4255 E RAYNOL ST 90032
Certificate Information: 4255 E RAYNOL ST 90032
- Application / Permit
- 19014-20000-05497
- Plan Check / Job No.
- B19VN17284
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 3-STORY SFD W/ ATTACHED 2-CAR GARAGE & MECHANICAL CAR LIFT (NFPA-13D FIRE SPRINKLERS THROUGHOUT)
- Permit Issued
- Issued on 2/13/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/13/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/8/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/17/2019 | NILOOFAR MEHRAIN |
| Corrections Issued | 10/21/2019 | NILOOFAR MEHRAIN |
| Green Plans Picked Up | 10/21/2019 | APPLICANT |
| Quality Review Completed | 10/23/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 10/23/2019 | APPLICANT |
| Applicant returned to address corrections | 1/9/2020 | NILOOFAR MEHRAIN |
| Applicant returned to address corrections | 1/17/2020 | NILOOFAR MEHRAIN |
| Plan Check Approved | 2/10/2020 | NILOOFAR MEHRAIN |
| Issued | 2/13/2020 | LADBS |
| CofO in Progress | 12/2/2021 | OSVALDO PARAMO |
| CofO in Progress | 12/2/2021 | OSVALDO PARAMO |
| Permit Finaled | 12/13/2021 | DEROLD HAUFF |
| CofO Issued | 12/13/2021 | DEROLD HAUFF |
| Permit Finaled | 12/13/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/15/2019 | ADRIAN CASTRO |
| BHO/Hillside ordinance | Cleared | 11/15/2019 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2019 | ADRIAN CASTRO |
| Permit | Cleared | 11/15/2019 | ADRIAN CASTRO |
| "D" conditions | Cleared | 11/18/2019 | SOPHIE GABEL-SCHEINBAU |
| "Q" conditions | Cleared | 11/18/2019 | SOPHIE GABEL-SCHEINBAU |
| Hydrant and Access approval | Cleared | 11/18/2019 | JEREMY CARTER |
| Miscellaneous | Cleared | 11/18/2019 | SOPHIE GABEL-SCHEINBAU |
| ZI | Cleared | 11/18/2019 | SOPHIE GABEL-SCHEINBAU |
| Disturb/Remove Protected Trees | Cleared | 11/19/2019 | JOHN KIM |
| Trees in Parkway | Cleared | 11/19/2019 | JOHN KIM |
| BHO/Hillside ordinance | Cleared | 11/26/2019 | JAMES MORALEZ |
| Sewer availability | Cleared | 11/26/2019 | JAMES MORALEZ |
| BHO/Hillside ordinance | Cleared | 12/3/2019 | CELINA MORENO |
| Low Impact Development | Cleared | 12/13/2019 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 12/13/2019 | EMIL KYUPELYAN |
| Green Code | Cleared | 12/19/2019 | AARON COSTA |
| Excavation more than 5-ft deep | Cleared | 1/9/2020 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 1/9/2020 | NILOOFAR MEHRAIN |
| Grading Pre-Inspection | Cleared | 1/9/2020 | NILOOFAR MEHRAIN |
Contact Information
| Contractor | M C A B Quality Homes Inc; Lic. No.: 1044578-B | 1432 MAYFLOWER AVE ARCADIA, CA 91006 |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 1950 SAWTELLE BLVD STE 175 LOS ANGELES, CA 90025 |
| Engineer | Nabilsi,, Haytham Mahmood; Lic. No.: GE2375 | 12935 CANYONWIND RD RIVERSIDE, CA 92503 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/20/2020 | Approved | OSVALDO PARAMO |
| Piling/Pier/Caisson | 2/26/2020 | Partial Approval | OSVALDO PARAMO |
| Deputy Reinf. Concrete | 2/28/2020 | Partial Approval | OSVALDO PARAMO |
| Piling/Pier/Caisson | 3/2/2020 | Approved | OSVALDO PARAMO |
| Deputy Reinf. Concrete | 3/6/2020 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 3/6/2020 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 3/20/2020 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 4/1/2020 | Partial Approval | OSVALDO PARAMO |
| Masonry Wall/Backfill | 4/1/2020 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 4/1/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 4/10/2020 | No Access for Inspection | OSVALDO PARAMO |
