1248 1/2 W 64TH ST 90044

Certificate Information: 1248 1/2 W 64TH ST 90044

Application / Permit
19014-20000-05421
Plan Check / Job No.
B19VN17020
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Remove 4'-5" x 18', add irr 32' x 24' to and convert detached garage to accessory dwelling unit. AB 494 & SB229
Permit Issued
Issued on 3/17/2020
Issuing Office
South Los Angeles
Current Status
CofO Issued on 4/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/4/2019 APPLICANT
Assigned to Plan Check Engineer 10/4/2019 ANGELICA DAVE
Corrections Issued 10/4/2019 ANGELICA DAVE
Plan Check Approved 12/20/2019 ANGELICA MARTINEZ
Issued 3/17/2020 LADBS
Permit Finaled 4/23/2026 DEROLD HAUFF
CofO Issued 4/23/2026 DEROLD HAUFF
Permit Finaled 4/23/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/8/2019 JEANIE LAM
ZA Case Cleared 10/8/2019 ANNA VIDAL
Construction near power lines Cleared 12/2/2019 OSCAR CASTRO
Low Impact Development Cleared 12/19/2019 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 12/19/2019 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 3/17/2020 JAMES KHO
Sewer availability Cleared 3/17/2020 JAMES KHO

Contact Information

Contractor Daniel Pascuale; Lic. No.: 573067-B 18729 CLARK DALE AVE #C      ARTESIA, CA 90701

Inspector Information

BARRY HACHE, (213) 202-9851 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/23/2020 Not Ready for Inspection COREY HUPP
PLUMBING-Rough 3/23/2020 Partial Approval COREY HUPP
Excavation/Setback/Form/Re-Bar 3/27/2020 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 3/31/2020 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 4/13/2020 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 4/22/2020 Corrections Issued FREDDIE RIVERA
ELECTRICAL-Rough 4/22/2020 Approved FREDDIE RIVERA
Green Building Rough 4/22/2020 Not Ready for Inspection FREDDIE RIVERA
HVAC-Rough 4/22/2020 Approved FREDDIE RIVERA
PLUMBING-Rough 4/22/2020 Approved FREDDIE RIVERA
Green Building Rough 4/24/2020 Approved FREDDIE RIVERA
Insulation 4/24/2020 Approved FREDDIE RIVERA
Wood Frame 4/24/2020 Approved FREDDIE RIVERA
Interior/Exterior Lathing 5/7/2020 Not Ready for Inspection ROBERT MCDOWELL
Drywall Nailing 5/11/2020 Not Ready for Inspection SABAS ALONSO
Interior/Exterior Lathing 5/11/2020 Approved SABAS ALONSO
Drywall Nailing 5/13/2020 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 6/29/2020 Approved FREDDIE RIVERA
Final 6/29/2020 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 6/29/2020 Approved FREDDIE RIVERA
Green Building Final 6/29/2020 Not Ready for Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 6/29/2020 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 6/29/2020 Approved FREDDIE RIVERA
Final 7/6/2020 Not Ready for Inspection FREDDIE RIVERA
Green Building Final 7/6/2020 Not Ready for Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 7/6/2020 SGSOV Not Ready FREDDIE RIVERA
Final 7/28/2020 Conditional Approval FREDDIE RIVERA
Green Building Final 7/28/2020 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 7/28/2020 SGSOV Approved FREDDIE RIVERA