107 N LUCERNE BLVD 90004

Certificate Information: 107 N LUCERNE BLVD 90004

Application / Permit
19014-20000-05031
Plan Check / Job No.
B19VN15540
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD 12' X 14' 5" IRR.-SHAPE PATIO COVER, ADD 2' X 9' 8' TO 1ST STORY, ADD 34' 9" X 30' 3" IRR.-SHAPE 2ND STORY AND ADD 8' 2" X 8' 9" IRR.-SHAPE BALCONY TO (E) SFD. ALL WORK DONE PER STRUCTURAL ENGINEERING.
Permit Issued
Issued on 12/2/2019
Issuing Office
Valley
Current Status
CofO Issued on 2/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/12/2019 APPLICANT
Assigned to Plan Check Engineer 9/26/2019 GURUNATH NESARAJAH
Green Plans Picked Up 9/26/2019 APPLICANT
Corrections Issued 9/28/2019 GURUNATH NESARAJAH
Quality Review Completed 10/2/2019 GUANG MIN TUNG
Building Plans Picked Up 10/2/2019 APPLICANT
Plan Check Approved 12/2/2019 GURUNATH NESARAJAH
Issued 12/2/2019 LADBS
CofO in Progress 1/30/2023 RICHARD DOCKUS
CofO in Progress 2/1/2023 SCOTT FINNILA
CofO Issued 2/9/2023 DEROLD HAUFF
Permit Finaled 2/9/2023 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 10/29/2019 MICHAEL AYERS
Low Impact Development Cleared 10/30/2019 ANDRES COVARRUBIAS
Eng Process Fee Ord 176,300 Cleared 11/6/2019 MARKOS PEREZ-BRAN
HPOZ Cleared 11/12/2019 MAX LODER
Miscellaneous Cleared 11/12/2019 MAX LODER
Miscellaneous Cleared 11/12/2019 MAX LODER
ZI Cleared 11/12/2019 MAX LODER
Roof/Waste drainage to street Cleared 11/27/2019 GUILLERMO PETRA
Sewer availability Cleared 11/27/2019 GUILLERMO PETRA

Contact Information

Contractor Baron Construction & Remodeling Corp; Lic. No.: 991076-B 14510 BIG BASIN WAY UNIT B      SARATOGA, CA 95070
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/9/2020 Completed (special insp) MICHAEL FAUNCE
Footing/Foundation/Slab 1/10/2020 Partial Approval ARTHUR SARGSYAN
METHANE-Barrier 1/10/2020 Partial Approval ARTHUR SARGSYAN
METHANE-Subgrade 1/10/2020 Partial Approval ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 2/14/2020 Corrections Issued ARTHUR SARGSYAN
Deputy Wood Construction 2/19/2020 Approved ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 2/20/2020 Partial Approval ARTHUR SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/6/2020 Approved JUSTIN CURTIS
ELECTRICAL-Rough 5/11/2020 Partial Inspection ARTHUR SARGSYAN
PLUMBING-Rough 5/11/2020 Approved ARTHUR SARGSYAN
ELECTRICAL-Rough 5/15/2020 Approved CHRIS CHRISTENSEN
Wood Frame 5/15/2020 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 6/25/2020 Approved ARTHUR SARGSYAN
Green Building Rough 6/25/2020 Approved ARTHUR SARGSYAN
HVAC-Rough 6/25/2020 Approved ARTHUR SARGSYAN
METHANE-Rough 6/25/2020 Approved ARTHUR SARGSYAN
Shower Pan 7/14/2020 Partial Approval THOMAS LOGRASSO
Interior/Exterior Lathing 8/5/2020 Approved ARTHUR SARGSYAN
Shower Pan 8/5/2020 Approved ARTHUR SARGSYAN
Drywall Nailing 8/14/2020 Corrections Issued THOMAS LOGRASSO
Insulation 8/14/2020 Approved THOMAS LOGRASSO
Drywall Nailing 3/15/2022 Approved ARTHUR SARGSYAN
Final 3/21/2022 Corrections Issued ARTHUR SARGSYAN
Footing/Foundation/Slab 3/21/2022 Approved ARTHUR SARGSYAN
Green Building Final 3/21/2022 Approved ARTHUR SARGSYAN
METHANE-Barrier 3/21/2022 Approved ARTHUR SARGSYAN
METHANE-Subgrade 3/21/2022 Approved ARTHUR SARGSYAN
SGSOV-Seismic Gas S/O Valve 3/21/2022 SGSOV Approved ARTHUR SARGSYAN
Smoke Detectors 3/21/2022 Approved ARTHUR SARGSYAN
Final 8/2/2022 Not Ready for Inspection STUART CHAPMAN
Final 11/8/2022 Corrections Issued MICHAEL LEWIS
Final 1/13/2023 Partial Inspection RICHARD DOCKUS
Final 1/27/2023 OK to Issue CofO RICHARD DOCKUS
Final 1/31/2023 OK to Issue CofO SCOTT FINNILA