10112 N NOBLE AVE 91345

Certificate Information: 10112 N NOBLE AVE 91345

Application / Permit
19014-20000-05092
Plan Check / Job No.
B19VN15766
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ADD 6' x 20' TO DETACHED GARAGE AND CONVER TO ACCESSORY DWELLING UNIT PER AB 494 AND SB 229. ALL WORKS ARE PER WFPP
Permit Issued
Issued on 6/3/2020
Issuing Office
Valley
Current Status
CofO Issued on 6/12/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/17/2019 APPLICANT
Assigned to Plan Check Engineer 9/17/2019 ALDOUS CHIC
Corrections Issued 9/17/2019 ALDOUS CHIC
Plan Check Approved 5/15/2020 PINANK PATEL
Issued 6/3/2020 LADBS
CofO in Progress 3/1/2021 JENNIFER RABUCHIN
Permit Finaled 6/12/2021 MICHAEL SMITH
CofO Issued 6/12/2021 MICHAEL SMITH
Permit Finaled 6/12/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 9/17/2019 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 9/17/2019 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 9/17/2019 ADRIAN CASTRO
Sewer availability Cleared 9/17/2019 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 7/7/2020 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 7/8/2020 Approved JENNIFER RABUCHIN
PLUMBING-Rough 7/8/2020 Partial Approval JENNIFER RABUCHIN
Pre-Inspection 7/8/2020 Approved JENNIFER RABUCHIN
Rough-Elec/Plmb/HVAC 8/11/2020 Corrections Issued CHRIS CHRISTENSEN
Underground Mechanical 8/11/2020 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 8/13/2020 Partial Inspection PIERRE VEGA
PLUMBING-Rough 8/13/2020 Approved PIERRE VEGA
BUILDING-Rough-Frame 9/25/2020 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 9/25/2020 Not Ready for Inspection JENNIFER RABUCHIN
HVAC-Rough 9/25/2020 Corrections Issued JENNIFER RABUCHIN
Underground Mechanical 9/25/2020 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 10/26/2020 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 10/26/2020 Partial Approval JENNIFER RABUCHIN
HVAC-Rough 10/26/2020 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 11/9/2020 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 11/9/2020 Approved JENNIFER RABUCHIN
Green Building Rough 11/9/2020 Approved JENNIFER RABUCHIN
Insulation 11/17/2020 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 11/17/2020 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 11/23/2020 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 11/23/2020 Approved JENNIFER RABUCHIN
Green Building Final 12/24/2020 Partial Inspection MICHEL ABAJAN
Pre-Inspection 12/24/2020 Partial Approval MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 12/24/2020 SGSOV Not Ready MICHEL ABAJAN
Service/Power Release 12/24/2020 Partial Inspection MICHEL ABAJAN
Smoke Detectors 12/24/2020 Not Ready for Inspection MICHEL ABAJAN
ELECTRICAL-Final 2/2/2021 Corrections Issued JENNIFER RABUCHIN
Final 2/2/2021 Corrections Issued JENNIFER RABUCHIN
Green Building Final 2/2/2021 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 2/2/2021 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 2/2/2021 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 2/2/2021 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 2/2/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 3/1/2021 Approved JENNIFER RABUCHIN
Final 3/1/2021 OK to Issue CofO JENNIFER RABUCHIN
Gas Test 3/1/2021 Approved JENNIFER RABUCHIN
Green Building Final 3/1/2021 Approved JENNIFER RABUCHIN
HVAC-Final 3/1/2021 Approved JENNIFER RABUCHIN
PLUMBING-Final 3/1/2021 Approved JENNIFER RABUCHIN