12110 N SALEM DR 91344
Certificate Information: 12110 N SALEM DR 91344
- Application / Permit
- 19014-20000-05511
- Plan Check / Job No.
- B19VN17336
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 40' X 6" IN FRONT AND 76'-11"X 2' ON THE BACK AND MAJOR REMODEL OF ONE STORY SINGLE FAMILY DWELLING W/ (E) ATT. TWO CAR GARAGE. (RE-FRAME ENTIRE ROOF, REMODEL & EXPAND ALL BEDROOMS & ADD 8" X 15' PORCH IN FRONT. NFPA-13D FIRE SPRINKLERS REQUIRED, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 12/2/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/1/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/9/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/31/2019 | PARISA ZAHABI |
| Corrections Issued | 11/5/2019 | PARISA ZAHABI |
| Green Plans Picked Up | 11/7/2019 | APPLICANT |
| Quality Review Completed | 11/12/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 11/13/2019 | APPLICANT |
| Applicant returned to address corrections | 11/27/2019 | PARISA ZAHABI |
| Plan Check Approved | 12/2/2019 | PARISA ZAHABI |
| Issued | 12/2/2019 | LADBS |
| CofO in Progress | 3/24/2021 | DAVID SCANTLIN |
| Permit Finaled | 4/1/2021 | JOHN JANSON |
| CofO Issued | 4/1/2021 | JOHN JANSON |
| Permit Finaled | 4/1/2021 | JOHN JANSON |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 11/14/2019 | JOHN LIN |
| BHO/Hillside ordinance | Cleared | 11/14/2019 | JOHN LIN |
| BHO/Hillside ordinance | Cleared | 11/14/2019 | JOHN LIN |
| BHO/Hillside ordinance | Cleared | 11/14/2019 | JOHN LIN |
| BHO/Hillside ordinance | Cleared | 11/14/2019 | JOHN LIN |
| Distance to fire station | Cleared | 11/14/2019 | GEORGE SUCHAND |
| Eng Process Fee Ord 176,300 | Cleared | 11/14/2019 | JOHN LIN |
| Grading Pre-Inspection | Cleared | 11/14/2019 | BARTON HOLMES |
| Hydrant and Access approval | Cleared | 11/14/2019 | GEORGE SUCHAND |
| Sewer availability | Cleared | 11/14/2019 | JOHN LIN |
| Low Impact Development | Cleared | 11/22/2019 | MITESH PATEL |
| Green Code | Cleared | 11/26/2019 | PARISA ZAHABI |
| Roof/Waste drainage to street | Cleared | 11/26/2019 | APEKSHYA BAJRACHARYA |
| GPI Written Notices | Cleared | 11/27/2019 | PARISA ZAHABI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vahram, Keshishian; Lic. No.: C6482 | , |
Inspector Information
| JEFFREY PARD, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN BACK, (818) 774-4312 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/16/2020 | Approved | DAVID SCANTLIN |
| Footing/Foundation/Slab | 1/16/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| METHANE-Barrier | 1/16/2020 | Approved | DAVID SCANTLIN |
| METHANE-Subgrade | 1/16/2020 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 1/16/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| Footing/Foundation/Slab | 1/22/2020 | Approved | DAVID SCANTLIN |
| Underground Mechanical | 1/22/2020 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2020 | Corrections Issued | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| ELECTRICAL-Rough | 5/5/2020 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 5/5/2020 | Approved | DAVID SCANTLIN |
| Shower Pan | 5/5/2020 | Approved | DAVID SCANTLIN |
| HVAC-Rough | 5/12/2020 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 5/12/2020 | Partial Approval | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 5/15/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Rough | 5/15/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| Insulation | 5/15/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| METHANE-Rough | 5/15/2020 | Approved | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 5/15/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 5/27/2020 | Approved | DAVID SCANTLIN |
| Green Building Rough | 5/27/2020 | Approved | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 5/27/2020 | Approved | DAVID SCANTLIN |
| Drywall Nailing | 6/4/2020 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 6/9/2020 | Approved | DAVID SCANTLIN |
| Final | 10/8/2020 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 10/8/2020 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 10/8/2020 | SGSOV Approved | DAVID SCANTLIN |
| Smoke Detectors | 10/8/2020 | Approved | DAVID SCANTLIN |
| Final | 11/16/2020 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 3/15/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 3/18/2021 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 3/23/2021 | OK to Issue CofO | DAVID SCANTLIN |