| Footing/Foundation/Slab | 4/14/2020 | Partial Approval | OSVALDO PARAMO |
| Deputy Reinf. Concrete | 4/15/2020 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Deputy Reinf. Masonry | 4/15/2020 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 4/28/2020 | Partial Approval | HAMIK HARTOUNIAN |
| Deputy Reinf. Concrete | 4/29/2020 | Partial Approval | OSVALDO PARAMO |
| Deputy Reinf. Masonry | 5/13/2020 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 5/14/2020 | Partial Approval | OSVALDO PARAMO |
| Masonry Wall/Backfill | 5/14/2020 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2020 | Partial Approval | OSVALDO PARAMO |
| Green Building Rough | 6/5/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 6/5/2020 | Partial Approval | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 6/5/2020 | Not Ready for Inspection | OSVALDO PARAMO |
| Deputy Reinf. Concrete | 6/10/2020 | Partial Approval | OSVALDO PARAMO |
| Insulation | 6/11/2020 | Partial Approval | OSVALDO PARAMO |
| Reinforced Masonry Frame | 6/11/2020 | Partial Approval | OSVALDO PARAMO |
| Deputy Reinf. Concrete | 6/30/2020 | Partial Approval | OSVALDO PARAMO |
| Masonry Wall/Backfill | 7/6/2020 | Partial Approval | SCOTT FINNILA |
| Wood Frame | 7/17/2020 | Partial Approval | OSVALDO PARAMO |
| Deputy Drilled-In Anchors | 8/26/2020 | Partial Approval | OSVALDO PARAMO |
| Wood Frame | 9/4/2020 | Partial Inspection | OSVALDO PARAMO |
| Deputy Wood Construction | 9/9/2020 | Partial Approval | OSVALDO PARAMO |
| PLUMBING-Rough | 9/10/2020 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 9/11/2020 | Approved | OSVALDO PARAMO |
| HVAC-Rough | 9/15/2020 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 9/24/2020 | Conditional Approval | OSVALDO PARAMO |
| Sewer | 9/24/2020 | Corrections Issued | OSVALDO PARAMO |
| Interior/Exterior Lathing | 10/1/2020 | Partial Approval | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 10/7/2020 | Approved | OSVALDO PARAMO |
| Green Building Rough | 10/7/2020 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 10/7/2020 | Approved | OSVALDO PARAMO |
| Insulation | 10/14/2020 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 10/19/2020 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 10/19/2020 | Approved | OSVALDO PARAMO |
| PLUMBING-Final | 1/22/2021 | Corrections Issued | OSVALDO PARAMO |
| HVAC-Final | 2/18/2021 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 3/17/2021 | Corrections Issued | OSVALDO PARAMO |
| ELECTRICAL-Final | 7/20/2021 | Approved | OSVALDO PARAMO |
| Final | 7/20/2021 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 7/20/2021 | Approved | OSVALDO PARAMO |
| Green Building Final | 7/20/2021 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 7/20/2021 | SGSOV Approved | OSVALDO PARAMO |
| Service/Power Release | 7/20/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| Smoke Detectors | 7/20/2021 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Final | 7/23/2021 | Approved | COREY HUPP |
| Final | 11/24/2021 | Corrections Issued | HAMIK HARTOUNIAN |
| Service/Power Release | 11/24/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Smoke Detectors | 11/24/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 12/1/2021 | OK to Issue CofO | OSVALDO PARAMO |
| Service/Power Release | 12/1/2021 | Approved | OSVALDO PARAMO |
| Smoke Detectors | 12/1/2021 | Approved | OSVALDO PARAMO |