3330 W GLENHURST AVE 90039

Certificate Information: 3330 W GLENHURST AVE 90039

Application / Permit
19014-20000-05377
Plan Check / Job No.
B19VN16840
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
34' X 24'-11" IRREGULAR SHAPE ADDITION TO (E) SINGLE FAMILY DWELLING FOR TWO NEW BEDROOMS, FULL BATHROOM, AND MASTER CLOSET. INTERIOR REMODEL TO RECONFIGURE (E) KITCHEN, DINING ROOM, AND BEDROOM. FULLY SPRINKLERED PER NFPA 13D.
Permit Issued
Issued on 12/2/2019
Issuing Office
Valley
Current Status
CofO Issued on 12/18/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/2/2019 APPLICANT
Green Plans Picked Up 10/16/2019 APPLICANT
Assigned to Plan Check Engineer 10/17/2019 ROSENDO MEDINA
Corrections Issued 10/21/2019 ROSENDO MEDINA
Quality Review Completed 10/22/2019 CHON CHIO KUO
Building Plans Picked Up 10/23/2019 APPLICANT
Applicant returned to address corrections 11/22/2019 ROSENDO MEDINA
Plan Check Approved 11/25/2019 ROSENDO MEDINA
Issued 12/2/2019 LADBS
CofO in Progress 12/17/2020 HAMIK HARTOUNIAN
Permit Finaled 12/18/2020 DEROLD HAUFF
Permit Finaled 12/18/2020 DEROLD HAUFF
CofO Issued 12/18/2020 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/22/2019 GUILLERMO PETRA
Green Code Cleared 11/22/2019 AARON COSTA
Sewer availability Cleared 11/22/2019 GUILLERMO PETRA
Hydrant and Access approval Cleared 11/25/2019 GEORGE SUCHAND
Low Impact Development Cleared 11/25/2019 MITESH PATEL
Roof/Waste drainage to street Cleared 11/25/2019 LEE GUILBEAUX

Contact Information

Architect Huddy,, Robert Francis; Lic. No.: C20474 3648 GOODLAND DR      STUDIO CITY, CA 91604
Contractor Owner-Builder       ,
Engineer Shagirian,, Ashot; Lic. No.: C79415 11337 RUNNYMEDE ST      SUN VALLEY, CA 91352

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/3/2019 Conditional Approval HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 12/3/2019 No Result Entered ELMER BLAND
Footing/Foundation/Slab 12/3/2019 No Result Entered ELMER BLAND
Excavation/Setback/Form/Re-Bar 12/10/2019 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 12/10/2019 Not Ready for Inspection HAMIK HARTOUNIAN
Grounding or Bonding 12/10/2019 Corrections Issued HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 12/18/2019 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 12/18/2019 Approved HAMIK HARTOUNIAN
Grounding or Bonding 12/18/2019 Partial Approval HAMIK HARTOUNIAN
Grounding or Bonding 12/19/2019 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 1/16/2020 Partial Approval HAMIK HARTOUNIAN
Green Building Rough 1/16/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Underground Mechanical 1/16/2020 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 1/21/2020 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 2/27/2020 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 3/2/2020 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 3/2/2020 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 3/2/2020 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 4/3/2020 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 4/3/2020 Approved HAMIK HARTOUNIAN
Gas Test 4/3/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Rough 4/3/2020 Partial Approval HAMIK HARTOUNIAN
HVAC-Rough 4/3/2020 Conditional Approval HAMIK HARTOUNIAN
Deputy Wood Construction 4/6/2020 Conditional Approval HAMIK HARTOUNIAN
Interior/Exterior Lathing 4/20/2020 Partial Approval CHRISTOPHER DELLEFIELD
Insulation 4/28/2020 Conditional Approval OSVALDO PARAMO
Drywall Nailing 5/7/2020 Conditional Approval HAMIK HARTOUNIAN
Green Building Rough 5/7/2020 Approved HAMIK HARTOUNIAN
Gas Test 5/8/2020 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 11/20/2020 Approved HAMIK HARTOUNIAN
Drywall Nailing 11/20/2020 Approved HAMIK HARTOUNIAN
Final 11/20/2020 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 11/20/2020 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 11/20/2020 SGSOV Not Ready HAMIK HARTOUNIAN
Smoke Detectors 11/20/2020 Approved HAMIK HARTOUNIAN
Final 11/30/2020 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 11/30/2020 SGSOV Approved HAMIK HARTOUNIAN
Final 12/17/2020 OK to Issue CofO HAMIK HARTOUNIAN