12802 W WILLARD ST 91605
Certificate Information: 12802 W WILLARD ST 91605
- Application / Permit
- 19014-20000-05229
- Plan Check / Job No.
- B19VN16282
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 14' x 10' ADDITION & CONVERT (E) DET. GARAGE TO ACCESSORY DWELLING PER AB 494 AND SB 229
- Permit Issued
- Issued on 1/17/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/24/2019 | JEFFREY TANGONAN |
| Corrections Issued | 9/24/2019 | JEFFREY TANGONAN |
| Building Plans Picked Up | 9/26/2019 | APPLICANT |
| Plan Check Approved | 12/26/2019 | JEFFREY TANGONAN |
| Issued | 1/17/2020 | LADBS |
| CofO in Progress | 2/1/2022 | GREGG CUMMINGS |
| Permit Finaled | 3/10/2022 | MICHAEL SMITH |
| CofO Issued | 3/10/2022 | MICHAEL SMITH |
| Permit Finaled | 3/10/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 11/14/2019 | RIDWAN HARDY |
| Address approval | Cleared | 11/21/2019 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 11/21/2019 | ADRIAN CASTRO |
| Roof/Waste drainage to street | Cleared | 11/21/2019 | ADRIAN CASTRO |
| Sewer availability | Cleared | 11/21/2019 | ADRIAN CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/14/2021 | Approved | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 9/14/2021 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 9/14/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 9/14/2021 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 9/28/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 9/28/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| MERV13>=Rough | 9/28/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/19/2021 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Rough | 10/19/2021 | Approved | GREGG CUMMINGS |
| Green Building Rough | 10/19/2021 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 10/19/2021 | Approved | GREGG CUMMINGS |
| MERV13>=Rough | 10/19/2021 | Approved | GREGG CUMMINGS |
| PLUMBING-Rough | 10/19/2021 | Approved | GREGG CUMMINGS |
| Sewer | 10/19/2021 | Partial Approval | GREGG CUMMINGS |
| Underground Mechanical | 10/19/2021 | Approved | GREGG CUMMINGS |
| Deputy Wood Construction | 10/21/2021 | Conditional Approval | GREGG CUMMINGS |
| Insulation | 11/2/2021 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 11/2/2021 | Approved | WILLIAM WREN |
| Drywall Nailing | 11/5/2021 | Approved | WILLIAM WREN |
| Green Building Rough | 11/5/2021 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 11/15/2021 | Approved | GREGG CUMMINGS |
| Shower Pan | 11/15/2021 | Approved | GREGG CUMMINGS |
| Final | 1/11/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 1/11/2022 | Approved | GREGG CUMMINGS |
| MERV13>=Final | 1/11/2022 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 1/11/2022 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 1/11/2022 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 2/1/2022 | Approved | GREGG CUMMINGS |
| Final | 2/1/2022 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 2/1/2022 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 2/1/2022 | Approved | GREGG CUMMINGS |