3228 W GLENHURST AVE 90039

Certificate Information: 3228 W GLENHURST AVE 90039

Application / Permit
19014-20000-05285
Plan Check / Job No.
B19VN16531
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 20'-5" X 22'-0" DETACHED GARAGE AND ADD IRREGULAR 19'-1" X 27'-2" FOR (N) ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 2/5/2020
Issuing Office
Valley
Current Status
CofO Issued on 4/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/26/2019 APPLICANT
Assigned to Plan Check Engineer 10/7/2019 JENNIFER LEE
Corrections Issued 10/7/2019 JENNIFER LEE
Applicant returned to address corrections 11/14/2019 ANGELICA DAVE
Plan Check Approved 1/9/2020 PINANK PATEL
Issued 2/5/2020 LADBS
CofO in Progress 3/24/2022 HAMIK HARTOUNIAN
Permit Finaled 4/1/2022 DEROLD HAUFF
CofO Issued 4/1/2022 DEROLD HAUFF
Permit Finaled 4/1/2022 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 11/8/2019 RIDWAN HARDY
Miscellaneous Cleared 11/14/2019 HERMINIGILDO AGUSTIN
Address approval Cleared 11/22/2019 GUILLERMO PETRA
Eng Process Fee Ord 176,300 Cleared 11/22/2019 GUILLERMO PETRA
Sewer availability Cleared 11/22/2019 GUILLERMO PETRA
Low Impact Development Cleared 1/8/2020 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 1/9/2020 MARKOS PEREZ-BRAN

Contact Information

Contractor Blue Pacific Contractors Inc; Lic. No.: 1022139-B 13535 LAZARD ST      SAN FERNANDO, CA 91340
Engineer Garcia,, Francisco Diaz; Lic. No.: C88029 7333 RANCHITO AVE      VAN NUYS, CA 91405

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 3/12/2020 No Access for Inspection HAMIK HARTOUNIAN
Sewer 3/12/2020 No Access for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 3/17/2020 Corrections Issued HAMIK HARTOUNIAN
Underground Mechanical 3/17/2020 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 3/27/2020 Partial Approval SABAS ALONSO
Sewer 3/27/2020 Not Ready for Inspection SABAS ALONSO
Footing/Foundation/Slab 4/1/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Footing/Foundation/Slab 4/7/2020 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 5/4/2020 Conditional Approval HAMIK HARTOUNIAN
Sewer 5/14/2020 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 6/3/2020 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 6/3/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Rough 6/3/2020 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 6/3/2020 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 6/3/2020 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 8/12/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 8/12/2020 Not Ready for Inspection HAMIK HARTOUNIAN
Green Building Rough 8/12/2020 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 8/12/2020 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 8/12/2020 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 8/28/2020 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 8/28/2020 Corrections Issued HAMIK HARTOUNIAN
Green Building Rough 8/28/2020 Partial Approval HAMIK HARTOUNIAN
Special/Order Compliance 8/28/2020 Approved CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 9/11/2020 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 9/22/2020 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 9/22/2020 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 9/22/2020 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 9/22/2020 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 10/26/2020 Approved HAMIK HARTOUNIAN
Green Building Rough 10/26/2020 Approved HAMIK HARTOUNIAN
HVAC-Rough 10/26/2020 Approved HAMIK HARTOUNIAN
Insulation 10/26/2020 Approved HAMIK HARTOUNIAN
Drywall Nailing 10/29/2020 Approved HAMIK HARTOUNIAN
Gas Test 10/29/2020 Partial Inspection HAMIK HARTOUNIAN
Green Building Rough 10/29/2020 Approved HAMIK HARTOUNIAN
Service/Power Release 10/18/2021 Corrections Issued HAMIK HARTOUNIAN
Final 2/10/2022 Partial Approval HAMIK HARTOUNIAN
Green Building Final 2/10/2022 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 2/10/2022 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 2/10/2022 Approved HAMIK HARTOUNIAN
Final 2/24/2022 Partial Inspection HAMIK HARTOUNIAN
Green Building Final 2/24/2022 Approved HAMIK HARTOUNIAN
Service/Power Release 2/24/2022 Approved HAMIK HARTOUNIAN
Final 3/24/2022 OK to Issue CofO HAMIK HARTOUNIAN