7947 N MCLAREN AVE 91304

Certificate Information: 7947 N MCLAREN AVE 91304

Application / Permit
19014-20000-05353
Plan Check / Job No.
B19VN16727
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20' X 20' DETACHED GARAGE AND ADD 10' X 20' FOR (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
Permit Issued
Issued on 11/27/2019
Issuing Office
Valley
Current Status
CofO Issued on 4/9/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/1/2019 APPLICANT
Assigned to Plan Check Engineer 10/8/2019 JENNIFER LEE
Corrections Issued 10/8/2019 JENNIFER LEE
Applicant returned to address corrections 10/18/2019 PINANK PATEL
Plan Check Approved 11/26/2019 GURUNATH NESARAJAH
Issued 11/27/2019 LADBS
CofO in Progress 3/26/2020 DAVID STEPANYAN
Permit Finaled 4/9/2020 DONALD SUNSERI
CofO Issued 4/9/2020 DONALD SUNSERI
Permit Finaled 4/9/2020 DONALD SUNSERI

Permit Application Clearance Information

Address approval Cleared 10/10/2019 THOMAS LANG
Eng Process Fee Ord 176,300 Cleared 10/10/2019 THOMAS LANG
Roof/Waste drainage to street Cleared 10/10/2019 THOMAS LANG
Sewer availability Cleared 10/10/2019 THOMAS LANG
Construction near power lines Cleared 11/23/2019 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY HARTLINE, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI
CHRIS CHRISTENSEN, (818) 774-4320 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/12/2019 Approved PETER FOLLING
ELECTRICAL-Rough 1/9/2020 Approved PETER FOLLING
Green Building Rough 1/9/2020 Approved PETER FOLLING
PLUMBING-Rough 1/9/2020 Approved PETER FOLLING
Interior/Exterior Lathing 1/13/2020 Partial Approval PETER FOLLING
Sewer 1/15/2020 Approved PETER FOLLING
HVAC-Rough 1/17/2020 Approved PETER FOLLING
PLUMBING-Rough 1/17/2020 Partial Approval PETER FOLLING
BUILDING-Rough-Frame 1/22/2020 Corrections Issued PETER FOLLING
BUILDING-Rough-Frame 2/10/2020 Approved PETER FOLLING
Insulation 2/12/2020 Approved PETER FOLLING
Interior/Exterior Lathing 2/12/2020 Approved PETER FOLLING
Shower Pan 2/12/2020 Approved PETER FOLLING
Drywall Nailing 2/18/2020 Approved HENRY KIM
ELECTRICAL-Final 3/19/2020 Approved DAVID STEPANYAN
Final 3/20/2020 Not Ready for Inspection DAVID STEPANYAN
Green Building Final 3/20/2020 Corrections Issued DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 3/20/2020 SGSOV Not Ready DAVID STEPANYAN
Smoke Detectors 3/20/2020 Approved DAVID STEPANYAN
Final 3/25/2020 OK to Issue CofO DAVID STEPANYAN
Gas Test 3/25/2020 Approved DAVID STEPANYAN
Green Building Final 3/25/2020 Approved DAVID STEPANYAN
HVAC-Final 3/25/2020 Approved DAVID STEPANYAN
PLUMBING-Final 3/25/2020 Approved DAVID STEPANYAN
SGSOV-Seismic Gas S/O Valve 3/25/2020 SGSOV Approved DAVID STEPANYAN