17625 W HIDDEN OAKS RD 91316
Certificate Information: 17625 W HIDDEN OAKS RD 91316
- Application / Permit
- 19014-20000-05310
- Plan Check / Job No.
- B19VN16617
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 4'-10" X 5'-7" ELEVATOR SHAFT ADDITION TO (E) 3 STORY SFD PER ENGINEERING.
- Permit Issued
- Issued on 4/21/2020
- Issuing Office
- Current Status
- CofO Issued on 11/21/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/27/2019 | ARTIN ZARUKIAN |
| Corrections Issued | 9/27/2019 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 10/3/2019 | APPLICANT |
| Applicant returned to address corrections | 11/18/2019 | ARTIN ZARUKIAN |
| Plan Check Approved | 12/12/2019 | ARTIN ZARUKIAN |
| Issued | 4/21/2020 | APPLICANT |
| CofO in Progress | 11/4/2020 | RONALD COWAN |
| Permit Finaled | 11/21/2020 | DONALD SUNSERI |
| CofO Issued | 11/21/2020 | DONALD SUNSERI |
| Permit Finaled | 11/21/2020 | DONALD SUNSERI |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 10/3/2019 | TIMOTHY POWELL |
| Eng Process Fee Ord 176,300 | Cleared | 10/4/2019 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 10/4/2019 | ADRIAN CASTRO |
| ZA Case | Cleared | 10/4/2019 | DAISY BENICIA |
| Private street | Cleared | 11/21/2019 | MARC WOERSCHING |
| ZI | Cleared | 12/6/2019 | VINCENT QUITORIANO |
Contact Information
| Contractor | Slater Construction And Development Inc; Lic. No.: 339608-B | 200 S BARRINGTON AVE 1486 LOS ANGELES, CA 90049 |
| Engineer | Judd,, Shane Dennis; Lic. No.: C70991 | 17 E HIGH ST STE A MOORPARK, CA 93021 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/4/2020 | Partial Approval | RONALD COWAN |
| Structural Steel Frame | 6/12/2020 | Partial Approval | RONALD COWAN |
| Footing/Foundation/Slab | 6/17/2020 | Approved | RONALD COWAN |
| BUILDING-Rough-Frame | 7/14/2020 | Corrections Issued | SEAN WIRCH |
| Green Building Rough | 7/14/2020 | Not Ready for Inspection | SEAN WIRCH |
| BUILDING-Rough-Frame | 7/17/2020 | Approved | RONALD COWAN |
| Green Building Rough | 7/17/2020 | Approved | RONALD COWAN |
| Insulation | 7/17/2020 | Approved | RONALD COWAN |
| Insulation | 7/21/2020 | Approved | RONALD COWAN |
| Drywall Nailing | 7/23/2020 | Approved | RONALD COWAN |
| Interior/Exterior Lathing | 7/23/2020 | Approved | RONALD COWAN |
| Final | 10/14/2020 | Corrections Issued | RONALD COWAN |
| Green Building Final | 10/14/2020 | Not Ready for Inspection | RONALD COWAN |
| SGSOV-Seismic Gas S/O Valve | 10/14/2020 | SGSOV Not Ready | RONALD COWAN |
| Smoke Detectors | 10/14/2020 | Not Ready for Inspection | RONALD COWAN |
| Final | 11/4/2020 | OK to Issue CofO | RONALD COWAN |
| Green Building Final | 11/4/2020 | Approved | RONALD COWAN |
| SGSOV-Seismic Gas S/O Valve | 11/4/2020 | SGSOV Approved | RONALD COWAN |
| Smoke Detectors | 11/4/2020 | Approved | RONALD COWAN |