16635-16637 W MARILLA ST 91343

Certificate Information: 16635-16637 W MARILLA ST 91343

Application / Permit
19014-20000-05330
Plan Check / Job No.
B19VN16665
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION TO (E) ATTACHED GARAGE AND CONVERSION TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229
Permit Issued
Issued on 12/5/2019
Issuing Office
Valley
Current Status
CofO Issued on 7/6/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/30/2019 APPLICANT
Assigned to Plan Check Engineer 9/30/2019 JEFFREY TANGONAN
Corrections Issued 9/30/2019 JEFFREY TANGONAN
Building Plans Picked Up 10/2/2019 APPLICANT
Issued 12/5/2019 LADBS
CofO in Progress 4/16/2020 JENNIFER RABUCHIN
CofO Issued 7/6/2020 MICHAEL SMITH
Permit Finaled 7/6/2020 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 10/9/2019 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 10/9/2019 JEANIE LAM
Grading Pre-Inspection Cleared 10/9/2019 PATRICK MISCHLICH
Roof/Waste drainage to street Cleared 10/9/2019 JEANIE LAM
Sewer availability Cleared 10/9/2019 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,
Engineer Bayani-Rad,, Padra; Lic. No.: C86320 18119 S PRAIRIE AVE 102      TORRANCE, CA 90504

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 1/23/2020 Approved JACK KARGODORIAN
PLUMBING-Rough 1/23/2020 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 1/30/2020 Not Ready for Inspection PIERRE VEGA
ELECTRICAL-Rough 1/30/2020 Not Ready for Inspection PIERRE VEGA
Green Building Rough 1/30/2020 Not Ready for Inspection PIERRE VEGA
PLUMBING-Rough 1/30/2020 Not Ready for Inspection PIERRE VEGA
ELECTRICAL-Rough 2/5/2020 Approved JACK KARGODORIAN
PLUMBING-Rough 2/5/2020 Approved JACK KARGODORIAN
Insulation 2/11/2020 Approved JACK KARGODORIAN
Interior/Exterior Lathing 2/11/2020 Approved JACK KARGODORIAN
Shower Pan 2/11/2020 Approved JACK KARGODORIAN
Drywall Nailing 2/21/2020 Approved JACK KARGODORIAN
Green Building Rough 2/21/2020 Approved JACK KARGODORIAN
Insulation 2/21/2020 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 3/20/2020 Approved ROBERT MINASSIANS
Final 3/20/2020 Corrections Issued ROBERT MINASSIANS
Green Building Final 3/20/2020 Approved ROBERT MINASSIANS
SGSOV-Seismic Gas S/O Valve 3/20/2020 SGSOV Not Ready ROBERT MINASSIANS
Smoke Detectors 3/20/2020 Approved ROBERT MINASSIANS
ELECTRICAL-Final 4/14/2020 Approved JENNIFER RABUCHIN
Final 4/14/2020 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 4/14/2020 Approved JENNIFER RABUCHIN
PLUMBING-Final 4/14/2020 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 4/14/2020 SGSOV Approved JENNIFER RABUCHIN