7946 N MORELLA AVE 91605

Certificate Information: 7946 N MORELLA AVE 91605

Application / Permit
19014-20000-05549
Plan Check / Job No.
B19VN17468
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD (28'-6"x 35'-0") IRR SHAPE ACCESSORY DWELLING UNIT PER AB 494 & SB 229 ATTACH TO (E) 2-CAR GARAGE. WORK PER ENGINEER.
Permit Issued
Issued on 2/5/2020
Issuing Office
Valley
Current Status
CofO Issued on 4/27/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/10/2019 APPLICANT
Assigned to Plan Check Engineer 10/31/2019 TROY DEGUZMAN
Corrections Issued 11/4/2019 TROY DEGUZMAN
Quality Review Completed 11/5/2019 CHON CHIO KUO
Building Plans Picked Up 11/6/2019 APPLICANT
Green Plans Picked Up 11/6/2019 APPLICANT
Plan Check Approved 1/24/2020 TROY DEGUZMAN
Issued 2/5/2020 LADBS
CofO in Progress 10/26/2021 CHRISTOPHER DELLEFIELD
No Progress 1/26/2022 CHRISTOPHER DELLEFIELD
CofO in Progress 4/27/2023 DAVID MATSON
CofO Issued 4/27/2023 MICHAEL SMITH
Permit Finaled 4/27/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 12/18/2019 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 12/18/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 12/18/2019 APEKSHYA BAJRACHARYA
Low Impact Development Cleared 12/24/2019 AMMAR ELTAWIL
Hold Cleared 12/26/2019 CYNTHIA RYAN
Green Code Cleared 1/21/2020 DAVID MATSON
Hydrant and Access approval Cleared 1/21/2020 GEORGE SUCHAND
Roof/Waste drainage to street Cleared 1/24/2020 ADRIAN CASTRO
Hold Cleared 6/10/2020 LOURDES RAMIRO

Contact Information

Contractor Owner-Builder       ,
Engineer Papazyan,, Andranik; Lic. No.: C56824 635 W COLORADO ST STE 104      GLENDALE, CA 91204

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 2/10/2020 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 2/11/2020 Approved JOHN HAYES
Excavation/Setback/Form/Re-Bar 2/14/2020 Approved DANIEL ORRANTE
Floor/Roof Diaphrgm/Shear Wall 6/11/2020 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Rough 6/12/2020 No Access for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 6/12/2020 No Access for Inspection JOHN HAYES
HVAC-Rough 6/12/2020 No Access for Inspection JOHN HAYES
BUILDING-Rough-Frame 6/19/2020 Corrections Issued JOHN HAYES
ELECTRICAL-Rough 6/19/2020 Not Ready for Inspection JOHN HAYES
HVAC-Rough 6/19/2020 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 6/19/2020 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Rough 6/22/2020 Not Ready for Inspection JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 6/22/2020 Partial Approval JOHN HAYES
HVAC-Rough 6/22/2020 Not Ready for Inspection JOHN HAYES
PLUMBING-Rough 6/22/2020 Not Ready for Inspection JOHN HAYES
BUILDING-Rough-Frame 7/13/2020 Approved JOHN HAYES
ELECTRICAL-Rough 7/13/2020 Approved JOHN HAYES
Green Building Rough 7/13/2020 Approved JOHN HAYES
HVAC-Rough 7/13/2020 Approved JOHN HAYES
PLUMBING-Rough 7/13/2020 Approved JOHN HAYES
Drywall Nailing 7/17/2020 Not Ready for Inspection BEAU COLLINS
Interior/Exterior Lathing 7/17/2020 Not Ready for Inspection BEAU COLLINS
Drywall Nailing 7/27/2020 Approved JOHN HAYES
Interior/Exterior Lathing 7/27/2020 Approved JOHN HAYES
Shower Pan 7/27/2020 Approved JOHN HAYES
ELECTRICAL-Final 11/18/2020 Not Ready for Inspection JOHN HAYES
Final 11/18/2020 Corrections Issued JOHN HAYES
Green Building Final 11/18/2020 Not Ready for Inspection JOHN HAYES
HVAC-Final 11/18/2020 Not Ready for Inspection JOHN HAYES
PLUMBING-Final 11/18/2020 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 11/18/2020 SGSOV Not Ready JOHN HAYES
Smoke Detectors 11/18/2020 Not Ready for Inspection JOHN HAYES
Final 4/21/2021 Corrections Issued JOHN HAYES
Green Building Final 4/21/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 4/21/2021 SGSOV Not Ready JOHN HAYES
Smoke Detectors 4/21/2021 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Final 9/20/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Final 9/20/2021 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 9/20/2021 Approved CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 9/20/2021 SGSOV Approved CHRISTOPHER DELLEFIELD
Smoke Detectors 9/20/2021 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 10/26/2021 Approved CHRISTOPHER DELLEFIELD
Final 10/26/2021 OK to Issue CofO CHRISTOPHER DELLEFIELD
Green Building Final 10/26/2021 Approved CHRISTOPHER DELLEFIELD
HVAC-Final 10/26/2021 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Final 10/26/2021 Approved CHRISTOPHER DELLEFIELD
Special/Order Compliance 1/26/2022 Corrections Issued CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 2/15/2023 Corrections Issued MATTHEW NELSON