18206-18208 W HERBOLD ST 91325
Certificate Information: 18206-18208 W HERBOLD ST 91325
- Application / Permit
- 19014-20000-05207
- Plan Check / Job No.
- B19VN16209
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Add 8'11" x 12' patio cover; Convert 2.5' x 12' portion of ground floor area and 9.5' x 34'1" addition to accessory dwelling per AB494 & SB229. All works are per design. See comment
- Permit Issued
- Issued on 10/15/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/23/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/23/2019 | ANGELICA DAVE |
| Corrections Issued | 9/23/2019 | ANGELICA DAVE |
| Applicant returned to address corrections | 10/9/2019 | ANGELICA DAVE |
| Applicant returned to address corrections | 10/11/2019 | ALDOUS CHIC |
| Plan Check Approved | 10/15/2019 | ALDOUS CHIC |
| Issued | 10/15/2019 | LADBS |
| CofO in Progress | 5/13/2020 | HENRY KIM |
| No Progress | 5/14/2020 | HENRY KIM |
| CofO in Progress | 8/16/2025 | MICHAEL PELHAM |
| Permit Finaled | 9/20/2025 | MICHAEL PELHAM |
| CofO Issued | 9/20/2025 | MICHAEL PELHAM |
| Permit Finaled | 9/20/2025 | MICHAEL PELHAM |
Permit Application Clearance Information
| Address approval | Cleared | 10/9/2019 | JULIUS GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 10/9/2019 | JULIUS GARCIA |
| Roof/Waste drainage to street | Cleared | 10/9/2019 | JULIUS GARCIA |
| Sewer availability | Cleared | 10/9/2019 | JULIUS GARCIA |
| ZA Case | Cleared | 10/11/2019 | STEVEN WECHSLER |
| ZA Case | Cleared | 10/11/2019 | STEVEN WECHSLER |
| ZA Case | Cleared | 10/11/2019 | STEVEN WECHSLER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 11/1/2019 | Not Ready for Inspection | COREY HUPP |
| Excavation/Setback/Form/Re-Bar | 11/5/2019 | Not Ready for Inspection | VINCENT HANLEY |
| PLUMBING-Rough | 11/5/2019 | Corrections Issued | VINCENT HANLEY |
| Excavation/Setback/Form/Re-Bar | 11/16/2019 | Corrections Issued | JOSEPH SAGEN |
| PLUMBING-Rough | 11/16/2019 | Corrections Issued | JOSEPH SAGEN |
| Sewer | 11/16/2019 | Approved | JOSEPH SAGEN |
| Excavation/Setback/Form/Re-Bar | 12/11/2019 | Corrections Issued | SEAN WIRCH |
| PLUMBING-Rough | 12/11/2019 | Not Ready for Inspection | SEAN WIRCH |
| Excavation/Setback/Form/Re-Bar | 12/17/2019 | Approved | RONALD COWAN |
| PLUMBING-Rough | 12/17/2019 | Approved | RONALD COWAN |
| BUILDING-Rough-Frame | 1/22/2020 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 1/22/2020 | Approved | VINCENT HANLEY |
| Green Building Rough | 1/22/2020 | Not Ready for Inspection | VINCENT HANLEY |
| HVAC-Rough | 1/22/2020 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 1/22/2020 | Partial Approval | VINCENT HANLEY |
| Rough-Elec/Plmb/HVAC | 1/31/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| ELECTRICAL-Rough | 2/10/2020 | Approved | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Interior/Exterior Lathing | 2/10/2020 | Partial Approval | KATHRYN BUTTERWORTH |
| Drywall Nailing | 2/20/2020 | Approved | KATHRYN BUTTERWORTH |
| Green Building Rough | 2/20/2020 | Approved | KATHRYN BUTTERWORTH |
| Insulation | 2/20/2020 | Approved | KATHRYN BUTTERWORTH |
| BUILDING-Rough-Frame | 4/21/2020 | Approved | VINCENT HANLEY |
| Final | 4/21/2020 | Corrections Issued | VINCENT HANLEY |
| Footing/Foundation/Slab | 4/21/2020 | Approved | VINCENT HANLEY |
| Green Building Final | 4/21/2020 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 4/21/2020 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 4/21/2020 | Approved | VINCENT HANLEY |
| ELECTRICAL-Final | 5/11/2020 | Corrections Issued | HENRY KIM |
| Final | 5/11/2020 | Not Ready for Inspection | HENRY KIM |
| HVAC-Final | 5/11/2020 | Approved | HENRY KIM |
| PLUMBING-Final | 5/11/2020 | Corrections Issued | HENRY KIM |
| ELECTRICAL-Final | 5/13/2020 | Approved | HENRY KIM |
| Final | 5/13/2020 | Partial Approval | HENRY KIM |
| PLUMBING-Final | 5/13/2020 | Approved | HENRY KIM |
| Final | 5/14/2020 | Corrections Issued | HENRY KIM |
| Final | 4/10/2023 | Not Ready for Inspection | DAVID SCANTLIN |
| Pre-Inspection | 4/10/2023 | Partial Inspection | JUSTIN HAWLEY |
| Final | 8/16/2025 | OK to Issue CofO | MICHAEL PELHAM |