2420 N GRIFFITH PARK BLVD 90039
Certificate Information: 2420 N GRIFFITH PARK BLVD 90039
- Application / Permit
- 19014-20000-05464
- Plan Check / Job No.
- B19VN17162
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL & 16'9-1/2"X34'10" 2ND FLOOR ADDITION TO (E) SFD
- Permit Issued
- Issued on 3/10/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2019 | MARVEL DELACRUZ |
| Corrections Issued | 10/28/2019 | MARVEL DELACRUZ |
| Quality Review Completed | 10/29/2019 | GUANG MIN TUNG |
| Green Plans Picked Up | 11/5/2019 | APPLICANT |
| Applicant returned to address corrections | 8/11/2020 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 12/23/2020 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 12/29/2020 | MARVEL DELACRUZ |
| Applicant returned to address corrections | 2/23/2021 | MARVEL DELACRUZ |
| Plan Check Approved | 2/25/2021 | MARVEL DELACRUZ |
| Issued | 3/10/2021 | APPLICANT |
| Building Plans Picked Up | 3/11/2021 | APPLICANT |
| CofO in Progress | 7/8/2025 | ENRIQUE MIRELES |
| Permit Finaled | 7/15/2025 | DEROLD HAUFF |
| CofO Issued | 7/15/2025 | DEROLD HAUFF |
| Permit Finaled | 7/15/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 10/25/2019 | MARVEL DELACRUZ |
| Grading Pre-Inspection | Cleared | 10/25/2019 | MARVEL DELACRUZ |
| Green Code | Cleared | 7/24/2020 | MICHAEL AYERS |
| BHO/Hillside ordinance | Cleared | 8/11/2020 | CECILIO NAVARRO |
| BHO/Hillside ordinance | Cleared | 8/11/2020 | CECILIO NAVARRO |
| BHO/Hillside ordinance | Cleared | 8/11/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 8/11/2020 | CECILIO NAVARRO |
| Distance to fire station | Cleared | 8/31/2020 | MATTHEW CRAIG |
| Hydrant and Access approval | Cleared | 8/31/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 11/18/2020 | ROBIN YAMADA |
| Eng Process Fee Ord 176,300 | Cleared | 12/8/2020 | CECILIO NAVARRO |
| Roof/Waste drainage to street | Cleared | 12/8/2020 | CECILIO NAVARRO |
| Flood clearance | Cleared | 2/2/2021 | BRYAN GATHUKA |
Contact Information
| Contractor | Jennings Bo L; Lic. No.: 735782-B | 3315 CASTERA AVENUE GLENDALE, CA 91208 |
| Engineer | Irvine,, Jon Alan; Lic. No.: GE2891 | 145 N SIERRA MADRE BLVD STE 1 PASADENA, CA 91107 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
| Engineer | Plouff,, Kacie Allison; Lic. No.: L9013 | 27821 FREMONT COURT 6 VALENCIA, CA 91355 |
| Geologist | Irvine,, Jon A; Lic. No.: EG1691 | 819 W HERITAGE OAK CT ALTADENA, CA 91001 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| FLOOD-Elevation Certificate | 3/23/2021 | Approved | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 3/23/2021 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 4/7/2021 | Partial Approval | JOSEPH MCGARRY |
| Deputy Reinf. Concrete | 4/8/2021 | Partial Approval | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 4/30/2021 | No Access for Inspection | CHRISTOPHER DELLEFIELD |
| Deputy Drilled-In Anchors | 5/6/2021 | Conditional Approval | AMY COLIN |
| Deputy Other (see comments) | 5/6/2021 | Approved | WILLIAM WREN |
| Deputy Reinf. Concrete | 5/7/2021 | No Access for Inspection | ELMER BLAND |
| Footing/Foundation/Slab | 5/10/2021 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 6/16/2021 | Approved | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2021 | Partial Approval | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 10/14/2021 | Conditional Approval | CHARLES BOGHOSKHAN |
| BUILDING-Rough-Frame | 10/15/2021 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 10/15/2021 | Partial Approval | JOSEPH MCGARRY |
| FLOOD-Proofing Certificate | 10/15/2021 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 10/15/2021 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 10/15/2021 | Approved | JOSEPH MCGARRY |
| PLUMBING-Rough | 10/15/2021 | Approved | JOSEPH MCGARRY |
| Verify Sprinkler Sign Off | 10/15/2021 | Not Ready for Inspection | JOSEPH MCGARRY |
| Insulation | 11/8/2021 | Conditional Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 12/1/2021 | Partial Approval | JOSEPH MCGARRY |
| Drywall Nailing | 12/7/2021 | Corrections Issued | CRAIG DAVIS |
| Deputy Drilled-In Anchors | 1/27/2022 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 1/28/2022 | Approved | JOSEPH MCGARRY |
| Shower Pan | 1/28/2022 | Approved | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 2/1/2022 | Partial Approval | JOSEPH MCGARRY |
| Deputy Wood Construction | 2/10/2022 | Partial Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 3/21/2022 | Partial Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 4/6/2022 | Approved | ARTHUR SARGSYAN |
| BUILDING-Rough-Frame | 10/1/2024 | Approved | ENRIQUE MIRELES |
| Final | 10/1/2024 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 10/1/2024 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 10/1/2024 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 10/1/2024 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 10/1/2024 | Approved | ENRIQUE MIRELES |
| Final | 10/16/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Wood Frame | 6/2/2025 | Approved | ENRIQUE MIRELES |
| Final | 6/4/2025 | OK to Issue CofO | ENRIQUE MIRELES |