116 E 109TH ST 90061
Certificate Information: 116 E 109TH ST 90061
- Application / Permit
- 19014-20000-05169
- Plan Check / Job No.
- B19VN16041
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD (22'-9"x 24'-5") IRR SHAPE AND CONVERT (E) 2-CAR DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. WORK PER ENGINEER.
- Permit Issued
- Issued on 3/11/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/13/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/19/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 10/10/2019 | TROY DEGUZMAN |
| Corrections Issued | 10/18/2019 | TROY DEGUZMAN |
| Green Plans Picked Up | 10/18/2019 | APPLICANT |
| Quality Review Completed | 10/22/2019 | CHON CHIO KUO |
| Building Plans Picked Up | 10/25/2019 | APPLICANT |
| Applicant returned to address corrections | 3/4/2020 | TROY DEGUZMAN |
| Plan Check Approved | 3/11/2020 | TROY DEGUZMAN |
| Issued | 3/11/2020 | LADBS |
| CofO in Progress | 10/9/2020 | EUGENE CASSIDY |
| Permit Finaled | 10/13/2020 | DEROLD HAUFF |
| CofO Issued | 10/13/2020 | DEROLD HAUFF |
| Permit Finaled | 10/13/2020 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/5/2020 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 3/5/2020 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 3/5/2020 | GABRIEL ROBLES |
| Sewer availability | Cleared | 3/5/2020 | GABRIEL ROBLES |
| Green Code | Cleared | 3/10/2020 | AARON COSTA |
| ZI | Cleared | 3/10/2020 | MIGUEL GAMBOA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adams,, Robert Charles; Lic. No.: C21234 | 22129 BRYANT STREET CANOGA PARK, CA 91304 |
Inspector Information
| JOHN KLARIN, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARTHUR NEGRETE, (310) 732-4558 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/3/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 6/3/2020 | Corrections Issued | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2020 | Not Ready for Inspection | BRIAN CHRISTIAN |
| PLUMBING-Rough | 6/11/2020 | Partial Approval | BRIAN CHRISTIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/15/2020 | Partial Approval | BRIAN CHRISTIAN |
| ELECTRICAL-Rough | 6/25/2020 | Corrections Issued | BRIAN CHRISTIAN |
| HVAC-Rough | 6/25/2020 | Approved | BRIAN CHRISTIAN |
| Insulation | 6/25/2020 | Partial Approval | BRIAN CHRISTIAN |
| PLUMBING-Rough | 6/25/2020 | Corrections Issued | BRIAN CHRISTIAN |
| Underground Mechanical | 6/25/2020 | Approved | BRIAN CHRISTIAN |
| BUILDING-Rough-Frame | 6/30/2020 | Approved | BRIAN CHRISTIAN |
| ELECTRICAL-Rough | 6/30/2020 | Approved | BRIAN CHRISTIAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2020 | Approved | BRIAN CHRISTIAN |
| Green Building Rough | 6/30/2020 | Approved | BRIAN CHRISTIAN |
| Interior/Exterior Lathing | 6/30/2020 | Partial Approval | BRIAN CHRISTIAN |
| PLUMBING-Rough | 6/30/2020 | Approved | BRIAN CHRISTIAN |
| Sewer | 6/30/2020 | Approved | BRIAN CHRISTIAN |
| Insulation | 7/1/2020 | Approved | BRIAN CHRISTIAN |
| Drywall Nailing | 7/8/2020 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 7/8/2020 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 8/24/2020 | Corrections Issued | JOSEPH MCGARRY |
| Final | 8/24/2020 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 8/24/2020 | Approved | JOSEPH MCGARRY |
| HVAC-Final | 8/24/2020 | Corrections Issued | JOSEPH MCGARRY |
| PLUMBING-Final | 8/24/2020 | Corrections Issued | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 8/24/2020 | SGSOV Not Ready | JOSEPH MCGARRY |
| Smoke Detectors | 8/24/2020 | Approved | JOSEPH MCGARRY |
| ELECTRICAL-Final | 9/25/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 9/25/2020 | Corrections Issued | EUGENE CASSIDY |
| HVAC-Final | 9/25/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 9/25/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 9/25/2020 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 9/25/2020 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 10/1/2020 | SGSOV Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 10/7/2020 | Approved | EUGENE CASSIDY |
| Final | 10/7/2020 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 10/7/2020 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 10/7/2020 | Approved | EUGENE CASSIDY |