2420 N GRIFFITH PARK BLVD 90039

Certificate Information: 2420 N GRIFFITH PARK BLVD 90039

Application / Permit
19014-20000-05464
Plan Check / Job No.
B19VN17162
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL & 16'9-1/2"X34'10" 2ND FLOOR ADDITION TO (E) SFD
Permit Issued
Issued on 3/10/2021
Issuing Office
Metro
Current Status
CofO Issued on 7/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/7/2019 APPLICANT
Assigned to Plan Check Engineer 10/24/2019 MARVEL DELACRUZ
Corrections Issued 10/28/2019 MARVEL DELACRUZ
Quality Review Completed 10/29/2019 GUANG MIN TUNG
Green Plans Picked Up 11/5/2019 APPLICANT
Applicant returned to address corrections 8/11/2020 MARVEL DELACRUZ
Applicant returned to address corrections 12/23/2020 MARVEL DELACRUZ
Applicant returned to address corrections 12/29/2020 MARVEL DELACRUZ
Applicant returned to address corrections 2/23/2021 MARVEL DELACRUZ
Plan Check Approved 2/25/2021 MARVEL DELACRUZ
Issued 3/10/2021 APPLICANT
Building Plans Picked Up 3/11/2021 APPLICANT
CofO in Progress 7/8/2025 ENRIQUE MIRELES
Permit Finaled 7/15/2025 DEROLD HAUFF
CofO Issued 7/15/2025 DEROLD HAUFF
Permit Finaled 7/15/2025 DEROLD HAUFF

Permit Application Clearance Information

GPI Written Notices Cleared 10/25/2019 MARVEL DELACRUZ
Grading Pre-Inspection Cleared 10/25/2019 MARVEL DELACRUZ
Green Code Cleared 7/24/2020 MICHAEL AYERS
BHO/Hillside ordinance Cleared 8/11/2020 CECILIO NAVARRO
BHO/Hillside ordinance Cleared 8/11/2020 CECILIO NAVARRO
BHO/Hillside ordinance Cleared 8/11/2020 CECILIO NAVARRO
Sewer availability Cleared 8/11/2020 CECILIO NAVARRO
Distance to fire station Cleared 8/31/2020 MATTHEW CRAIG
Hydrant and Access approval Cleared 8/31/2020 MATTHEW CRAIG
Low Impact Development Cleared 11/18/2020 ROBIN YAMADA
Eng Process Fee Ord 176,300 Cleared 12/8/2020 CECILIO NAVARRO
Roof/Waste drainage to street Cleared 12/8/2020 CECILIO NAVARRO
Flood clearance Cleared 2/2/2021 BRYAN GATHUKA

Contact Information

Contractor Jennings Bo L; Lic. No.: 735782-B 3315 CASTERA AVENUE      GLENDALE, CA 91208
Engineer Irvine,, Jon Alan; Lic. No.: GE2891 145 N SIERRA MADRE BLVD STE 1      PASADENA, CA 91107
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026
Engineer Plouff,, Kacie Allison; Lic. No.: L9013 27821 FREMONT COURT 6      VALENCIA, CA 91355
Geologist Irvine,, Jon A; Lic. No.: EG1691 819 W HERITAGE OAK CT      ALTADENA, CA 91001

Inspector Information

ENRIQUE MIRELES, (213) 202-3438 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

FLOOD-Elevation Certificate 3/23/2021 Approved JOSEPH MCGARRY
Footing/Foundation/Slab 3/23/2021 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 4/7/2021 Partial Approval JOSEPH MCGARRY
Deputy Reinf. Concrete 4/8/2021 Partial Approval JOSEPH MCGARRY
Deputy Drilled-In Anchors 4/30/2021 No Access for Inspection CHRISTOPHER DELLEFIELD
Deputy Drilled-In Anchors 5/6/2021 Conditional Approval AMY COLIN
Deputy Other (see comments) 5/6/2021 Approved WILLIAM WREN
Deputy Reinf. Concrete 5/7/2021 No Access for Inspection ELMER BLAND
Footing/Foundation/Slab 5/10/2021 Partial Approval JOSEPH MCGARRY
Footing/Foundation/Slab 6/16/2021 Approved JOSEPH MCGARRY
Floor/Roof Diaphrgm/Shear Wall 9/22/2021 Partial Approval JOSEPH MCGARRY
Deputy Drilled-In Anchors 10/14/2021 Conditional Approval CHARLES BOGHOSKHAN
BUILDING-Rough-Frame 10/15/2021 Partial Approval JOSEPH MCGARRY
ELECTRICAL-Rough 10/15/2021 Partial Approval JOSEPH MCGARRY
FLOOD-Proofing Certificate 10/15/2021 Approved JOSEPH MCGARRY
Green Building Rough 10/15/2021 Approved JOSEPH MCGARRY
HVAC-Rough 10/15/2021 Approved JOSEPH MCGARRY
PLUMBING-Rough 10/15/2021 Approved JOSEPH MCGARRY
Verify Sprinkler Sign Off 10/15/2021 Not Ready for Inspection JOSEPH MCGARRY
Insulation 11/8/2021 Conditional Approval JOSEPH MCGARRY
Interior/Exterior Lathing 12/1/2021 Partial Approval JOSEPH MCGARRY
Drywall Nailing 12/7/2021 Corrections Issued CRAIG DAVIS
Deputy Drilled-In Anchors 1/27/2022 Approved JOSEPH MCGARRY
Drywall Nailing 1/28/2022 Approved JOSEPH MCGARRY
Shower Pan 1/28/2022 Approved JOSEPH MCGARRY
Deputy Drilled-In Anchors 2/1/2022 Partial Approval JOSEPH MCGARRY
Deputy Wood Construction 2/10/2022 Partial Approval JOSEPH MCGARRY
Interior/Exterior Lathing 3/21/2022 Partial Approval JOSEPH MCGARRY
Interior/Exterior Lathing 4/6/2022 Approved ARTHUR SARGSYAN
BUILDING-Rough-Frame 10/1/2024 Approved ENRIQUE MIRELES
Final 10/1/2024 Corrections Issued ENRIQUE MIRELES
Green Building Final 10/1/2024 Approved ENRIQUE MIRELES
SGSOV-Seismic Gas S/O Valve 10/1/2024 SGSOV Approved ENRIQUE MIRELES
Smoke Detectors 10/1/2024 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 10/1/2024 Approved ENRIQUE MIRELES
Final 10/16/2024 Not Ready for Inspection ENRIQUE MIRELES
Wood Frame 6/2/2025 Approved ENRIQUE MIRELES
Final 6/4/2025 OK to Issue CofO ENRIQUE MIRELES