5922 N JAMIESON AVE 91316
Certificate Information: 5922 N JAMIESON AVE 91316
- Application / Permit
- 19014-20000-05112
- Plan Check / Job No.
- B19VN15818
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 26'-2" X 45'-0" IRREGULAR SHAPE ADDITION TO REAR OF (E) SINGLE FAMILY DWELLING. NEW 10'-11" X 10'-0" ADDITION TO FRONT OF (E) SFD TO EXTEND GARAGE. INTERIOR REMODEL OF (E) KITCHEN AND LIVING ROOM.
- Permit Issued
- Issued on 10/30/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/23/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/17/2019 | ROSENDO MEDINA |
| Corrections Issued | 9/18/2019 | ROSENDO MEDINA |
| Building Plans Picked Up | 9/18/2019 | APPLICANT |
| Plan Check Approved | 10/29/2019 | ROSENDO MEDINA |
| Issued | 10/30/2019 | LADBS |
| CofO in Progress | 4/22/2020 | STEVEN BACK |
| CofO Issued | 4/23/2020 | DONALD SUNSERI |
| Permit Finaled | 4/23/2020 | DONALD SUNSERI |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 10/28/2019 | APEKSHYA BAJRACHARYA |
| Hold | Cleared | 10/28/2019 | LOURDES RAMIRO |
| Low Impact Development | Cleared | 10/28/2019 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 10/28/2019 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 10/28/2019 | APEKSHYA BAJRACHARYA |
| ZI | Cleared | 10/28/2019 | RINA LARA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lampa,, Matthew Micheal; Lic. No.: C73161 | 4606 MARTSMITH WAY FAIR OAKS, CA 95628 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/14/2019 | Partial Approval | STEVEN BACK |
| Footing/Foundation/Slab | 11/20/2019 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 12/6/2019 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 12/6/2019 | Partial Approval | STEVEN BACK |
| Insulation | 12/10/2019 | Corrections Issued | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 12/11/2019 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2020 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 1/27/2020 | Approved | STEVEN BACK |
| Green Building Rough | 1/27/2020 | Approved | STEVEN BACK |
| HVAC-Final | 1/27/2020 | Corrections Issued | STEVEN BACK |
| Interior/Exterior Lathing | 1/27/2020 | Partial Approval | STEVEN BACK |
| Rough-Elec/Plmb/HVAC | 1/27/2020 | Approved | STEVEN BACK |
| HVAC-Rough | 2/3/2020 | Approved | STEVEN BACK |
| Insulation | 2/3/2020 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 2/3/2020 | Approved | STEVEN BACK |
| Shower Pan | 2/3/2020 | Approved | STEVEN BACK |
| Drywall Nailing | 2/7/2020 | Approved | STEVEN BACK |
| Gas Test | 2/7/2020 | Partial Approval | STEVEN BACK |
| HVAC-Rough | 2/7/2020 | Approved | STEVEN BACK |
| Final | 4/13/2020 | Corrections Issued | STEVEN BACK |
| Green Building Final | 4/13/2020 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 4/13/2020 | SGSOV Not Ready | STEVEN BACK |
| Smoke Detectors | 4/13/2020 | Approved | STEVEN BACK |
| Final | 4/15/2020 | Corrections Issued | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 4/15/2020 | SGSOV Approved | STEVEN BACK |
| Final | 4/22/2020 | OK to Issue CofO | STEVEN BACK |