4602 S 11TH AVE 90043

Certificate Information: 4602 S 11TH AVE 90043

Application / Permit
19014-20000-05406
Plan Check / Job No.
B19VN16972
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
21'-11" X 35'-1" IRREGULAR SHAPED SECOND STORY ADDITION TO EXISTING SINGLE FAMILY DWELLING' ADD 24'-5" X 33' ROOF DECK
Permit Issued
Issued on 11/7/2019
Issuing Office
Valley
Current Status
CofO Issued on 6/14/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/3/2019 APPLICANT
Green Plans Picked Up 10/16/2019 APPLICANT
Assigned to Plan Check Engineer 10/17/2019 SELLA BENYAMIN
Corrections Issued 10/21/2019 SELLA BENYAMIN
Quality Review Completed 10/21/2019 STEVEN KIM
Building Plans Picked Up 10/24/2019 APPLICANT
Plan Check Approved 11/7/2019 SELLA BENYAMIN
Issued 11/7/2019 LADBS
CofO in Progress 6/4/2024 ANTHONY EGSON
CofO Issued 6/14/2024 DEROLD HAUFF
Permit Finaled 6/14/2024 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 10/30/2019 ELAINE LEI
Roof/Waste drainage to street Cleared 10/30/2019 ELAINE LEI
Sewer availability Cleared 10/30/2019 ELAINE LEI
Green Code Cleared 11/4/2019 DAVID MATSON

Contact Information

Contractor Supreme Remodeling Inc; Lic. No.: 939981-B 14545 VICTORY BLVD UNIT 401      VAN NUYS, CA 91411

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/3/2019 Conditional Approval COREY HUPP
Footing/Foundation/Slab 12/6/2019 Partial Inspection COREY HUPP
Footing/Foundation/Slab 12/11/2019 Approved COREY HUPP
Drywall Nailing 1/17/2020 Not Ready for Inspection COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 1/17/2020 Not Ready for Inspection COREY HUPP
Floor/Roof Diaphrgm/Shear Wall 1/22/2020 Partial Approval ROBERT MCDOWELL
Pre-Inspection 1/22/2020 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 7/13/2020 Partial Inspection FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 7/17/2020 Approved FREDDIE RIVERA
Pre-Inspection 7/17/2020 Corrections Issued FREDDIE RIVERA
Rough-Elec/Plmb/HVAC 9/23/2020 Not Ready for Inspection DAVID FEILER
Rough-Elec/Plmb/HVAC 10/13/2020 Partial Inspection DAVID FEILER
HVAC-Rough 10/23/2020 Approved DAVID FEILER
PLUMBING-Rough 10/23/2020 Partial Approval DAVID FEILER
Interior/Exterior Lathing 11/13/2020 Corrections Issued DAVID FEILER
Interior/Exterior Lathing 11/23/2020 Partial Approval DAVID FEILER
BUILDING-Rough-Frame 12/4/2020 Approved DAVID FEILER
Green Building Rough 12/4/2020 Approved DAVID FEILER
Shower Pan 12/4/2020 Approved DAVID FEILER
Insulation 12/18/2020 Approved DAVID FEILER
Gas Test 1/11/2021 Approved STUART CHAPMAN
Pre-Inspection 5/12/2022 Corrections Issued ANTHONY EGSON
Pre-Inspection 5/13/2022 Corrections Issued ANTHONY EGSON
Final 10/25/2023 No Access for Inspection ANTHONY EGSON
Green Building Final 10/25/2023 No Access for Inspection ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 10/25/2023 SGSOV Not Ready ANTHONY EGSON
Smoke Detectors 10/25/2023 No Access for Inspection ANTHONY EGSON
Final 10/30/2023 Corrections Issued ANTHONY EGSON
Special/Order Compliance 10/30/2023 Not Ready for Inspection ANTHONY EGSON
Final 4/10/2024 Corrections Issued ANTHONY EGSON
Green Building Final 4/10/2024 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 4/10/2024 SGSOV Approved ANTHONY EGSON
Smoke Detectors 4/10/2024 Approved ANTHONY EGSON
Final 5/15/2024 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Final 6/3/2024 Approved ANTHONY EGSON
Final 6/3/2024 OK to Issue CofO ANTHONY EGSON
HVAC-Final 6/3/2024 Approved ANTHONY EGSON
PLUMBING-Final 6/3/2024 Approved ANTHONY EGSON