12816 W LORNE ST 91605

Certificate Information: 12816 W LORNE ST 91605

Application / Permit
19014-20000-05231
Plan Check / Job No.
B19VN16298
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
13-2" X 10'-7" ADDITION TO (E) 20' X 18' GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229
Permit Issued
Issued on 1/10/2020
Issuing Office
Valley
Current Status
CofO Issued on 3/1/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/24/2019 APPLICANT
Assigned to Plan Check Engineer 9/24/2019 ROSENDO MEDINA
Corrections Issued 9/30/2019 ROSENDO MEDINA
Building Plans Picked Up 10/2/2019 APPLICANT
Plan Check Approved 12/20/2019 ROSENDO MEDINA
Issued 1/10/2020 LADBS
CofO in Progress 1/11/2021 GREGG CUMMINGS
Permit Finaled 3/1/2021 MICHAEL SMITH
CofO Issued 3/1/2021 MICHAEL SMITH
Permit Finaled 3/1/2021 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 11/15/2019 RIDWAN HARDY
Address approval Cleared 11/21/2019 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 11/21/2019 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 11/21/2019 ADRIAN CASTRO
Sewer availability Cleared 11/21/2019 ADRIAN CASTRO
Hydrant and Access approval Cleared 12/19/2019 GEORGE SUCHAND

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/29/2020 Corrections Issued GREGG CUMMINGS
PLUMBING-Rough 7/29/2020 Not Ready for Inspection GREGG CUMMINGS
Excavation/Setback/Form/Re-Bar 7/31/2020 Approved GREGG CUMMINGS
PLUMBING-Rough 7/31/2020 Partial Approval GREGG CUMMINGS
Deputy Wood Construction 8/11/2020 Approved PIERRE VEGA
Deputy Wood Construction 8/12/2020 Approved GREGG CUMMINGS
BUILDING-Rough-Frame 8/13/2020 Corrections Issued GREGG CUMMINGS
ELECTRICAL-Rough 8/13/2020 Corrections Issued GREGG CUMMINGS
Green Building Rough 8/13/2020 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 8/13/2020 Not Ready for Inspection GREGG CUMMINGS
Deputy Wood Construction 8/18/2020 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 8/18/2020 Approved GREGG CUMMINGS
Interior/Exterior Lathing 8/25/2020 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 9/2/2020 Approved GREGG CUMMINGS
ELECTRICAL-Rough 9/2/2020 Approved GREGG CUMMINGS
Green Building Rough 9/2/2020 Approved GREGG CUMMINGS
HVAC-Rough 9/2/2020 Approved GREGG CUMMINGS
Interior/Exterior Lathing 9/2/2020 Approved GREGG CUMMINGS
PLUMBING-Rough 9/2/2020 Approved GREGG CUMMINGS
Insulation 9/9/2020 Not Ready for Inspection GREGG CUMMINGS
Interior/Exterior Lathing 9/9/2020 Not Ready for Inspection GREGG CUMMINGS
Shower Pan 9/9/2020 Not Ready for Inspection GREGG CUMMINGS
Insulation 9/14/2020 Approved THOMAS FINNILA
Sewer 9/14/2020 Approved THOMAS FINNILA
Shower Pan 9/14/2020 Corrections Issued THOMAS FINNILA
Underground Mechanical 9/14/2020 Partial Approval THOMAS FINNILA
Drywall Nailing 9/24/2020 Approved GREGG CUMMINGS
Interior/Exterior Lathing 9/24/2020 Approved GREGG CUMMINGS
Shower Pan 9/24/2020 Approved GREGG CUMMINGS
Final 12/17/2020 Corrections Issued GREGG CUMMINGS
Footing/Foundation/Slab 12/17/2020 Approved GREGG CUMMINGS
Green Building Final 12/17/2020 Not Ready for Inspection GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 12/17/2020 SGSOV Approved GREGG CUMMINGS
Smoke Detectors 12/17/2020 Approved GREGG CUMMINGS
ELECTRICAL-Final 1/11/2021 Approved GREGG CUMMINGS
Final 1/11/2021 OK to Issue CofO GREGG CUMMINGS
Green Building Final 1/11/2021 Approved GREGG CUMMINGS
HVAC-Final 1/11/2021 Approved GREGG CUMMINGS
PLUMBING-Final 1/11/2021 Approved GREGG CUMMINGS