7724 N BECK AVE 91605

Certificate Information: 7724 N BECK AVE 91605

Application / Permit
19014-20000-05302
Plan Check / Job No.
B19VN16594
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Add irregular 36'-9" x 23'-0" to and convert detached garage into an Accessory Dwelling Unit per AB 494 & SB 229 per engineer.
Permit Issued
Issued on 12/23/2021
Issuing Office
Current Status
CofO Issued on 9/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/27/2019 APPLICANT
Assigned to Plan Check Engineer 9/27/2019 ANGELICA DAVE
Corrections Issued 9/27/2019 ANGELICA DAVE
Applicant returned to address corrections 2/11/2020 ANGELICA DAVE
Plan Check Approved 2/14/2020 ANGELICA MARTINEZ
No Progress 10/30/2020 ANGELICA MARTINEZ
Plan Check Approved 6/8/2021 ANGELICA MARTINEZ
Building Plans Picked Up 6/18/2021 APPLICANT
Issued 12/23/2021 APPLICANT
CofO in Progress 8/23/2022 CHRISTOPHER DELLEFIELD
Permit Finaled 9/3/2022 MICHAEL SMITH
CofO Issued 9/3/2022 MICHAEL SMITH
Permit Finaled 9/3/2022 MICHAEL SMITH

Permit Application Clearance Information

Low Impact Development Cleared 1/14/2020 MITESH PATEL
Address approval Cleared 1/21/2020 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 1/21/2020 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 1/21/2020 GABRIEL ROBLES
Sewer availability Cleared 1/21/2020 GABRIEL ROBLES

Contact Information

Contractor Pampa Investment Inc; Lic. No.: 832632-B 984 BROADWAY #302      CHULA VISTA, CA 91911
Engineer Sabzehzar,, Habib; Lic. No.: C50442 8180 N PRICE AVE      FRESNO, CA 93720

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/18/2022 Approved RICHARD DOCKUS
ELECTRICAL-Rough 1/26/2022 Partial Approval CHRISTOPHER DELLEFIELD
PLUMBING-Rough 1/26/2022 Partial Approval CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 2/4/2022 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 3/14/2022 Approved RYAN SALAZAR
ELECTRICAL-Rough 3/14/2022 Approved RYAN SALAZAR
Floor/Roof Diaphrgm/Shear Wall 3/14/2022 Partial Approval RYAN SALAZAR
Green Building Rough 3/14/2022 Not Ready for Inspection RYAN SALAZAR
HVAC-Rough 3/14/2022 Approved RYAN SALAZAR
PLUMBING-Rough 3/14/2022 Approved RYAN SALAZAR
Insulation 3/18/2022 Partial Inspection KRISTEN CAUSEY
Interior/Exterior Lathing 3/18/2022 Partial Approval KRISTEN CAUSEY
Drywall Nailing 3/24/2022 Approved CHRISTOPHER DELLEFIELD
Green Building Rough 3/24/2022 Approved CHRISTOPHER DELLEFIELD
Shower Pan 3/24/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 8/4/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Final 8/4/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 8/4/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
HVAC-Final 8/4/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 8/4/2022 Corrections Issued CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 8/4/2022 SGSOV Not Ready CHRISTOPHER DELLEFIELD
Smoke Detectors 8/4/2022 Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 8/12/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Final 8/12/2022 Corrections Issued CHRISTOPHER DELLEFIELD
Green Building Final 8/12/2022 Approved CHRISTOPHER DELLEFIELD
HVAC-Final 8/12/2022 Corrections Issued CHRISTOPHER DELLEFIELD
PLUMBING-Final 8/12/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
SGSOV-Seismic Gas S/O Valve 8/12/2022 SGSOV Approved CHRISTOPHER DELLEFIELD
ELECTRICAL-Final 8/23/2022 Approved CHRISTOPHER DELLEFIELD
Final 8/23/2022 OK to Issue CofO CHRISTOPHER DELLEFIELD
HVAC-Final 8/23/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Final 8/23/2022 Approved CHRISTOPHER DELLEFIELD