6608 N MATILIJA AVE 91405
Certificate Information: 6608 N MATILIJA AVE 91405
- Application / Permit
- 19014-20000-05534
- Plan Check / Job No.
- B19VN17421
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 41'-6" X 25'-3" (IRREGULAR SHAPED) ADDITION & CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK DONE PER WFPP.
- Permit Issued
- Issued on 10/9/2020
- Issuing Office
- Current Status
- CofO Issued on 9/23/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/10/2019 | ARTIN ZARUKIAN |
| Corrections Issued | 10/10/2019 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 10/17/2019 | APPLICANT |
| Plan Check Approved | 9/28/2020 | ARTIN ZARUKIAN |
| Issued | 10/9/2020 | APPLICANT |
| CofO in Progress | 8/11/2021 | JENNIFER RABUCHIN |
| CofO in Progress | 8/25/2021 | MICHAEL TEMPLE |
| CofO in Progress | 9/2/2021 | JENNIFER RABUCHIN |
| CofO Issued | 9/23/2021 | MICHAEL SMITH |
| Permit Finaled | 9/23/2021 | MICHAEL SMITH |
Permit Application Clearance Information
| Low Impact Development | Cleared | 9/15/2020 | ORVAL HERNANDEZ-MARCI |
| Construction near power lines | Cleared | 9/16/2020 | RIDWAN HARDY |
| Address approval | Cleared | 9/18/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 9/18/2020 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 9/18/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 9/18/2020 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 10/15/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Footing/Foundation/Slab | 10/15/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| PLUMBING-Rough | 10/15/2020 | Partial Inspection | WILLIAM KUEHN |
| Pre-Inspection | 10/15/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Deputy Drilled-In Anchors | 10/21/2020 | Conditional Approval | DANIEL ORRANTE |
| Footing/Foundation/Slab | 10/21/2020 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 10/26/2020 | Approved | MATTHEW NELSON |
| Pre-Inspection | 10/26/2020 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 11/12/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| Green Building Rough | 11/12/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| PLUMBING-Rough | 11/12/2020 | Not Ready for Inspection | WILLIAM KUEHN |
| ELECTRICAL-Rough | 12/8/2020 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2020 | Partial Approval | MICHEL ABAJAN |
| HVAC-Rough | 12/8/2020 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 12/8/2020 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/14/2020 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2020 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 12/14/2020 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 12/14/2020 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2020 | Approved | DANIEL DREW |
| Insulation | 12/22/2020 | Approved | DANIEL DREW |
| Drywall Nailing | 12/30/2020 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 1/11/2021 | Approved | JENNIFER RABUCHIN |
| Shower Pan | 1/11/2021 | Approved | JENNIFER RABUCHIN |
| Sewer | 3/3/2021 | Partial Approval | BEAU COLLINS |
| Gas Test | 3/16/2021 | Not Ready for Inspection | JOHN STEPHENS |
| Sewer | 3/16/2021 | Approved | JOHN STEPHENS |
| Gas Test | 3/18/2021 | Corrections Issued | BRENDAN LOONEY |
| Pre-Inspection | 3/18/2021 | Partial Inspection | MICHAEL TEMPLE |
| Gas Test | 4/21/2021 | Approved | JOHN HAYES |
| Sewer | 4/21/2021 | Approved | JOHN HAYES |
| Final | 7/2/2021 | Corrections Issued | ARTHUR SARGSYAN |
| Green Building Final | 7/2/2021 | Approved | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 7/2/2021 | SGSOV Approved | ARTHUR SARGSYAN |
| Smoke Detectors | 7/2/2021 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Final | 8/12/2021 | Approved | JENNIFER RABUCHIN |
| Final | 8/12/2021 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Final | 8/12/2021 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 8/12/2021 | Approved | JENNIFER RABUCHIN |
| Final | 9/2/2021 | OK to Issue CofO | JENNIFER RABUCHIN |