8959 W FOOTHILL BLVD 91040

Certificate Information: 8959 W FOOTHILL BLVD 91040

Application / Permit
19014-20000-05103
Plan Check / Job No.
B19VN15798
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
24'-6" X 18'-4" ADDITION TO & CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER AB 494 & SB 229
Permit Issued
Issued on 6/19/2020
Issuing Office
Valley
Current Status
CofO Issued on 7/3/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/17/2019 APPLICANT
Assigned to Plan Check Engineer 9/17/2019 JEROME MAGAT PALMA
Corrections Issued 9/18/2019 JEROME MAGAT PALMA
Building Plans Picked Up 9/24/2019 APPLICANT
Plan Check Approved 12/17/2019 JEROME MAGAT PALMA
Issued 6/19/2020 LADBS
CofO in Progress 3/17/2021 MATTHEW NELSON
CofO Issued 7/3/2021 MICHAEL SMITH
Permit Finaled 7/3/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 11/18/2019 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 11/18/2019 MARKOS PEREZ-BRAN
Roof/Waste drainage to street Cleared 11/18/2019 MARKOS PEREZ-BRAN
Sewer availability Cleared 11/18/2019 MARKOS PEREZ-BRAN
Grading Pre-Inspection Cleared 12/17/2019 JEROME MAGAT PALMA

Contact Information

Contractor Owner-Builder       ,
Engineer Papazyan,, Andranik; Lic. No.: C56824 635 W COLORADO ST STE 104      GLENDALE, CA 91204

Inspector Information

NICHOLAS TROWBRIDGE, (818) 374-1174 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/29/2020 Corrections Issued MATTHEW NELSON
PLUMBING-Rough 7/29/2020 Partial Inspection MATTHEW NELSON
Special/Order Compliance 7/29/2020 Partial Approval PIERRE VEGA
Excavation/Setback/Form/Re-Bar 8/18/2020 Approved MATTHEW NELSON
Footing/Foundation/Slab 8/18/2020 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 9/24/2020 Approved MATTHEW NELSON
PLUMBING-Rough 9/24/2020 Approved MATTHEW NELSON
ELECTRICAL-Rough 10/1/2020 Approved MATTHEW NELSON
HVAC-Rough 10/1/2020 Approved MATTHEW NELSON
Wood Frame 10/8/2020 Approved MATTHEW NELSON
Insulation 10/16/2020 Approved MATTHEW NELSON
Interior/Exterior Lathing 10/16/2020 Approved MATTHEW NELSON
Drywall Nailing 10/22/2020 Approved MATTHEW NELSON
Interior/Exterior Lathing 11/4/2020 Approved MATTHEW NELSON
Shower Pan 11/4/2020 Approved MATTHEW NELSON
BUILDING-Rough-Frame 2/10/2021 Partial Approval MATTHEW NELSON
ELECTRICAL-Final 2/10/2021 Not Ready for Inspection MATTHEW NELSON
Final 2/10/2021 Not Ready for Inspection MATTHEW NELSON
Green Building Final 2/10/2021 No Access for Inspection MATTHEW NELSON
Green Building Rough 2/10/2021 Not Ready for Inspection MATTHEW NELSON
HVAC-Final 2/10/2021 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Final 2/10/2021 Not Ready for Inspection MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 2/10/2021 SGSOV Not Ready MATTHEW NELSON
Smoke Detectors 2/10/2021 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 2/24/2021 Approved MATTHEW NELSON
ELECTRICAL-Final 2/24/2021 Approved MATTHEW NELSON
Final 2/24/2021 Corrections Issued MATTHEW NELSON
Green Building Final 2/24/2021 Corrections Issued MATTHEW NELSON
Green Building Rough 2/24/2021 Approved MATTHEW NELSON
HVAC-Final 2/24/2021 Corrections Issued MATTHEW NELSON
PLUMBING-Final 2/24/2021 Corrections Issued MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 2/24/2021 SGSOV Not Ready MATTHEW NELSON
Smoke Detectors 2/24/2021 Approved MATTHEW NELSON
Final 3/10/2021 Corrections Issued MATTHEW NELSON
Green Building Final 3/10/2021 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 3/10/2021 SGSOV Approved MATTHEW NELSON
ELECTRICAL-Final 3/16/2021 Approved MATTHEW NELSON
Final 3/16/2021 OK to Issue CofO MATTHEW NELSON
HVAC-Final 3/16/2021 Approved MATTHEW NELSON
PLUMBING-Final 3/16/2021 Approved MATTHEW NELSON