11954 W SNELLING ST 91352
Certificate Information: 11954 W SNELLING ST 91352
- Application / Permit
- 19014-20000-05306
- Plan Check / Job No.
- B19VN16605
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- REMOVE 5'-4" x 14'-8" STORAGE, CONVERT (E) 18'-4" X 20'-0" DETACHED GARAGE AND ADD 10'-5" X 12'-7" FOR (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER WFPP.
- Permit Issued
- Issued on 10/30/2020
- Issuing Office
- Current Status
- CofO Issued on 12/16/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/8/2019 | JENNIFER LEE |
| Corrections Issued | 10/8/2019 | JENNIFER LEE |
| Applicant returned to address corrections | 1/31/2020 | ANGELICA DAVE |
| Plan Check Approved | 5/27/2020 | HAYATO TSUCHIYA |
| No Progress | 5/27/2020 | HAYATO TSUCHIYA |
| Plan Check Approved | 5/27/2020 | HAYATO TSUCHIYA |
| Issued | 10/30/2020 | APPLICANT |
| CofO in Progress | 6/3/2021 | JOHN HAYES |
| CofO in Progress | 8/19/2021 | JOHN HAYES |
| Permit Finaled | 12/16/2021 | RONALD MYRICK |
| CofO Issued | 12/16/2021 | RONALD MYRICK |
| Permit Finaled | 12/16/2021 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 10/8/2019 | SAFA JAVANMARDI |
| Eng Process Fee Ord 176,300 | Cleared | 10/8/2019 | SAFA JAVANMARDI |
| Roof/Waste drainage to street | Cleared | 10/8/2019 | SAFA JAVANMARDI |
| Sewer availability | Cleared | 10/8/2019 | SAFA JAVANMARDI |
| Construction near power lines | Cleared | 11/21/2019 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/2/2020 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 11/2/2020 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 11/12/2020 | Approved | JOHN HAYES |
| Underground Mechanical | 11/12/2020 | Approved | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 11/16/2020 | Not Ready for Inspection | JOHN HAYES |
| Sewer | 11/16/2020 | Not Ready for Inspection | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 11/18/2020 | Partial Approval | JOHN HAYES |
| Sewer | 11/18/2020 | Approved | JOHN HAYES |
| Underground Mechanical | 11/18/2020 | Partial Approval | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2020 | Partial Approval | JOHN HAYES |
| Underground Mechanical | 11/23/2020 | Approved | JOHN HAYES |
| Gas Test | 11/25/2020 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 12/2/2020 | Partial Approval | JOHN HAYES |
| Interior/Exterior Lathing | 12/2/2020 | Partial Approval | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 12/2/2020 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 12/4/2020 | Not Ready for Inspection | JOHN HAYES |
| Green Building Rough | 12/4/2020 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Rough | 12/4/2020 | Not Ready for Inspection | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 12/4/2020 | Not Ready for Inspection | JOHN HAYES |
| BUILDING-Rough-Frame | 12/8/2020 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 12/8/2020 | Approved | JOHN HAYES |
| Green Building Rough | 12/8/2020 | Approved | JOHN HAYES |
| HVAC-Rough | 12/8/2020 | Approved | JOHN HAYES |
| MERV13>=Rough | 12/8/2020 | Approved | JOHN HAYES |
| PLUMBING-Rough | 12/8/2020 | Approved | JOHN HAYES |
| Drywall Nailing | 1/7/2021 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 1/7/2021 | Approved | JOHN HAYES |
| Final | 4/23/2021 | Corrections Issued | BEAU COLLINS |
| Green Building Final | 4/23/2021 | Not Ready for Inspection | BEAU COLLINS |
| SGSOV-Seismic Gas S/O Valve | 4/23/2021 | SGSOV Not Ready | BEAU COLLINS |
| Smoke Detectors | 4/23/2021 | Approved | BEAU COLLINS |
| ELECTRICAL-Final | 4/29/2021 | Not Ready for Inspection | JOHN HAYES |
| Final | 4/29/2021 | Corrections Issued | JOHN HAYES |
| Green Building Final | 4/29/2021 | Not Ready for Inspection | JOHN HAYES |
| HVAC-Final | 4/29/2021 | Not Ready for Inspection | JOHN HAYES |
| MERV13>=Final | 4/29/2021 | Not Ready for Inspection | JOHN HAYES |
| PLUMBING-Final | 4/29/2021 | Not Ready for Inspection | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 4/29/2021 | SGSOV Not Ready | JOHN HAYES |
| Final | 6/3/2021 | OK to Issue CofO | JOHN HAYES |
| Green Building Final | 6/3/2021 | Approved | JOHN HAYES |
| MERV13>=Final | 6/3/2021 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 6/3/2021 | SGSOV Approved | JOHN HAYES |
| Special/Order Compliance | 8/18/2021 | No Access for Inspection | JOHN HAYES |
| Final | 8/19/2021 | OK to Issue CofO | JOHN HAYES |
| Special/Order Compliance | 8/19/2021 | Approved | JOHN HAYES |