4904 W MARATHON ST 90029
Certificate Information: 4904 W MARATHON ST 90029
- Application / Permit
- 19014-20000-05375
- Plan Check / Job No.
- B19VN16836
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT TWO STORY GARAGE & STORAGE TO 21'-10" X 21'-9" IRRIGULAR SHAPE ACCESSORY DWELLING UNIT, W/ NEW ATTACH. 16'-11" X 4'-0" STORAGE ON 1ST FLOOR. ALL WORK PER ENG. COMPLY WITH DEPARTMENT ORDER EFFECTIVE DATE 04/22/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE (SEE COMMENTS)
- Permit Issued
- Issued on 9/10/2020
- Issuing Office
- Current Status
- CofO Issued on 1/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/24/2019 | PARISA ZAHABI |
| Corrections Issued | 10/31/2019 | PARISA ZAHABI |
| Quality Review Completed | 11/4/2019 | OMID HEDAYAT |
| Building Plans Picked Up | 11/8/2019 | APPLICANT |
| Green Plans Picked Up | 11/8/2019 | APPLICANT |
| Applicant returned to address corrections | 6/25/2020 | PARISA ZAHABI |
| Applicant returned to address corrections | 8/6/2020 | PARISA ZAHABI |
| Applicant returned to address corrections | 8/7/2020 | PARISA ZAHABI |
| Plan Check Approved | 9/4/2020 | PARISA ZAHABI |
| Issued | 9/10/2020 | APPLICANT |
| CofO Issued | 1/3/2025 | JEFF NAPIER |
| Permit Finaled | 1/3/2025 | JEFF NAPIER |
Permit Application Clearance Information
| Address approval | Cleared | 11/25/2019 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 11/25/2019 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 11/25/2019 | LEE GUILBEAUX |
| Sewer availability | Cleared | 11/25/2019 | LEE GUILBEAUX |
| Hydrant and Access approval | Cleared | 11/27/2019 | JOHN CONNEALLY |
| Green Code | Cleared | 12/2/2019 | AARON COSTA |
| HPOZ | Cleared | 5/1/2020 | DEEPEAKA DHALIWAL |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Baluyut,, Agustin Pangilinan; Lic. No.: C66025 | 22828 S CYPRESS DR CARSON, CA 90745 |
Inspector Information
| RUBEN PEREZ, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT NILES, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK BEVELAQUA, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL SANCHEZ, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| COREY HUPP, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
| EMIL OPFFER, (213) 252-3053 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/8/2023 | Conditional Approval | PTOLEMY HILL |
| Footing/Foundation/Slab | 5/10/2023 | Approved | PTOLEMY HILL |
| Deputy Reinf. Concrete | 5/11/2023 | Conditional Approval | PTOLEMY HILL |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2023 | Corrections Issued | PTOLEMY HILL |
| PLUMBING-Rough | 6/21/2023 | Corrections Issued | PTOLEMY HILL |
| Underground Mechanical | 7/6/2023 | Approved | PTOLEMY HILL |
| BUILDING-Rough-Frame | 8/2/2023 | Corrections Issued | PTOLEMY HILL |
| ELECTRICAL-Rough | 8/2/2023 | Not Ready for Inspection | PTOLEMY HILL |
| Floor/Roof Diaphrgm/Shear Wall | 8/2/2023 | Not Ready for Inspection | PTOLEMY HILL |
| Gas Test | 8/2/2023 | Not Ready for Inspection | PTOLEMY HILL |
| Green Building Rough | 8/2/2023 | Not Ready for Inspection | PTOLEMY HILL |
| PLUMBING-Rough | 8/2/2023 | Not Ready for Inspection | PTOLEMY HILL |
| BUILDING-Rough-Frame | 9/13/2023 | Approved | PTOLEMY HILL |
| ELECTRICAL-Rough | 9/13/2023 | Approved | PTOLEMY HILL |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2023 | Approved | PTOLEMY HILL |
| Gas Test | 9/13/2023 | Approved | PTOLEMY HILL |
| Green Building Rough | 9/13/2023 | Approved | PTOLEMY HILL |
| PLUMBING-Rough | 9/13/2023 | Approved | PTOLEMY HILL |
| Insulation | 9/28/2023 | Approved | PTOLEMY HILL |
| Interior/Exterior Lathing | 9/28/2023 | Approved | PTOLEMY HILL |
| Drywall Nailing | 10/23/2023 | Approved | PTOLEMY HILL |
| Shower Pan | 10/23/2023 | Approved | PTOLEMY HILL |
| Final | 5/14/2024 | Conditional Approval | EMIL OPFFER |
| Green Building Final | 5/14/2024 | Approved | EMIL OPFFER |
| SGSOV-Seismic Gas S/O Valve | 5/14/2024 | SGSOV Approved | EMIL OPFFER |
| Smoke Detectors | 5/14/2024 | Approved | EMIL OPFFER |
| Final | 5/22/2024 | Conditional Approval | EMIL OPFFER |
| ELECTRICAL-Final | 5/29/2024 | Approved | EMIL OPFFER |
| Final | 5/29/2024 | Conditional Approval | EMIL OPFFER |
| HVAC-Final | 5/29/2024 | Approved | EMIL OPFFER |
| PLUMBING-Final | 5/29/2024 | Approved | EMIL OPFFER |
| Final | 7/19/2024 | Conditional Approval | EMIL OPFFER |