13717 W LOUVRE ST 91331
Certificate Information: 13717 W LOUVRE ST 91331
- Application / Permit
- 19014-20000-05072
- Plan Check / Job No.
- B19VN15696
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (14'-6"x 1'-6") ADDITION TO RELOCATE & EXPAND KITCHEN, INTERIOR REMODEL TO (E) SINGLE FAMILY DWELLING. WORK PER LA STD WFPP,
- Permit Issued
- Issued on 9/25/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/28/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/16/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/16/2019 | TROY DEGUZMAN |
| Plan Check Approved | 9/16/2019 | TROY DEGUZMAN |
| Issued | 9/25/2019 | LADBS |
| CofO in Progress | 6/27/2022 | MARK BEVELAQUA |
| CofO Issued | 7/28/2022 | DAVID JAMES |
| Permit Finaled | 7/28/2022 | DAVID JAMES |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JACK UPCHURCH, (818) 374-9853 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 1/22/2020 | Not Ready for Inspection | JAMES ABREU |
| ELECTRICAL-Rough | 1/22/2020 | Approved | JAMES ABREU |
| Green Building Rough | 1/22/2020 | Approved | JAMES ABREU |
| HVAC-Rough | 1/22/2020 | Not Ready for Inspection | JAMES ABREU |
| METHANE-Rough | 1/22/2020 | Approved | JAMES ABREU |
| PLUMBING-Rough | 1/22/2020 | Approved | JAMES ABREU |
| BUILDING-Rough-Frame | 2/20/2020 | Partial Inspection | MICHEL ABAJAN |
| Green Building Rough | 2/20/2020 | Partial Inspection | MICHEL ABAJAN |
| Drywall Nailing | 2/24/2020 | Approved | JAMES ABREU |
| Green Building Rough | 2/24/2020 | Approved | JAMES ABREU |
| Interior/Exterior Lathing | 2/24/2020 | Approved | JAMES ABREU |
| Service/Power Release | 2/24/2020 | Approved | JAMES ABREU |
| Final | 5/21/2021 | Corrections Issued | JASON BRANNON |
| BUILDING-Rough-Frame | 6/27/2022 | Approved | MARK BEVELAQUA |
| Final | 6/27/2022 | Conditional Approval | MARK BEVELAQUA |
| Footing/Foundation/Slab | 6/27/2022 | Approved | MARK BEVELAQUA |
| Green Building Final | 6/27/2022 | Approved | MARK BEVELAQUA |
| METHANE-Barrier | 6/27/2022 | Approved | MARK BEVELAQUA |
| METHANE-Subgrade | 6/27/2022 | Approved | MARK BEVELAQUA |
| SGSOV-Seismic Gas S/O Valve | 6/27/2022 | SGSOV Approved | MARK BEVELAQUA |
| Service/Power Release | 6/27/2022 | Conditional Approval | MARK BEVELAQUA |
| Smoke Detectors | 6/27/2022 | Approved | MARK BEVELAQUA |