4364 N LATONA AVE 90031
Certificate Information: 4364 N LATONA AVE 90031
- Application / Permit
- 19014-20000-05341
- Plan Check / Job No.
- B19VN16693
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition/Alteration to consist of 21'4" x 22'8" second story addition to create bedroom, closet, and full restroom. Single-Family Dwelling to designed to have two bedrooms, two full bathrooms, kitchen and living room.
- Permit Issued
- Issued on 3/12/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/25/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/10/2019 | LUIS RINCON |
| Green Plans Picked Up | 10/10/2019 | APPLICANT |
| Corrections Issued | 10/12/2019 | LUIS RINCON |
| Quality Review Completed | 10/22/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 10/29/2019 | APPLICANT |
| Plan Check Approved | 2/21/2020 | LUIS RINCON |
| Issued | 3/12/2020 | LADBS |
| CofO in Progress | 2/16/2022 | COREY HUPP |
| CofO in Progress | 2/16/2022 | COREY HUPP |
| Permit Finaled | 2/25/2022 | DEROLD HAUFF |
| CofO Issued | 2/25/2022 | DEROLD HAUFF |
| Permit Finaled | 2/25/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 11/15/2019 | JOHN LIN |
| BHO/Hillside ordinance | Cleared | 11/15/2019 | JOHN LIN |
| BHO/Hillside ordinance | Cleared | 11/15/2019 | JOHN LIN |
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2019 | JOHN LIN |
| Highway dedication | Cleared | 11/15/2019 | JOHN LIN |
| "Q" conditions | Cleared | 1/15/2020 | JOE LUCKEY |
| Distance to fire station | Cleared | 1/15/2020 | GEORGE SUCHAND |
| Hydrant and Access approval | Cleared | 1/15/2020 | GEORGE SUCHAND |
| ZI | Cleared | 1/15/2020 | JOE LUCKEY |
| Green Code | Cleared | 1/22/2020 | DAVID MATSON |
| Construction near power lines | Cleared | 1/29/2020 | RIDWAN HARDY |
| Low Impact Development | Cleared | 2/6/2020 | ANDRES COVARRUBIAS |
| Grading Pre-Inspection | Cleared | 2/19/2020 | LUIS RINCON |
| "D" conditions | Cleared | 2/20/2020 | JOE LUCKEY |
Contact Information
| Contractor | Gamburd Inc; Lic. No.: 939455-B | 12405 MONTAGUE ST PACOIMA, CA 91331 |
| Engineer | Andrejic,, Milos M; Lic. No.: C67443 | 3601 BEVERLY RIDGE DR SHERMAN OAKS, CA 91423 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2020 | Partial Approval | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 4/1/2020 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2020 | Partial Approval | ENRIQUE MIRELES |
| Underground Mechanical | 5/4/2020 | Corrections Issued | ENRIQUE MIRELES |
| Underground Mechanical | 5/6/2020 | Partial Approval | OSVALDO PARAMO |
| ELECTRICAL-Rough | 5/13/2020 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 5/13/2020 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 5/13/2020 | Partial Approval | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 6/22/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 6/22/2020 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Rough | 6/22/2020 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 6/22/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 6/22/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 6/22/2020 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 6/24/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Rough | 6/24/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 6/24/2020 | Corrections Issued | ENRIQUE MIRELES |
| Wood Frame | 6/24/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 6/30/2020 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 6/30/2020 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 6/30/2020 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 6/30/2020 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 6/30/2020 | Approved | ENRIQUE MIRELES |
| Shower Pan | 6/30/2020 | Approved | ENRIQUE MIRELES |
| Wood Frame | 6/30/2020 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 7/20/2020 | Approved | OSVALDO PARAMO |
| Insulation | 7/30/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 8/5/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 1/15/2021 | Corrections Issued | COREY HUPP |
| Green Building Final | 1/15/2021 | Not Ready for Inspection | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 1/15/2021 | SGSOV Not Ready | COREY HUPP |
| Smoke Detectors | 1/15/2021 | Not Ready for Inspection | COREY HUPP |
| Final | 1/26/2021 | Not Ready for Inspection | COREY HUPP |
| Green Building Final | 1/26/2021 | Not Ready for Inspection | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 1/26/2021 | SGSOV Not Ready | COREY HUPP |
| Smoke Detectors | 1/26/2021 | Not Ready for Inspection | COREY HUPP |
| Final | 8/10/2021 | OK to Issue CofO | COREY HUPP |
| Green Building Final | 8/10/2021 | Approved | COREY HUPP |
| SGSOV-Seismic Gas S/O Valve | 8/10/2021 | SGSOV Approved | COREY HUPP |
| Smoke Detectors | 8/10/2021 | Approved | COREY HUPP |