7827 N BROADLEAF AVE 91402

Certificate Information: 7827 N BROADLEAF AVE 91402

Application / Permit
19014-20000-05537
Plan Check / Job No.
B19VN17443
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED (7'-5" X 12'-11") AT FRONT AND (26'-6.5" X 46'-9") IRREGULAR SHAPED AT REAR ADDITIONS TO (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 1/21/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/29/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/10/2019 APPLICANT
Assigned to Plan Check Engineer 10/10/2019 RAPHAEL ROSAS
Corrections Issued 10/10/2019 RAPHAEL ROSAS
Building Plans Picked Up 10/18/2019 APPLICANT
Plan Check Approved 1/10/2020 RAPHAEL ROSAS
Issued 1/21/2020 LADBS
CofO in Progress 5/21/2021 MICKEY YAMASHITA
Permit Finaled 7/29/2021 DAVID JAMES
CofO Issued 7/29/2021 DAVID JAMES
Permit Finaled 7/29/2021 DAVID JAMES

Permit Application Clearance Information

Low Impact Development Cleared 11/6/2019 ORVAL HERNANDEZ-MARCI
Construction near power lines Cleared 12/23/2019 RIDWAN HARDY
Construction within easement Cleared 12/23/2019 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 1/7/2020 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 1/7/2020 ADRIAN CASTRO
Sewer availability Cleared 1/7/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIO CUEVAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/28/2020 Corrections Issued MICKEY YAMASHITA
BUILDING-Rough-Frame 2/11/2020 Corrections Issued MICKEY YAMASHITA
Drywall Nailing 2/11/2020 Not Ready for Inspection MICKEY YAMASHITA
Final 2/11/2020 Not Ready for Inspection MICKEY YAMASHITA
Footing/Foundation/Slab 2/11/2020 Corrections Issued MICKEY YAMASHITA
Green Building Final 2/11/2020 Not Ready for Inspection MICKEY YAMASHITA
Green Building Rough 2/11/2020 Not Ready for Inspection MICKEY YAMASHITA
SGSOV-Seismic Gas S/O Valve 2/11/2020 SGSOV Not Ready MICKEY YAMASHITA
Smoke Detectors 2/11/2020 Not Ready for Inspection MICKEY YAMASHITA
Footing/Foundation/Slab 6/29/2020 Partial Inspection MICKEY YAMASHITA
Footing/Foundation/Slab 7/13/2020 Corrections Issued MICKEY YAMASHITA
Footing/Foundation/Slab 7/20/2020 Partial Approval MICKEY YAMASHITA
BUILDING-Rough-Frame 11/9/2020 Not Ready for Inspection MICKEY YAMASHITA
Drywall Nailing 11/9/2020 Not Ready for Inspection MICKEY YAMASHITA
Final 11/9/2020 Not Ready for Inspection MICKEY YAMASHITA
Footing/Foundation/Slab 11/9/2020 Approved MICKEY YAMASHITA
Green Building Final 11/9/2020 Not Ready for Inspection MICKEY YAMASHITA
Green Building Rough 11/9/2020 Not Ready for Inspection MICKEY YAMASHITA
SGSOV-Seismic Gas S/O Valve 11/9/2020 SGSOV Not Ready MICKEY YAMASHITA
Smoke Detectors 11/9/2020 Not Ready for Inspection MICKEY YAMASHITA
BUILDING-Rough-Frame 11/23/2020 Corrections Issued MICKEY YAMASHITA
Floor/Roof Diaphrgm/Shear Wall 11/23/2020 Not Ready for Inspection MICKEY YAMASHITA
Green Building Rough 11/23/2020 Approved MICKEY YAMASHITA
Green Building Rough 12/1/2020 Approved THOMAS WOODS
Posting Pre-Inspection 12/1/2020 Approved THOMAS WOODS
BUILDING-Rough-Frame 4/27/2021 Approved MICKEY YAMASHITA
Drywall Nailing 4/27/2021 Approved MICKEY YAMASHITA
Final 4/27/2021 Corrections Issued MICKEY YAMASHITA
Green Building Final 4/27/2021 Approved MICKEY YAMASHITA
SGSOV-Seismic Gas S/O Valve 4/27/2021 SGSOV Approved MICKEY YAMASHITA
Smoke Detectors 4/27/2021 Corrections Issued MICKEY YAMASHITA
Final 5/4/2021 Conditional Approval MICKEY YAMASHITA
Smoke Detectors 5/4/2021 Approved MICKEY YAMASHITA