107 N LUCERNE BLVD 90004
Certificate Information: 107 N LUCERNE BLVD 90004
- Application / Permit
- 19014-20000-05031
- Plan Check / Job No.
- B19VN15540
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD 12' X 14' 5" IRR.-SHAPE PATIO COVER, ADD 2' X 9' 8' TO 1ST STORY, ADD 34' 9" X 30' 3" IRR.-SHAPE 2ND STORY AND ADD 8' 2" X 8' 9" IRR.-SHAPE BALCONY TO (E) SFD. ALL WORK DONE PER STRUCTURAL ENGINEERING.
- Permit Issued
- Issued on 12/2/2019
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 9/26/2019 | GURUNATH NESARAJAH |
| Green Plans Picked Up | 9/26/2019 | APPLICANT |
| Corrections Issued | 9/28/2019 | GURUNATH NESARAJAH |
| Quality Review Completed | 10/2/2019 | GUANG MIN TUNG |
| Building Plans Picked Up | 10/2/2019 | APPLICANT |
| Plan Check Approved | 12/2/2019 | GURUNATH NESARAJAH |
| Issued | 12/2/2019 | LADBS |
| CofO in Progress | 1/30/2023 | RICHARD DOCKUS |
| CofO in Progress | 2/1/2023 | SCOTT FINNILA |
| CofO Issued | 2/9/2023 | DEROLD HAUFF |
| Permit Finaled | 2/9/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Green Code | Cleared | 10/29/2019 | MICHAEL AYERS |
| Low Impact Development | Cleared | 10/30/2019 | ANDRES COVARRUBIAS |
| Eng Process Fee Ord 176,300 | Cleared | 11/6/2019 | MARKOS PEREZ-BRAN |
| HPOZ | Cleared | 11/12/2019 | MAX LODER |
| Miscellaneous | Cleared | 11/12/2019 | MAX LODER |
| Miscellaneous | Cleared | 11/12/2019 | MAX LODER |
| ZI | Cleared | 11/12/2019 | MAX LODER |
| Roof/Waste drainage to street | Cleared | 11/27/2019 | GUILLERMO PETRA |
| Sewer availability | Cleared | 11/27/2019 | GUILLERMO PETRA |
Contact Information
| Contractor | Baron Construction & Remodeling Corp; Lic. No.: 991076-B | 14510 BIG BASIN WAY UNIT B SARATOGA, CA 95070 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/9/2020 | Completed (special insp) | MICHAEL FAUNCE |
| Footing/Foundation/Slab | 1/10/2020 | Partial Approval | ARTHUR SARGSYAN |
| METHANE-Barrier | 1/10/2020 | Partial Approval | ARTHUR SARGSYAN |
| METHANE-Subgrade | 1/10/2020 | Partial Approval | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2020 | Corrections Issued | ARTHUR SARGSYAN |
| Deputy Wood Construction | 2/19/2020 | Approved | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/20/2020 | Partial Approval | ARTHUR SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/6/2020 | Approved | JUSTIN CURTIS |
| ELECTRICAL-Rough | 5/11/2020 | Partial Inspection | ARTHUR SARGSYAN |
| PLUMBING-Rough | 5/11/2020 | Approved | ARTHUR SARGSYAN |
| ELECTRICAL-Rough | 5/15/2020 | Approved | CHRIS CHRISTENSEN |
| Wood Frame | 5/15/2020 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 6/25/2020 | Approved | ARTHUR SARGSYAN |
| Green Building Rough | 6/25/2020 | Approved | ARTHUR SARGSYAN |
| HVAC-Rough | 6/25/2020 | Approved | ARTHUR SARGSYAN |
| METHANE-Rough | 6/25/2020 | Approved | ARTHUR SARGSYAN |
| Shower Pan | 7/14/2020 | Partial Approval | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 8/5/2020 | Approved | ARTHUR SARGSYAN |
| Shower Pan | 8/5/2020 | Approved | ARTHUR SARGSYAN |
| Drywall Nailing | 8/14/2020 | Corrections Issued | THOMAS LOGRASSO |
| Insulation | 8/14/2020 | Approved | THOMAS LOGRASSO |
| Drywall Nailing | 3/15/2022 | Approved | ARTHUR SARGSYAN |
| Final | 3/21/2022 | Corrections Issued | ARTHUR SARGSYAN |
| Footing/Foundation/Slab | 3/21/2022 | Approved | ARTHUR SARGSYAN |
| Green Building Final | 3/21/2022 | Approved | ARTHUR SARGSYAN |
| METHANE-Barrier | 3/21/2022 | Approved | ARTHUR SARGSYAN |
| METHANE-Subgrade | 3/21/2022 | Approved | ARTHUR SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 3/21/2022 | SGSOV Approved | ARTHUR SARGSYAN |
| Smoke Detectors | 3/21/2022 | Approved | ARTHUR SARGSYAN |
| Final | 8/2/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 11/8/2022 | Corrections Issued | MICHAEL LEWIS |
| Final | 1/13/2023 | Partial Inspection | RICHARD DOCKUS |
| Final | 1/27/2023 | OK to Issue CofO | RICHARD DOCKUS |
| Final | 1/31/2023 | OK to Issue CofO | SCOTT FINNILA |