5839 N RHODES AVE 91607

Certificate Information: 5839 N RHODES AVE 91607

Application / Permit
19014-20000-05016
Plan Check / Job No.
B19VN15494
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD ( 30'-3"x 58'-2") IRR. SHAPE & MAJOR REMODEL TO (E) ONE STORY SINGLE FAMILY DWELLING. WORK PER ENGINEER.
Permit Issued
Issued on 2/19/2020
Issuing Office
Valley
Current Status
CofO Issued on 2/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/12/2019 APPLICANT
Assigned to Plan Check Engineer 10/3/2019 TROY DEGUZMAN
Corrections Issued 10/7/2019 TROY DEGUZMAN
Quality Review Completed 10/9/2019 CHON CHIO KUO
Building Plans Picked Up 10/15/2019 APPLICANT
Green Plans Picked Up 10/15/2019 APPLICANT
Applicant returned to address corrections 1/2/2020 TROY DEGUZMAN
Plan Check Approved 1/9/2020 TROY DEGUZMAN
Issued 2/19/2020 LADBS
CofO in Progress 1/20/2022 JACK KARGODORIAN
CofO Issued 2/3/2022 MICHAEL SMITH
Permit Finaled 2/3/2022 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/19/2019 MARKOS PEREZ-BRAN
Sewer availability Cleared 12/19/2019 MARKOS PEREZ-BRAN
Green Code Cleared 12/30/2019 MICHAEL AYERS
Hydrant and Access approval Cleared 12/30/2019 JEREMY CARTER
Low Impact Development Cleared 12/30/2019 ORVAL HERNANDEZ-MARCI
Roof/Waste drainage to street Cleared 12/30/2019 ERIK BEASLEY
Grading Pre-Inspection Cleared 1/2/2020 TROY DEGUZMAN

Contact Information

Contractor Owner-Builder       ,
Engineer Warling,, Jeffrey Paul; Lic. No.: C43743 2828 COCHRAN STREET 321      SIMI VALLEY, CA 93065

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/1/2020 Conditional Approval BRENDAN LOONEY
Footing/Foundation/Slab 5/22/2020 Conditional Approval BRENDAN LOONEY
PLUMBING-Rough 6/25/2020 Approved BRENDAN LOONEY
Insulation 7/1/2020 Approved BRENDAN LOONEY
Deputy Drilled-In Anchors 7/9/2020 Conditional Approval BRENDAN LOONEY
Wood Frame 7/15/2020 Partial Approval BRENDAN LOONEY
Deputy Drilled-In Anchors 11/13/2020 Partial Approval MATTHEW NELSON
BUILDING-Rough-Frame 11/16/2020 Partial Approval MATTHEW NELSON
Green Building Rough 11/16/2020 Approved MATTHEW NELSON
ELECTRICAL-Rough 4/19/2021 Approved RICHARD DOCKUS
HVAC-Rough 4/26/2021 Approved RICHARD DOCKUS
PLUMBING-Rough 4/26/2021 Approved RICHARD DOCKUS
Interior/Exterior Lathing 5/25/2021 Partial Approval RICHARD DOCKUS
Insulation 5/28/2021 Approved MORRIS JACKSON
Drywall Nailing 7/1/2021 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 7/7/2021 Partial Approval ARAM AVEDISIAN
Shower Pan 7/7/2021 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 1/3/2022 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 1/3/2022 Approved CHRISTOPHE COCHRAN
Final 1/3/2022 Corrections Issued CHRISTOPHE COCHRAN
Footing/Foundation/Slab 1/3/2022 Approved CHRISTOPHE COCHRAN
Green Building Final 1/3/2022 Not Ready for Inspection CHRISTOPHE COCHRAN
HVAC-Final 1/3/2022 Approved CHRISTOPHE COCHRAN
PLUMBING-Final 1/3/2022 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 1/3/2022 SGSOV Approved CHRISTOPHE COCHRAN
Smoke Detectors 1/3/2022 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 1/18/2022 Approved JACK KARGODORIAN
Final 1/18/2022 OK to Issue CofO JACK KARGODORIAN
Green Building Final 1/18/2022 Approved JACK KARGODORIAN
HVAC-Final 1/18/2022 Approved JACK KARGODORIAN
PLUMBING-Final 1/18/2022 Approved JACK KARGODORIAN