1016 N GLEN ARBOR AVE 90041
Certificate Information: 1016 N GLEN ARBOR AVE 90041
- Application / Permit
- 19014-20000-05548
- Plan Check / Job No.
- B19VN17467
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 11' 10" X 9' STUDY ROOM TO 1ST FLOOR AND ADD 10' 3" X 44' 5" 1ST FLOOR DECK ON GRADE. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 1/23/2020
- Issuing Office
- Valley
- Current Status
- Issued on 1/23/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/10/2019 | APPLICANT |
| Green Plans Picked Up | 10/21/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2019 | GURUNATH NESARAJAH |
| Corrections Issued | 10/30/2019 | GURUNATH NESARAJAH |
| Quality Review Completed | 11/5/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 11/7/2019 | APPLICANT |
| Plan Check Approved | 12/16/2019 | GURUNATH NESARAJAH |
| Issued | 1/23/2020 | LADBS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2019 | GUILLERMO PETRA |
| Green Code | Cleared | 12/3/2019 | AARON COSTA |
| Grading Pre-Inspection | Cleared | 12/13/2019 | GURUNATH NESARAJAH |
| Roof/Waste drainage to street | Cleared | 12/13/2019 | JOHN LIN |
Contact Information
| Architect | Hall,, Andrew Jackson; Lic. No.: C37666 | 207-1/2 NORTH AVE 54 LOS ANGELES, CA 90042 |
| Contractor | Owner-Builder | , |
| Engineer | Mills,, Garrett Ward; Lic. No.: S5271 | 553 S OAK KNOLL AVE PASADENA, CA 91101 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/31/2022 | Conditional Approval | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/23/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 2/23/2022 | Corrections Issued | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 4/5/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 4/5/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2022 | Partial Approval | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 6/22/2022 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 6/24/2022 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/29/2022 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 8/29/2022 | Approved | CRAIG VAUGHAN |
| Final | 8/29/2022 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 8/29/2022 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 8/29/2022 | Approved | CRAIG VAUGHAN |
| Smoke Detectors | 8/29/2022 | Approved | CRAIG VAUGHAN |