12415 N LITTLER PL 91344

Certificate Information: 12415 N LITTLER PL 91344

Application / Permit
19014-20000-05510
Plan Check / Job No.
B19VN17335
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ENCLOSE 3' X 6' AREA AT FRONT OF (E) SINGLE FAMILY DWELLING FOR NEW ENTRY. NEW 22'-0" X 20'-0" TWO-CAR ATTACHED GARAGE ADDITION AT FRONT AND CONVERT (E) ATTACHED GARAGE AT REAR TO RECREATION ROOM. INTERIOR REMODEL TO RELOCATE BATHROOM AND CLOSET. RECONFIGURE (E) BEDROOM FOR NEW MASTER BEDROOM, BATHROOM AND CLOSET.
Permit Issued
Issued on 12/17/2019
Issuing Office
Valley
Current Status
CofO Issued on 8/21/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/9/2019 APPLICANT
Assigned to Plan Check Engineer 10/24/2019 ROSENDO MEDINA
Corrections Issued 10/29/2019 ROSENDO MEDINA
Quality Review Completed 10/29/2019 CHON CHIO KUO
Building Plans Picked Up 11/1/2019 APPLICANT
Applicant returned to address corrections 11/22/2019 ROSENDO MEDINA
Green Plans Picked Up 11/22/2019 APPLICANT
Plan Check Approved 12/17/2019 ROSENDO MEDINA
Issued 12/17/2019 LADBS
CofO in Progress 6/1/2021 MARK JOHNSON
CofO Issued 8/21/2021 MICHAEL SMITH
Permit Finaled 8/21/2021 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/22/2019 LEE GUILBEAUX
Grading Pre-Inspection Cleared 11/22/2019 BARTON HOLMES
Sewer availability Cleared 11/22/2019 LEE GUILBEAUX
Low Impact Development Cleared 12/13/2019 RYAN HUDSON
Green Code Cleared 12/16/2019 DAVID MATSON
Roof/Waste drainage to street Cleared 12/17/2019 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Ghavimi,, Rassoul Daneshvar; Lic. No.: C48282 7007 SHADETREE LANE      WEST HILLS, CA 91307

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/16/2020 Not Ready for Inspection MARK JOHNSON
Footing/Foundation/Slab 1/21/2020 Approved MARK JOHNSON
ELECTRICAL-Rough 2/18/2020 Approved MARK JOHNSON
Green Building Rough 2/18/2020 Approved MARK JOHNSON
HVAC-Rough 2/18/2020 Approved MARK JOHNSON
PLUMBING-Rough 2/18/2020 Approved MARK JOHNSON
Shower Pan 2/18/2020 Approved MARK JOHNSON
Wood Frame 9/9/2020 Not Ready for Inspection MARK JOHNSON
Deputy Wood Construction 9/11/2020 Conditional Approval DANIEL ORRANTE
BUILDING-Rough-Frame 9/15/2020 Approved MARK JOHNSON
Interior/Exterior Lathing 9/24/2020 Approved MARK JOHNSON
Insulation 9/30/2020 Approved MARK JOHNSON
Drywall Nailing 10/7/2020 Approved MARK JOHNSON
Interior/Exterior Lathing 10/16/2020 Approved MARK JOHNSON
Final 5/12/2021 Corrections Issued MARK JOHNSON
Green Building Final 5/12/2021 Approved MARK JOHNSON
SGSOV-Seismic Gas S/O Valve 5/12/2021 SGSOV Approved MARK JOHNSON
Smoke Detectors 5/12/2021 Approved MARK JOHNSON
Final 5/20/2021 Not Ready for Inspection MARK JOHNSON
Final 6/1/2021 OK to Issue CofO MARK JOHNSON