNIFER LEE
Corrections Issued 10/16/2019 JENNIFER LEE
Plan Check Approved 2/11/2020 RAPHAEL ROSAS
Issued 2/12/2020 LADBS
CofO in Progress 5/1/2021 GREGG CUMMINGS
Permit Finaled 8/7/2021 MICHAEL SMITH
CofO Issued 8/7/2021 MICHAEL SMITH
Permit Finaled 8/7/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 10/21/2019 APEKSHYA BAJRACHARYA
Roof/Waste drainage to street Cleared 10/21/2019 APEKSHYA BAJRACHARYA
Construction near power lines Cleared 11/27/2019 OSCAR CASTRO
Eng Process Fee Ord 176,300 Cleared 1/28/2020 GUILLERMO PETRA
Sewer availability Cleared 1/28/2020 GUILLERMO PETRA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/7/2020 Partial Inspection WILLIAM KUEHN
Sewer 5/7/2020 Approved WILLIAM KUEHN
Footing/Foundation/Slab 5/11/2020 Approved MARK JOHNSON
Floor/Roof Diaphrgm/Shear Wall 6/5/2020 Partial Inspection WILLIAM KUEHN
Green Building Rough 6/5/2020 Not Ready for Inspection WILLIAM KUEHN
Interior/Exterior Lathing 6/22/2020 Partial Inspection WILLIAM KUEHN
Rough-Elec/Plmb/HVAC 6/22/2020 Approved WILLIAM KUEHN
Insulation 6/26/2020 Approved WILLIAM KUEHN
Interior/Exterior Lathing 6/26/2020 Approved WILLIAM KUEHN
Shower Pan 6/26/2020 Approved WILLIAM KUEHN
Drywall Nailing 7/2/2020 Approved WILLIAM KUEHN
Green Building Rough 7/2/2020 Approved WILLIAM KUEHN
Underground Mechanical 8/5/2020 Partial Approval GREGG CUMMINGS
BUILDING-Rough-Frame 4/9/2021 Approved GREGG CUMMINGS
Final 4/9/2021 Corrections Issued GREGG CUMMINGS
Green Building Final 4/9/2021 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 4/9/2021 SGSOV Approved GREGG CUMMINGS
Smoke Detectors 4/9/2021 Approved GREGG CUMMINGS
ELECTRICAL-Final 4/30/2021 Approved GREGG CUMMINGS
Final 4/30/2021 OK to Issue CofO GREGG CUMMINGS
HVAC-Final 4/30/2021 Approved GREGG CUMMINGS
PLUMBING-Final 4/30/2021 Approved GREGG CUMMINGS