1931 W MELLON AVE 90039
Certificate Information: 1931 W MELLON AVE 90039
- Application / Permit
- 19014-20000-05469
- Plan Check / Job No.
- B19VN17179
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED (8' X 30') ADDITION TO (E) SFD TO ENLARGE LIVING ROOM AND MASTER BEDROOM. REMODEL (E) SFD TO REMODEL BEDROOMS, BATHROOMS, KITCHEN & DINING ROOM AND (N) LAUNDRY ROOM. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 1/24/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2019 | RAPHAEL ROSAS |
| Corrections Issued | 10/7/2019 | RAPHAEL ROSAS |
| Plan Check Approved | 10/8/2019 | JENNIFER LEE |
| Issued | 1/24/2020 | LADBS |
| CofO in Progress | 5/14/2021 | KATHRYN BUTTERWORTH |
| Permit Finaled | 9/29/2021 | DEROLD HAUFF |
| Permit Finaled | 9/29/2021 | DEROLD HAUFF |
| CofO Issued | 9/29/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/8/2019 | JOHN LIN |
| Roof/Waste drainage to street | Cleared | 10/8/2019 | JOHN LIN |
| Sewer availability | Cleared | 10/8/2019 | JOHN LIN |
| ZI | Cleared | 10/8/2019 | DAISY BENICIA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVENUE LONG BEACH, CA 90813 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/10/2020 | Corrections Issued | AJA COLLAY |
| Footing/Foundation/Slab | 2/25/2020 | Not Ready for Inspection | AJA COLLAY |
| Footing/Foundation/Slab | 3/4/2020 | Conditional Approval | AJA COLLAY |
| Floor/Roof Diaphrgm/Shear Wall | 3/12/2020 | Approved | AJA COLLAY |
| Green Building Rough | 3/12/2020 | Not Ready for Inspection | AJA COLLAY |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2020 | Approved | AJA COLLAY |
| Floor/Roof Diaphrgm/Shear Wall | 4/16/2020 | Partial Approval | STUART CHAPMAN |
| HVAC-Rough | 4/16/2020 | Corrections Issued | STUART CHAPMAN |
| ELECTRICAL-Rough | 4/24/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| HVAC-Rough | 4/24/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| PLUMBING-Rough | 4/24/2020 | Approved | KATHRYN BUTTERWORTH |
| Wood Frame | 4/24/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 5/11/2020 | Not Ready for Inspection | MATTHEW NUCKOLLS |
| Wood Frame | 5/11/2020 | Corrections Issued | MATTHEW NUCKOLLS |
| Wood Frame | 5/15/2020 | Corrections Issued | STUART CHAPMAN |
| BUILDING-Rough-Frame | 6/8/2020 | Conditional Approval | DAVID CHAN |
| Green Building Rough | 6/8/2020 | Approved | DAVID CHAN |
| HVAC-Rough | 6/8/2020 | Partial Inspection | DAVID CHAN |
| MERV13>=Rough | 6/8/2020 | Partial Inspection | DAVID CHAN |
| BUILDING-Rough-Frame | 6/15/2020 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Insulation | 6/15/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Insulation | 6/16/2020 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 6/22/2020 | Conditional Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 6/22/2020 | Partial Approval | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 7/2/2020 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Rough | 7/2/2020 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 7/2/2020 | Approved | KATHRYN BUTTERWORTH |
| MERV13>=Rough | 7/2/2020 | Approved | KATHRYN BUTTERWORTH |
| ELECTRICAL-Final | 4/5/2021 | Approved | KATHRYN BUTTERWORTH |
| Final | 4/5/2021 | Corrections Issued | KATHRYN BUTTERWORTH |
| Footing/Foundation/Slab | 4/5/2021 | Approved | KATHRYN BUTTERWORTH |
| Green Building Final | 4/5/2021 | Approved | KATHRYN BUTTERWORTH |
| HVAC-Final | 4/5/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| MERV13>=Final | 4/5/2021 | Approved | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 4/5/2021 | Approved | KATHRYN BUTTERWORTH |
| SGSOV-Seismic Gas S/O Valve | 4/5/2021 | SGSOV Approved | KATHRYN BUTTERWORTH |
| Smoke Detectors | 4/5/2021 | Approved | KATHRYN BUTTERWORTH |
| Final | 4/9/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| HVAC-Final | 4/9/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| PLUMBING-Final | 4/9/2021 | Approved | KATHRYN BUTTERWORTH |
| Final | 4/20/2021 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 5/14/2021 | OK to Issue CofO | KATHRYN BUTTERWORTH |
| Gas Test | 8/11/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |