- ADD 26.5'x40', 2ND STORY, (N) ACCESSORY DWELLING UNIT PER AB 494 & SB 229 TO (E) GARAGE. REMOVE (E) CONTINOUS GARAGE FOOTING PER STRUCTURAL PLANS.
- Permit Issued
- Issued on 3/3/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/19/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2019 | SEAN SHAHMIRI |
| Corrections Issued | 11/7/2019 | SEAN SHAHMIRI |
| Green Plans Picked Up | 11/13/2019 | APPLICANT |
| Quality Review Completed | 11/14/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 11/15/2019 | APPLICANT |
| Plan Check Approved | 2/19/2020 | SEAN SHAHMIRI |
| Issued | 3/3/2020 | LADBS |
| CofO in Progress | 4/13/2022 | MATT KELLERMAN |
| CofO in Progress | 4/13/2022 | MATT KELLERMAN |
| CofO Issued | 4/19/2022 | MICHAEL SMITH |
| Permit Finaled | 4/19/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 11/20/2019 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 11/20/2019 | ADRIAN CASTRO |
| Sewer availability | Cleared | 11/20/2019 | ADRIAN CASTRO |
| Low Impact Development | Cleared | 1/17/2020 | ORVAL HERNANDEZ-MARCI |
| Green Code | Cleared | 1/28/2020 | DAVID MATSON |
| Roof/Waste drainage to street | Cleared | 2/12/2020 | JOHN TRIANTAFYLLOS |
| Hydrant and Access approval | Cleared | 2/19/2020 | GEORGE SUCHAND |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Papazyan,, Andranik; Lic. No.: C56824 | 635 W COLORADO ST STE 104 GLENDALE, CA 91204 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/3/2020 | Approved | DANIEL DREW |
| PLUMBING-Rough | 8/5/2020 | Corrections Issued | DANIEL DREW |
| Sewer | 8/5/2020 | Not Ready for Inspection | DANIEL DREW |
| Underground Mechanical | 8/5/2020 | Approved | DANIEL DREW |
| Footing/Foundation/Slab | 8/7/2020 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 9/11/2020 | Corrections Issued | DANIEL DREW |
| Green Building Rough | 9/11/2020 | Not Ready for Inspection | DANIEL DREW |
| Special/Order Compliance | 9/15/2020 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2020 | Not Ready for Inspection | DANIEL DREW |
| Sewer | 9/25/2020 | Approved | DANIEL DREW |
| Underground Mechanical | 9/25/2020 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 10/19/2020 | Not Ready for Inspection | DANIEL DREW |
| ELECTRICAL-Rough | 10/19/2020 | Approved | DANIEL DREW |
| Green Building Rough | 10/19/2020 | Not Ready for Inspection | DANIEL DREW |
| HVAC-Rough | 10/19/2020 | Corrections Issued | DANIEL DREW |
| PLUMBING-Rough | 10/19/2020 | Corrections Issued | DANIEL DREW |
| HVAC-Rough | 11/5/2020 | Approved | DANIEL DREW |
| PLUMBING-Rough | 11/5/2020 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 11/24/2020 | Not Ready for Inspection | BRENDAN LOONEY |
| Green Building Rough | 11/24/2020 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 12/2/2020 | Corrections Issued | BEAU COLLINS |
| Interior/Exterior Lathing | 12/14/2020 | Approved | DANIEL DREW |
| Insulation | 12/21/2020 | Approved | DANIEL DREW |
| Drywall Nailing | 12/24/2020 | Approved | DANIEL DREW |
| Shower Pan | 1/11/2021 | Approved | DANIEL DREW |
| BUILDING-Rough-Frame | 4/7/2021 | Approved | DANIEL DREW |
| Final | 4/7/2021 | Corrections Issued | DANIEL DREW |
| Green Building Final | 4/7/2021 | Not Ready for Inspection | DANIEL DREW |
| SGSOV-Seismic Gas S/O Valve | 4/7/2021 | SGSOV Approved | DANIEL DREW |
| Smoke Detectors | 4/7/2021 | Approved | DANIEL DREW |
| ELECTRICAL-Final | 4/16/2021 | Approved | DANIEL DREW |
| Final | 4/22/2021 | Not Ready for Inspection | DANIEL DREW |
| Green Building Final | 4/22/2021 | Not Ready for Inspection | DANIEL DREW |
| HVAC-Final | 4/28/2021 | Approved | DANIEL DREW |
| Service/Power Release | 4/28/2021 | Not Ready for Inspection | DANIEL DREW |
| Final | 6/30/2021 | Corrections Issued | DANIEL DREW |
| Green Building Final | 6/30/2021 | Not Ready for Inspection | DANIEL DREW |
| Final | 12/9/2021 | No Access for Inspection | JOHN HAYES |
| Green Building Final | 12/9/2021 | No Access for Inspection | JOHN HAYES |
| Final | 12/20/2021 | No Access for Inspection | THOMAS FINNILA |
| Green Building Final | 12/20/2021 | No Access for Inspection | THOMAS FINNILA |
| Final | 2/23/2022 | Corrections Issued | MATT KELLERMAN |
| Green Building Final | 2/23/2022 | Approved | MATT KELLERMAN |
| Final | 3/31/2022 | Corrections Issued | ARAM AVEDISIAN |
| Final | 4/5/2022 | Corrections Issued | MISAEL ESPARZA |
| Final | 4/12/2022 | OK to Issue CofO | MATT KELLERMAN |
| Service/Power Release | 4/12/2022 | Approved | MATT KELLERMAN |