927 N HOOVER ST 90029
Certificate Information: 927 N HOOVER ST 90029
- Application / Permit
- 19014-20000-05239
- Plan Check / Job No.
- B19VN16345
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMODEL, 1'-9" x 13'-0" ADDITION AT FIRST FLOOR AND 27'-9" X 19'-3" IRREGULAR SHAPED 2ND STORY ADDITION TO (E) SFD.
- Permit Issued
- Issued on 4/29/2020
- Issuing Office
- Current Status
- Issued on 4/29/2020
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 9/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/10/2019 | ARTIN ZARUKIAN |
| Green Plans Picked Up | 10/18/2019 | APPLICANT |
| Corrections Issued | 10/29/2019 | ARTIN ZARUKIAN |
| Quality Review Completed | 10/31/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 11/1/2019 | APPLICANT |
| Plan Check Approved | 4/15/2020 | ARTIN ZARUKIAN |
| Issued | 4/29/2020 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/1/2019 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 1/16/2020 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 1/16/2020 | EMIL KYUPELYAN |
| Green Code | Cleared | 3/31/2020 | MICHAEL AYERS |
| Grading Pre-Inspection | Cleared | 4/15/2020 | ARTIN ZARUKIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hernandez,, Gerardo; Lic. No.: C78115 | 1426 E STUART AVE WEST COVINA, CA 91791 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/29/2020 | Conditional Approval | ROBERT VORHIS |
| Footing/Foundation/Slab | 6/2/2020 | Approved | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2020 | Not Ready for Inspection | ROBERT VORHIS |
| Insulation | 6/26/2020 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 7/1/2020 | No Access for Inspection | ROBERT VORHIS |
| Insulation | 7/1/2020 | Not Ready for Inspection | ROBERT VORHIS |
| Wood Frame | 7/8/2020 | Partial Approval | ROBERT VORHIS |
| ELECTRICAL-Rough | 7/28/2020 | Approved | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 7/28/2020 | Corrections Issued | ROBERT VORHIS |
| Green Building Rough | 7/28/2020 | Not Ready for Inspection | ROBERT VORHIS |
| PLUMBING-Rough | 7/28/2020 | Conditional Approval | ROBERT VORHIS |
| BUILDING-Rough-Frame | 8/5/2020 | Approved | ROBERT VORHIS |
| Green Building Rough | 8/5/2020 | Approved | ROBERT VORHIS |
| Interior/Exterior Lathing | 8/5/2020 | Partial Approval | ROBERT VORHIS |
| Insulation | 8/11/2020 | Approved | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 8/13/2020 | Approved | THOMAS LOGRASSO |
| SGSOV-Seismic Gas S/O Valve | 10/5/2020 | SGSOV Not Ready | DONALD CRICHLOW |
| Final | 10/8/2020 | Corrections Issued | CRAIG VAUGHAN |
| Final | 10/13/2020 | Not Ready for Inspection | ROBERT VORHIS |
| Green Building Final | 10/13/2020 | Approved | ROBERT VORHIS |
| SGSOV-Seismic Gas S/O Valve | 10/13/2020 | SGSOV Approved | ROBERT VORHIS |
| Smoke Detectors | 10/13/2020 | Approved | ROBERT VORHIS |